UNIVERSIDADE FEDERAL DE ITAJUBÁ - UNIFEI
INSTITUTO DE MATEMÁTICA E COMPUTAÇÃO
CURSO SISTEMAS DE INFORMAÇÃO
REVISÃO SISTEMÁTICA SOBRE GERENCIAMENTO
DE VALOR AGREGADO
PALOMA CRISTINA PINTO SANTOS
ITAJUBÁ
2018
2
UNIVERSIDADE FEDERAL DE ITAJUBÁ - UNIFEI
INSTITUTO DE MATEMÁTICA E COMPUTAÇÃO
CURSO SISTEMAS DE INFORMAÇÃO
REVISÃO SISTEMÁTICA SOBRE GERENCIAMENTO
DE VALOR AGREGADO
Trabalho Final de Graduação apresentado
ao curso Sistemas de Informação da
Universidade Federal de Itajubá como parte
dos requisitos para a obtenção do título de
Bacharel em Sistemas de Informação.
Orientador: Prof. Dr. Adler Diniz de Souza
ITAJUBÁ
2018
3
SUMÁRIO
1. INTRODUÇÃO ............................................................................................................................. 5
1.1 QUESTÕES DE PESQUISA ........................................................................................... 6
1.1.1 Objetivo .................................................................................................................. 6
1.1.2 Questão Principal ..................................................................................................... 6
1.1.3 Questões Secundárias ................................................................................................ 6
1.1.4 População ................................................................................................................ 7
1.1.5 Resultados ............................................................................................................... 7
2. MÉTODO DE PESQUISA ........................................................................................................... 7
2.1 LEVANTAMENTO E SELEÇÃO DE ESTUDOS – BASES DIGITAIS, PERÍODO E
CRITÉRIOS DE BUSCA ..................................................................................................... 9
2.2 ANÁLISE E SÍNTESE ................................................................................................. 13
2.2.1. Snowballing .......................................................................................................... 17
2.2.2. Classificação de resultados ..................................................................................... 17
3. ANÁLISE DESCRITIVA DOS ARTIGOS ENCONTRADOS .............................................. 18
3.1. DEMONSTRAÇÃO DAS PUBLICAÇÕES ................................................................... 18
3.2. PUBLICAÇÕES SELECIONADAS .............................................................................. 20
4. RESULTADOS ENCONTRADOS ........................................................................................... 22
4.1. ESTABILIDADE DO ÍNDICE DE DESEMPENHO DE CUSTO (CPI) E DO ÍNDICE DE
DESEMPENHO DE PRAZO (SPI) ...................................................................................... 23
4.2. PROPOSTAS DE NOVAS TÉCNICAS DE MONITORAMENTO DE PROJETOS ........... 23
4.2.1 Modelo Bayesiano .................................................................................................. 24
4.2.2 Métodos de Inteligência Artificial ............................................................................. 24
4.3. PROPOSTAS DE MELHORIAS NA TRADICIONAL TÉCNICA DE GERENCIAMENTO
DE VALOR AGREGADO (EVM) ...................................................................................... 25
4.3.1 Métodos Estatísticos ............................................................................................... 25
4.3.1.1 Números Fuzzy ................................................................................................ 25
4.3.1.2 Curvas Sigmodais............................................................................................. 26
4.3.2 Dados Históricos de Custo ....................................................................................... 26
4.3.3 Indicadores de Desempenho de Qualidade ................................................................. 26
4.3.4 Análise de Risco ..................................................................................................... 27
5. PERSPECTIVAS PARA NOVOS ESTUDOS ......................................................................... 27
6. CONCLUSÃO ............................................................................................................................. 28
REFERÊNCIAS .................................................................................................................................. 29
ANEXOS .............................................................................................................................................. 34
ANEXO 1 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA NA
BASE DIGITAL SCOPUS ................................................................................................ 35
ANEXO 2 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA NA
BASE DIGITAL COMPENDEX....................................................................................... 37
ANEXO 3 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA NA
BASE DIGITAL IEEE ..................................................................................................... 39
ANEXO 4 - PUBLICAÇÕES SELECIONADAS ATRAVÉS DA STRING DE BUSCA E DA
APLICAÇÃO DOS FILTROS, SEM A TÉCNICA DE SNOWBALLING .......................... 42
APÊNDICES ....................................................................................................................................... 44
APÊNDICE A – RESUMOS DAS PUBLICAÇÕES SELECIONADAS .............................. 45
4
Resumo
O Gerenciamento de Valor Agregado (GVA) é uma técnica muito utilizada em gestão de projetos, cuja
aplicação proporciona a integração de escopo, cronogramas e recursos a fim de obter cálculos e respostas
quanto aos custos e o desempenho do projeto até a sua conclusão. Esta monografia apresenta um estudo
secundário, realizado através de referências bibliográficas que discutem sobre a estabilidade de índices de
custo e de prazo, alguns problemas encontrados na técnica de gerenciamento de valor agregado e que também
demonstram propostas comprovadas e validadas de melhorias identificadas. Primeiramente, foram definidos
critérios de busca, de inclusão e exclusão de artigos relevantes à este trabalho e como resultado dessa revisão
sistemática, serão apresentados estudos que demonstram propostas alternativas de gerenciamento de projetos,
como a utilização de métodos de inteligência artificial e do método Bayesiano, e propostas de melhorias na
própria técnica de gerenciamento de valor agregado, como a integração de alguns métodos – dados e cálculos
estatísticos, índices de qualidade, dados históricos de custo, análise de risco - com o EVM. Sendo assim, após
todos os estudos feitos para a composição desta revisão sistemática, algumas perspectivas para novos estudos
foram definidas.
Palavras-chave: Revisão sistemática; Gerenciamento de projetos; Gerenciamento de valor agregado.
Abstract
The Earned Value Management (EVM) is a technique widely used in project management, whose application
provides the integration of scope, schedules and resources in order to obtain calculations and answers
regarding costs and the performance of the project until its conclusion. This monography presents a secondary
study, carried out through bibliographical references that discuss the stability of cost and term indices, some
problems encountered in the technique of earned value management and also demonstrate proven and validated
proposals for identified improvements. First, search, inclusion and exclusion criteria of articles relevant to this
work were defined and as a result of this systematic review, studies will be presented that demonstrate
alternative project management proposals, such as the use of artificial intelligence and Bayesian methods, and
proposals for improvements in the earned value management technique, such as the integration of some
methods - statistical data and calculations, quality indexes, historical cost data, risk analysis - with EVM. So,
after all the studies made for the composition of this systematic review, some prospects for new studies have
been defined.
Keywords: Systematic review; Project management; Earned value management.
5
1. INTRODUÇÃO
De acordo com o Project Management Institute (PMI), a profissão dedicada ao
gerenciamento de projetos tem se formalizado e emergido cada vez mais desde meados do
século XX. Esse gerenciamento é caracterizado pelo estudo de todas as fases do projeto,
desde a definição dos objetivos e dos recursos a serem utilizados, até a fase final de teste,
correção e implementação dele.
A prática de gerenciamento de projetos agrega valor aos resultados finais do projeto
pelo fato de: (i) permitir que esse gerenciamento possa acontecer em empresas de pequeno,
médio e grande porte; (ii) quando utilizada, pode evitar eventuais surpresas ao longo do
projeto; (iii) possibilita que a empresa se desenvolva ainda mais com novas técnicas e
diferenciais competitivos; (iv) apoia e facilita a tomada de decisões. (VARGAS, 2014).
Atualmente, existem diversas técnicas para apoiar a prática de gerenciamento de
projetos utilizando como base o escopo, os custos e os prazos. A mais confiável delas é a
técnica de Gerenciamento de Valor Agregado (Earned Value Management - EVM). (LIPKE,
2006a).
A técnica citada acima possibilita o controle de todo o processo de execução do
projeto, proporcionando um planejamento de custos e de tempo ainda em sua fase inicial.
Caso esse planejamento vá se distanciando da realidade de acordo com o avanço do projeto, a
utilização dessa técnica torna possível a identificação do desvio e o replanejamento das
atividades, facilitando que os profissionais envolvidos apliquem as devidas correções, a fim
de atingir o resultado esperado. (ANBARI, 2003).
A técnica de Gerenciamento de Valor Agregado propõe uma gestão de projetos
eficiente por meio do planejamento, da avaliação de riscos, da organização e da emissão de
relatórios de desempenho do projeto, facilitando que o seu resultado final seja de sucesso e
de acordo com o planejado. Algumas fórmulas matemáticas foram propostas, no estudo da
técnica de EVM, para auxiliar a quantificar os custos de um determinado projeto,
considerando-se os seus prazos e recursos. (LIPKE, 2006a).
Ainda segundo (LIPKE, 2006a), a prática de gerenciamento de projetos passa a ser
tratada como uma ciência; e como toda ciência, para que ela apresente resultados confiáveis e
satisfatórios, torna-se necessário fazer uso dos números e das fórmulas em seus estudos, para
que ela possa ser considerada uma gestão científica.
Sendo assim, essa pesquisa científica apresenta estudos que propõem novos métodos
para a prática de gerenciamento de projetos e/ou medidas derivadas da técnica de
6
Gerenciamento de Valor Agregado a fim de sugerir uma melhoria nela. Essas referências
utilizam variáveis do EVM para a base de sua proposta. Entre essas variáveis, encontram-se:
(i) Variação de Prazos (VPR): mede o desempenho do cronograma em seu projeto; (ii)
Variação de Custo (VC): mede o desempenho dos custos de um projeto; (iii) Indicador de
Desempenho de Prazo (IDP): mede o progresso real comparado ao progresso planejado; (iv)
Indicador de Desempenho de Custo (IDC): mede o trabalho executado comparado ao custo
real do projeto. (PMI, 2011; PMI, 2013)
Contudo, muitos estudos questionam a confiabilidade do uso do Indicador de
Desempenho de Custo (IDC) nos estudos da técnica de EVM a fim de calcular o custo
estimado de um determinado projeto. Esses questionamentos se fazem presentes em estudos
realizados por (CHRISTENSEN et al., 1993; ZWIKAEL, 2000; LIPKE, 2006a e
HENDERSON e ZWIKAEL, 2008, SOUZA e. al. 2014).
O problema relacionado à utilização do Indicador de Desempenho de Custo (IDC) se
caracteriza pela sua variação durante a execução dos projetos. Caso um determinado projeto
apresente uma variação significativa entre os custos reais e o IDC planejado, os profissionais
envolvidos nessa área da gestão apresentarão dificuldades em corrigir o indicador, devido à
sua projeção pouco confiável. (SOUZA, 2014).
1.1 QUESTÕES DE PESQUISA
1.1.1 Objetivo
Essa revisão sistemática tem como objetivo reunir referências bibliográficas do
contexto acadêmico ou industrial que estudam e discutem sobre a estabilidade dos índices de
custo e de cronograma utilizados nas fórmulas da técnica de Gerenciamento de Valor
Agregado e que propõem maneiras alternativas de gerenciamento de projetos ou uma
melhoria nas limitações apresentadas pelo EVM.
1.1.2 Questão Principal
A inserção de variáveis de qualidade na técnica de EVM compensa os problemas
encontrados nela e pode ser considerada a melhor opção de solução para esses problemas?
1.1.3 Questões Secundárias
-Quais são as outras soluções propostas nos artigos relevantes?
-Os autores têm focado mais em novas técnicas ou em melhorias na técnica
tradicional?
7
-Quais referências selecionadas discutem sobre o aumento da estabilidade de
indicadores de custo para a melhoria da técnica de EVM?
1.1.4 População
Serão considerados artigos publicados em conferências ou jornais que discutam sobre
os problemas contidos na técnica de gerenciamento de valor agregado e que propõem
melhorias na técnica ou novos métodos de monitoramento, controle e previsão de índices do
projeto; essas propostas devem ter sido testadas e validadas por meio de casos reais ou dados
simulados.
1.1.5 Resultados
Os resultados dessa pesquisa demonstrarão os estudos que focam na eficiência da
inserção de variáveis de qualidade na técnica de EVM para superar suas desvantagens e
também estudos com outras possíveis soluções para os problemas dessa técnica. Além disso,
perspectivas para novos estudos serão definidas, embasadas por meio do desenvolvimento
desta pesquisa e da análise dos resultados encontrados.
2. MÉTODO DE PESQUISA
Uma revisão sistemática da literatura (SRL) é um método de estudo secundário que
deve seguir padrões e normas pré-estabelecidas antes de dar início ao trabalho de pesquisa a
ser realizado, tendo como fundamento uma visão transparente, precisa e explícita. (Tranfield
et al., 2003; Kitchenham and Charters, 2007).
Segundo Denyer e Tranfield (2009), uma revisão sistemática é composta por cinco
fases principais, sendo elas: (i) definição das questões a serem respondidas pelo estudo da
Revisão Sistemática de Literatura (RSL); (ii) métodos de localização de publicações em
potencial; (iii) estudo e seleção/exclusão dessas publicações através de filtros pré-
determinados; (iv) análise e síntese daquelas realmente consideradas relevantes após a
aplicação dos filtros; (v) utilização e documentação dos resultados encontrados.
A Tabela 1 evidencia e demonstra cada fase de pesquisa necessária para as atividades
de obtenção, análise e discussão de referências relevantes a este estudo. Num primeiro
momento, as palavras-chave foram definidas a fim de iniciar a pesquisa através dos engenhos
de busca que também foram definidos juntamente com o período de tempo a ser considerado.
Logo após a obtenção do primeiro resultado da pesquisa realizada, alguns filtros de inclusão
e exclusão foram aplicados aos artigos e foram mantidos apenas os itens mais relevantes.
8
O protocolo utilizado para o estudo foi derivado dos trabalhos produzidos por
(MAFRA et al., 2006) e (SILVA, 2004) e será detalhado na próxima seção.
Como pode ser observado na Tabela 1, na fase inicial de definição de métodos de
busca, a tese “Uma Proposta Para Melhoria da Previsibilidade de Custo de Projetos,
Utilizando a Técnica de Gerenciamento de Valor Agregado e Dados Históricos de Custo e
Qualidade” de (Souza, 2014) é apresentada como ferramenta por ter sido utilizada como base
fundamental para as definições da string de busca deste estudo e dos critérios de inclusão e
exclusão de referências. A utilização dessa tese foi essencial ao desenvolvimento do trabalho
e será explanada mais à frente.
A tabela de detalhamento de cada etapa da pesquisa que está exposta abaixo foi uma
adaptação inspirada no fluxograma contido no artigo “Lean and green - a systematic review
of the state of the art literature” de (REYES, 2015) para descrever as fases do seu estudo de
revisão sistemática. Essa tabela tem a função de especificar o passo-a-passo fundamental
para a confecção deste estudo.
Tabela 1: Detalhamento das etapas da revisão sistemática realizada.
OBJETIVO
MÉTODO
FERRAMENTA
SEÇÃO
NO
ARTIGO
Definição dos
métodos de busca,
inclusão e exclusão
de referências
Definir as palavras chave e os
critérios de inclusão e
exclusão.
“Uma Proposta Para
Melhoria da Previsibilidade
de Custo de Projetos,
Utilizando a Técnica de
Gerenciamento de Valor
Agregado e Dados
Históricos de Custo e
Qualidade” (SOUZA, 2014)
2.1
Procura de
referências
relevantes
Buscar, selecionar e capturar
referências relevantes.
- Utilização de bases
acadêmicas digitais;
- Definição/aplicação do
período de busca;
- Utilização das tags de
busca.
- Bases digitais;
- Palavras-chave.
2.2
Seleção de
referências
relevantes
Aplicar os filtros de inclusão
e exclusão sobre o resultado
da busca.
Aplicação dos filtros de
inclusão e exclusão.
- Critérios de inclusão;
- Critérios de exclusão.
2.2
Busca de novos
artigos relevantes
Encontrar mais artigos
relevantes que não foram
retornados na primeira busca.
Snowballing. Referências anteriormente
selecionadas.
2.2.1
9
Análise e resumo
dos artigos
selecionados
Analisar e resumir os artigos
que passaram pelos filtros e
permaneceram na pesquisa.
Seleção de um método
padrão para síntese dos
artigos.
Todas as referências
selecionadas.
Anexos
Exposição dos
resultados
Discutir e apresentar os
resultados encontrados.
Definição de categorias de
estudos.
4.
Fonte: Autor.
2.1 LEVANTAMENTO E SELEÇÃO DE ESTUDOS – BASES DIGITAIS,
PERÍODO E CRITÉRIOS DE BUSCA
Com o objetivo de levantar estudos para compor a revisão sistemática, foram
consideradas, primeiramente, bases de dados digitais, sendo os engenhos de busca dessas
bases a ferramenta utilizada para a procura dos arquivos relevantes ao estudo. Com a
necessidade de confiabilidade das bases digitais, aquelas que foram consideradas na pesquisa
são a biblioteca do site SCOPUS (http://www.scopus.com/home.url), da Compendex
(http://www.engineeringvillage.com/) e também a biblioteca do site do IEEE
(http://www.ieee.org/portal/site).
Foram consideradas as publicações relevantes em um determinado idioma, que é o
inglês, devido à sua adoção pela maioria das conferências e periódicos internacionais sobre o
tema de pesquisa.
Essa revisão sistemática analisou dados disponíveis nas fontes considerando o
período de 01 de janeiro de 2011 até 31 de dezembro de 2017 com o intuito de complementar
a revisão sistemática apresentada no estudo de (Souza, 2014), que considerou a busca por
estudos até setembro de 2010.
Os critérios de busca utilizados nessa revisão estão especificados abaixo e foram
retirados da Tese de Doutorado “Uma Proposta Para Melhoria Da Previsibilidade De Custo
De Projetos, Utilizando a Técnica De Gerenciamento De Valor Agregado e Dados Históricos
De Custo e Qualidade” apresentada ao Programa de Pós-Graduação em Engenharia de
Sistemas e Computação, COPPE, da Universidade Federal do Rio de Janeiro, como parte dos
requisitos necessários à obtenção do título de Doutor em Engenharia de Sistemas e
Computação por Adler Diniz de Souza, tendo como orientadora a Doutora em Informática
Ana Regina Cavalcanti Rocha.
Como primeiro critério de busca, foi definida a string necessária para a procura por
todas as publicações em dados de bases digitais. Ela é composta por um conjunto de
palavras-chave que são relevantes ao estudo, para que a procura possa ser feita através do
10
mesmo. Ela é uma adaptação e atualização da string criada e utilizada por (Souza, 2014) em
sua revisão sistemática. Essa atualização foi necessária a fim de diminuir o grande número de
falsos positivos atualmente encontrados na aplicação da antiga string. Sendo assim, a string
atualizada que será considerada neste estudo pode ser denotada da seguinte maneira: “EVM
OR "earned value" OR "earned value technique" OR "earned value method" OR "earned
value metric" OR "earned value calculation" OR "earned value methodology" OR "earned
value management" AND "cost performance index" OR "schedule performance index"”.
Após essa busca, foram aplicados alguns critérios de inclusão e exclusão, retirados na
íntegra da tese de (Souza, 2014), pois apenas o fato da expressão de busca estar presente na
publicação não garante que ela seja aplicável ao caso desta revisão.
O primeiro filtro trata-se então da seleção dos estudos que se encaixam nos critérios
mencionados a seguir; essa seleção é realizada por meio da leitura de seus resumos
(abstracts).
Considerando-se os critérios de exclusão definidos por Souza (2014), foram excluídas
as publicações que se encaixaram nos seguintes tópicos:
• CE1-01 - Não serão selecionadas publicações em que as palavras chave não estão
presentes na publicação e não há variações destas palavras chave (exceto plural).
● CE1-02 - Não serão selecionadas publicações em que as palavras chave da busca não
apareçam no título, resumo e/ou texto da publicação (exclui-se daí o campo ‘palavras
chave’, as seções agradecimentos, biografia dos autores, referências bibliográficas e
anexos).
● CE1-03 - Não serão selecionadas publicações que descrevam e/ou apresentem
“keynote speeches”, tutoriais, cursos, workshops e similares.
● CE1-04 - Não serão selecionadas publicações em que a sigla EVM não signifique
"earned value management".
● CE1-05 - Não serão selecionadas publicações em que a sigla CPI não signifique "cost
performance index".
● CE1-06 - Não serão selecionadas publicações em que a sigla SPI não signifique
"schedule performance index".
● CE1-07 - Não serão selecionadas publicações em que a sigla EAC não signifique
"estimated at completion".
● CE1-08 - Não serão selecionadas publicações em que a sigla TAC não signifique
"time at completion".
11
● CE1-09 - Não serão selecionadas publicações em que a sigla TCPI não signifique "to
cost performance index".
● CE1-10 - Não serão selecionadas publicações que apresentem ferramentas de apoio a
análise de valor agregado.
● CE1-11 - Não serão selecionadas publicações que mostrem a aderência de
determinada abordagem de gerência de projetos a análise de valor agregado.
● CE1-12 - Não serão selecionadas publicações que descrevem melhorias nas técnicas
de análise de valor agregado, mas não apresentem subsídios que permitam identificar
se foi aplicada ou simulada.
● CE1-13 - Não serão selecionadas publicações que descrevem o uso de técnicas de
análise de valor agregado, como forma de controle de projetos, ou sub processos de
domínios específicos.
● CE1-14 – Não serão selecionadas publicações que simplesmente citem a análise de
valor agregado como uma técnica de monitoramento e controle, ou que expliquem
como utilizá-la como uma técnica de monitoramento e controle.
Considerando-se os critérios de inclusão definidos por Souza (2014), foram incluídas
as publicações que se encaixaram nos seguintes tópicos:
● CI1-01 – Podem ser selecionadas publicações que mencionam a técnica de análise de
valor agregado.
● CI1-02 – Podem ser selecionadas publicações que descrevam novas técnicas de
controle de custo e prazo.
● CI1-03 – Podem ser selecionadas publicações que discutam a estabilidade dos
indicadores de desempenho de prazo e custo.
● CI1-04 – Podem ser selecionadas publicações que descrevam evoluções (extensões)
da técnica de análise de valor agregado (sem mencionar melhoria da previsibilidade
dos indicadores EAC e TAC).
● CI1-05 – Podem ser selecionadas publicações que descrevam propostas de variação
(extensões) da técnica de análise de valor agregado, visando melhorar a
previsibilidade do EAC e TAC.
● CI1-06 – Podem ser selecionadas publicações que apontem os problemas mais
comuns da análise de valor agregado.
12
● CI1-07 – Podem ser selecionadas publicações que apresentem métodos estatísticos ou
de controle estatístico de processo, aplicados á análise de valor agregado.
● CI1-08 – Podem ser selecionadas publicações que comparem a análise de valor
agregado tradicional com novas técnicas.
● CI1-09 – Podem ser selecionadas publicações que adicionem novas variáveis a
análise de valor agregado, visando melhorar a previsibilidade do EAC e TAC.
As publicações já estavam mais refinadas nessa etapa do processo, porém, não se
deve considerar que todas elas seriam eficazes a esse estudo. Sendo assim, um segundo filtro
foi aplicado, seguindo os seguintes critérios (SOUZA, 2014):
• CS2 -EVM - NovTec –Uso - Não devem ser selecionadas publicações que não
utilizem a técnica de análise de valor agregado ou uma nova técnica e que não deem
indícios de que foi utilizada uma nova técnica de análise de valor agregado na
prática ou através de simulações.
● CS2 -EVM -NovTec +Uso - Não devem ser selecionadas publicações que descrevem
o uso de uma técnica para controle de custo e prazo, mas não apresentem indícios que
essa técnica é nova.
● CS2 -EVM +NovTec -Uso - Não devem ser selecionadas publicações que descrevem
uma nova técnica para controle de custo e prazo, mas não apresentem indícios que a
nova técnica foi utilizada na prática ou através de simulações.
● CS2 +EVM -NovTec +Uso - Não devem ser selecionadas publicações que descrevem
o uso da análise de valor agregado, mas não apresentem uma nova técnica.
● CS2 +EVM -NovTec -Uso - Não devem ser selecionadas publicações que descrevem
o uso da análise de valor agregado, mas não apresentem uma nova técnica e não
apresentam o seu uso prático ou através de simulações.
● CS2 +EVM +NovTec -Uso - Não devem ser selecionadas publicações que descrevem
o uso da análise de valor agregado, descrevem uma nova técnica de análise de valor
agregado, mas não apresentam o seu uso prático ou através de simulações.
Dessa forma, de acordo com Souza (2014), todas as publicações que foram mantidas
respeitam os critérios abaixo:
● CI2 +EVM +NovTec +Uso - Podem ser selecionadas publicações que descrevam a
utilização da análise de valor agregado, descrevam a utilização de novas técnicas de
13
controle de custos e prazos e dê indícios que as novas técnicas são reais e que foram
utilizadas na prática ou através de simulações.
● CI2 -EVM +NovTec +Uso - Podem ser selecionadas publicações que não descrevam
a utilização da análise de valor agregado, mas que descrevam a utilização de novas
técnicas de controle de custos e prazos e dê indícios que as novas técnicas são reais e
que foram utilizadas na prática ou através de simulações.
Foram consideradas ainda as publicações que:
● Sejam citadas nas referências bibliográficas e forem considerados relevantes apesar
de não terem sido identificados pelas palavras chave do estudo.
2.2 ANÁLISE E SÍNTESE
Depois de definir as expressões de busca e os critérios de inclusão e de exclusão do
primeiro e do segundo filtro, alguns engenhos de busca foram utilizados para que os artigos
relevantes a este estudo pudessem ser encontrados e acessados.
Como pode ser observado abaixo, a partir do site SCOPUS, foram retornados 30
artigos de acordo com a expressão de busca utilizada (Anexo 1); enquanto que no site da
Compendex, 24 artigos foram encontrados (Anexo 2). Por fim, no site do IEEE, 39 artigos
compuseram o primeiro resultado da busca realizada (Anexo 3).
Nota-se que alguns artigos foram encontrados nas 3 plataformas de busca
simultaneamente (Figura 1), fazendo com que o número total de publicações que resultaram
da utilização do primeiro critério se igualasse a 70. As porcentagens referentes a esses
resultados podem ser observadas na Figura 2.
Figura 1: Número de artigos resultantes da busca, separadamente e simultaneamente em
cada base digital.
Fonte: Autor.
14
Figura 2: Porcentagem de publicações encontradas em cada base digital como resultado das
buscas.
32%
42%
26%Compendex
IEEE
Scopus
Fonte: Autor.
De acordo com os critérios de busca definidos por Souza (2014) já citados
anteriormente, todas as 70 publicações foram analisadas por meio de seus resumos
(abstracts) e a grande maioria delas se tratava de um falso-positivo em relação ao objetivo
dessa revisão sistemática. Através disso, foram aplicados os critérios de inclusão e exclusão,
compondo o primeiro filtro do estudo.
A grande maioria das publicações consideradas como um “falso-positivo” tratava-se
de artigos que apenas demonstravam e exemplificavam a técnica de Gerenciamento de Valor
Agregado e também aquelas publicações que a utilizavam aplicando em um determinado
contexto para justificar a necessidade e as vantagens da prática de gerenciamento de projetos;
porém, nenhuma proposta de melhoria para a técnica de gerenciamento de valor agregado era
estudada e/ou demonstrada nesses artigos.
Um outro caso de “falso-positivo” bastante encontrado nesse primeiro resultado da
busca foi a questão de algumas publicações apresentarem um estudo que propõe uma
melhoria da técnica de EVM ou até mesmo uma integração dela com outros métodos, porém,
sem nenhum teste ou simulação que comprove que a proposta foi testada e validada.
Sendo assim, depois de aplicado o primeiro filtro, os números de publicações
selecionadas de cada base digital diminuíram significativamente refinando as buscas. O site
Scopus passou a apresentar 15 publicações relevantes a esse estudo, enquanto que o site
Compendex, apresentou 10 publicações e o site do IEEE apresentou 5. Dessa forma, 19
artigos compõem essa fase da revisão sistemática (Figura 3). As porcentagens referentes a
esses resultados podem ser observadas na Figura 4.
15
Figura 3: Número de artigos resultantes da aplicação do primeiro filtro do estudo,
separadamente e simultaneamente, em cada base digital.
Fonte: Autor.
Figura 4: Porcentagem de publicações selecionadas em cada base digital após a aplicação do
primeiro filtro.
33%
17%
50% Compendex
IEEE
Scopus
Fonte: Autor.
Após a aplicação do primeiro filtro, as publicações encontravam-se mais refinadas e
objetivas. Porém, nem todas elas poderiam ser consideradas efetivamente relevantes a este
estudo, pois não comprovavam de fato, por meio de testes e/ou simulações, a técnica ou
melhoria da técnica que foram propostas. Sendo assim, os critérios de inclusão e exclusão
que formam o segundo filtro, definidos por Souza (2014) e citados acima, foram utilizados
para poder refinar ainda mais o resultado dessa busca por artigos relevantes.
Dessa maneira, o número de referências que foram mantidas e consideradas nessa
revisão sistemática se reduziu um pouco mais a fim de tornar este estudo mais específico e
eficiente. Passando a fase de análise dos resultados obtidos na busca realizada, 10 artigos
compõem o grupo de publicações que serão estudadas, analisadas, resumidas e demonstradas
16
nessa revisão sistemática (Anexo 4). A base digital da Scopus é a que está mais presente
nessa fase final, com 7 artigos considerados para a pesquisa. Em seguida, Compendex com 5
artigos; e por fim, o site do IEEE com 4 artigos selecionados nessa última etapa (Figura 5).
Algumas referências que aparentemente se encaixavam nessa pesquisa acabaram
sendo excluídas após a aplicação do segundo filtro por não apresentar uma melhoria na
técnica de EVM e nem uma nova técnica para o gerenciamento de projetos; outras ainda
foram excluídas por não apresentarem simulações ou aplicações para a validação da técnica
proposta.
Alguns artigos que também foram excluídos nessa fase discutiam sobre a estabilidade
dos indicadores de custo e de cronograma e pareciam apresentar estudos promissores, porém,
não apresentavam uma proposta de melhoria para as desvantagens apresentadas.
Sendo assim, dentre aqueles artigos que foram selecionados, a grande maioria deles
propõe uma melhoria na técnica tradicional de Gerenciamento de Valor Agregado (EVM).
Figura 5: Número de artigos resultantes da aplicação do segundo filtro do estudo,
separadamente e simultaneamente, em cada base digital.
Fonte: Autor.
Figura 6: Porcentagem de publicações selecionadas em cada base digital após a aplicação do
segundo filtro.
25%
44%31%
Compendex
IEEE
Scopus
Fonte: Autor.
17
2.2.1. Snowballing
Neste momento da pesquisa, novos artigos relevantes foram procurados, analisados e
escolhidos, a fim de aumentar a gama de novos métodos utilizados para o gerenciamento de
projetos ou propostas de melhorias pra o EVM. Para isto, utilizou-se a técnica de
Snowballing, que se trata da procura de estudos por meio das referências de artigos
relevantes já encontrados (Goodman, 1961).
Dessa maneira, mais 5 estudos foram adicionados aos resultados finais da pesquisa
realizada até aqui. Eles foram escolhidos por apresentarem novas técnicas de gerenciamento
de projetos que ainda não tinham sido mencionados no primeiro grupo de artigos
selecionados ou que já haviam sido mencionados, mas também apresentavam uma melhoria
promissora à técnica tradicional.
2.2.2. Classificação de resultados
Por fim, após a aplicação dos dois filtros definidos por Souza (2014) no resultado da
busca realizada por meio das strings e após a utilização da técnica de snowballing, os 15
artigos selecionados e relevantes a este estudo serão divididos em três categorias para estudo:
(I) Estabilidade dos indicadores de Desempenho de Custo (CPI) e/ou de prazo (SPI); (II)
Propostas de novas técnicas para o gerenciamento e controle de projetos; (III) Propostas de
melhorias para a tradicional técnica de Gerenciamento de Valor Agregado.
Das 15 referências selecionadas para essa revisão sistemática, pode-se considerar que
2 delas pertencem à primeira categoria por apresentarem estudos que discutem sobre a
estabilidade do CPI e/ou do SPI, enquanto que 4 publicações pertencem à segunda categoria
por apresentarem uma técnica inovadora para a prática de gerenciamento de projetos e 11
publicações pertencem à terceira categoria por apresentarem e validarem em seu estudo uma
melhoria à técnica de EVM, como pode ser visualizado no gráfico abaixo (Figura 7).
É interessante ressaltar aqui que uma categoria não exclui a possibilidade de que a
outra aconteça. Um artigo que apesenta uma nova técnica alternativa para o gerenciamento
de projetos pode ter demonstrado e defendido discussões sobre a estabilidade de indicadores
de custo e de cronograma em seu estudo, por exemplo. Enquanto que, ao mesmo tempo, uma
referência encontrada que propõe uma melhoria no EVM também pode apresentar a
discussão sobre os índices citados.
18
Figura 7: Demonstração da quantidade de referências por categorias.
0
2
4
6
8
10
12
14
I II III
I
II
III
Fonte: Autor.
3. ANÁLISE DESCRITIVA DOS ARTIGOS ENCONTRADOS
3.1. DEMONSTRAÇÃO DAS PUBLICAÇÕES
Aqui as 15 publicações que foram selecionadas para serem tratadas nessa revisão
sistemática serão apresentadas de diferentes formas, como pode ser visto nas figuras abaixo.
Elas são referenciadas de acordo com o seu índice da tabela apresentada na seção 3.2.1 e de
acordo com o índice das Referências deste artigo. Primeiramente, as publicações estão
divididas por ano em que foram publicadas (Figura 8).
Figura 8: Número de artigos estudados nessa revisão, por ano de publicação.
0 1 2 3 4
2017
2016
2015
2014
2013
2012
2011
Número deartigos
Fonte: Autor.
19
Nesse momento, as referências são demonstradas de acordo com o local onde elas
foram publicadas e apresentadas (Figura 9), bem como cada jornal ou revista (Tabela 2) e
cada conferência (Tabela 3).
Na Figura 9 está detalhado quantas referências foram publicadas em Conferências e
quantas foram publicadas em Jornais e Revistas. Pode-se observar que 11 artigos foram
publicados em jornais ou revistas, enquanto 4 foram publicados em conferências. Este
número se dá pelo fato de um único artigo (4) ter sido publicado em algum jornal e
conferência também. Já um outro artigo (11) foi publicado em duas conferências distintas.
Figura 9: Demonstração da quantidade de referências publicadas em Jornais e Revistas e em
Conferências.
73%
27%Conferências
Jornais e Revistas
Fonte: Autor.
Na Tabela 2, a demonstração de cada Jornal que aparece nos resultados dessa revisão
está detalhada com os índices de cada artigo que faz parte de seu respectivo acervo de
publicações selecionadas.
Tabela 2: Demonstração das referências publicadas em Jornais.
Jornal Índices de
publicações
International Journal of Project Management [1]; [14]
Journal of the Operational Research Society [2]
European Journal of Operational Research [3]
International Journal of Software Engineering and Knowledge Engineering [4]
Communications in Computer and Information Science [5]; [7]
Journal of Intelligent and Fuzzy Systems [8]
Revista de Metodos Cuantitativos para la Economia y la Empresa [9]
20
International Journal of Networking and Virtual Organizations [10]
IEEE Transactions on Engineering Management [12]
Procedia Computer Science [15]
Fonte: Autor.
Da mesma maneira como foram detalhados os Jornais, aqui são detalhadas as
Conferências que apresentam artigos relevantes a esse estudo. A quantidade de publicações
que foram encontradas em cada uma dessas Conferências pode ser visualizada na Tabela 3.
Tabela 3: Demonstração das referências publicadas em Conferências.
Conferência Índices de
publicações
Proceedings of the International Conference on Software Engineering and Knowledge
Engineering, SEKE
[4]
Proceedings - International Conference on Software Engineering [6]
2011 Joint Conference of the 21st International Workshop on Software Measurement [11]
6th International Conference on Software Process and Product Measurement [11]
2012 International Conference on Information Management, Innovation Management and
Industrial Engineering
[14]
Fonte: Autor.
3.2. PUBLICAÇÕES SELECIONADAS
Nessa seção, finalmente, são demonstradas as 15 publicações que retornaram das
pesquisas por meio das strings de busca definidas por Souza (2014) que passaram pelo
primeiro e segundo filtro, também definidos por ele, e também aquelas que são provenientes
da aplicação da técnica de snowballing. Juntamente com cada artigo abaixo, é possível notar
também quem são seus autores, em qual evento e ano que foi apresentado/publicado e
também a base digital em que pode ser encontrado (Tabela 4).
Tabela 4: Publicações selecionadas e suas particularidades
Autor Título da Publicação Evento Base
Digital
01. Caron, Franco;
Ruggeri, Fabrizio;
Pierini, Beatrice
A Bayesian approach to improving
estimate to complete
International Journal of
Project Management
2016
Scopus
Compendex
21
02. Salari, M.,
Khamooshi, H.
A better project performance
prediction model using fuzzy time
series and data envelopment analysis
Journal of the Operational
Research Society 2016
Scopus
03. Wauters, Mathieu;
Vanhoucke, Mario
A Nearest Neighbour extension to
project duration forecasting with
Artificial Intelligence
European Journal of
Operational Research
2017
Scopus
04. Souza, A.D., Rocha,
A.R.C., Santos,
D.C.S.
A proposal for the improvement of
project's cost predictability using
earned value management and
historical data of cost - An empirical
study
- International Journal of
Software Engineering and
Knowledge Engineering
2015;
- Proceedings of the
International Conference
on Software Engineering
and Knowledge
Engineering, SEKE 2014
Scopus
Compendex
05. Souza, A.D., Rocha,
A.R.C., Cristina, D.,
Constantino, B.A.
A Proposal for the Improvement of
Project's Cost Predictability Using
Earned Value Management and
Quality Data - An Empirical Study
Communications in
Computer and
Information Science 2014
Scopus
Compendex
06. Souza, A.D. A proposal for the improvement of
project's cost predictability using
EVM and historical data of cost
Proceedings -
International Conference
on Software Engineering
2013
Scpopus
Compendex
IEEE
07. Souza, A.D., Rocha,
A.R.C.
A Proposal for the Improvement
Predictability of Cost Using Earned
Value Management and Quality Data
Communications in
Computer and
Information Science 2013
Scopus
Compendex
08. Moradi, Navid;
Mousavi, S.
Meysam; Vahdani,
Behnam
An earned value model with risk
analysis for project management
under uncertain conditions
Journal of Intelligent and
Fuzzy Systems 2017
Compendex
09. Radek, D. Fuzzy logic: An instrument for the
evaluation of project status
Revista de Metodos
Cuantitativos para la
Economia y la Empresa
2015
Scopus
10. Li, You; Liu, Lu Hybrid artificial neural network and
statistical model for forecasting
project total duration in earned value
management
International Journal of
Networking and Virtual
Organisations 2012
Compendex
22
11. Garcia J.L.C.;
Gallego J.J.C.;
Martinez M.A.H.;
Soria P.R.
Improve Tracking in the Software
Development Projects
- Joint Conference of the
21st International
Workshop on Software
Measurement, IWSM
2011
- 6th International
Conference on Software
Process and Product
Measurement,
MENSURA 2011
IEEE
12. Kim B.C. Integrating Risk Assessment and
Actual Performance for Probabilistic
Project Cost Forecasting: A Second
Moment Bayesian Model
IEEE Transactions on
Engineering Management
2015
IEEE
13. Aliverdi, R.,
Moslemi Naeni, L.,
Salehipour, A.
Monitoring project duration and cost
in a construction project by applying
statistical quality control charts
International Journal of
Project Management
2013
Scopus
Compendex
14. Ma, X.; Yang, B. Optimization study of Earned Value
Method in construction project
management
International Conference
on Information
Management, Innovation
Management and
Industrial Engineering,
ICIII 2012
IEEE
15. Dodson, M.;
Defavari, G.;
Carvalho, V.
Quality: The Third Element of Earned
Value Management
Procedia Computer
Science 2015
Scopus
Compendex
Fonte: Autor.
4. RESULTADOS ENCONTRADOS
De acordo com as categorias definidas no tópico 2.2.2, os resultados foram
classificados, primeiramente, em: estabilidade do índice de desempenho de custo (CPI) e do
índice de desempenho de prazo (SPI); propostas de novas técnicas de monitoramento de
projetos e propostas de melhoria na tradicional técnica de gerenciamento de valor agregado
(EVM). Em seguida, subcategorias foram criadas para que os resultados pudessem ser
melhor agrupados (Figura 10).
23
Figura 10: Fluxograma que representa as categorias e subcategorias em que os resultados
foram divididos.
Fonte: Autor.
4.1. ESTABILIDADE DO ÍNDICE DE DESEMPENHO DE CUSTO (CPI) E DO
ÍNDICE DE DESEMPENHO DE PRAZO (SPI)
Dos 15 artigos selecionados para esta revisão sistemática, apenas 2 apresentam em
seu estudo uma discussão sobre a estabilidade do Índice de Desempenho de Custo (CPI) ou
do Índice de Desempenho de Prazo/Cronograma (SPI).
Alguns pontos de vulnerabilidade da tradicional técnica de EVM levantados por
(SOUZA, 2015) são (i) os dados de desempenho de custos nem sempre têm distribuição
normal, o que dificulta as projeções confiáveis; (ii) a instabilidade de índices de desempenho
de custos durante a execução de projetos, (iii) há uma tendência de piora nos índices de
desempenho de custos quando o projeto se aproxima do término. Para solucionar casos como
esse, o autor propõe que dados históricos de custos sejam utilizados para o cálculo do CPI, a
fim de garantir uma maior credibilidade a essa previsão dos custos.
Outra proposta de (SOUZA, 2014) para essa instabilidade do Índice de Desempenho
de Custo é utilizar dados de qualidade integrados ao método EVM para uma maior precisão
na previsão do CPI.
4.2. PROPOSTAS DE NOVAS TÉCNICAS DE MONITORAMENTO DE
PROJETOS
Dos 15 artigos selecionados para esta revisão sistemática, apenas 4 deles apresentam
uma proposta para nova técnica composta de métodos diversos para a prática de
gerenciamento de projetos.
24
4.2.1 Modelo Bayesiano
Um estudo Bayesiano é a proposta defendida por (CARON, RUGGERI E PIERINI,
2016) que foca na probabilidade subjetiva como base para o começo da discussão sobre o
controle do projeto. Essa probabilidade trata-se da opinião, suposições e conhecimentos
tácitos de especialistas. Dessa forma, dados de projetos anteriores similares ao atual também
são considerados uma fonte de conhecimento para monitoramento e controle. E por fim, os
dados de desempenho do atual projeto vão formando ao longo do tempo de evolução a
terceira fonte de conhecimento que compõe o método proposto. O modelo proposto pelos
autores foi aplicado a três projetos grandes e complexos de petróleo e gás e demonstrou
sucesso em seus resultados comparados à utilização da técnica de gerenciamento de valor
agregado. (Anexos – Artigo 01).
O artigo de (KIM, 2015) apresenta um modelo Bayesiano para a previsão de
desempenho de projetos integrando à sua avaliação de riscos. Este modelo fornece fórmulas
algébricas eficientes para promover a previsão do desempenho do projeto. Exemplos
numéricos e simulações são utilizados para a demonstração e validação da técnica proposta
pelo autor e comprovam a sua eficácia e sua utilização em ambientes reais. (Anexos – Artigo
13).
4.2.2 Métodos de Inteligência Artificial
Uma outra novidade interessante foi trazida por (WAUTERS E VANHOUCKE,
2017) ao introduzirem o método do vizinho mais próximo com o objetivo de minimizar o
conjunto de situações semelhantes à fase atual do projeto e aumentar a precisão da previsão
de seu futuro. Um método de Inteligência Artificial é utilizado para proporcionar a previsão
sobre esse futuro por meio dos dados minimizados. Um grande experimento computacional
foi configurado para o teste e validação da proposta feita pelos autores e comprovou que a
técnica do vizinho mais próximo possibilita resultados mais precisos do que a tradicional
EVM. (Anexos - Artigo 04).
O artigo de (LI E LIU, 2012) propõe um novo modelo para o gerenciamento de
projetos que utiliza o conceito de redes neurais artificiais juntamente com o método de
simulação de número aleatório para prever o indicador de cronograma. Este estudo também
considera dados de períodos próximos (técnica do vizinho mais próximo) para a recruta de
informações iniciais. Logo em seguida, métodos estatísticos são utilizados para prever os
índices de cronograma futuros do projeto. Testes e experimentos que foram realizados neste
25
estudo, comprova que essa proposta híbrida supera a tradicional técnica de gerenciamento de
valor agregado. (Anexos - Artigo 11).
4.3. PROPOSTAS DE MELHORIAS NA TRADICIONAL TÉCNICA DE
GERENCIAMENTO DE VALOR AGREGADO (EVM)
A maioria das publicações selecionadas para o estudo desta revisão, representada por
11 artigos dentro de 15 que foram selecionados, tem como objetivo propor uma melhoria na
técnica tradicional de Gerenciamento de Valor Agregado.
4.3.1 Métodos Estatísticos
4.3.1.1 Números Fuzzy
O estudo de (SALARI E KHAMOOSHI, 2016) sugere um planejamento de projetos
baseado em dados anteriores e em séries temporais Fuzzy para obter a previsão final
desejada. Dessa maneira, algumas expressões linguísticas são utilizadas para representar o
desenvolvimento dessa estimativa Fuzzy e para interpretar as possíveis condições do atual
projeto. Alguns dados e casos simulados foram criados para o teste dessa proposta e também
para ilustrar como ela pode ser utilizada em situações reais. Sendo assim, foram realizados
três estudos de caso utilizando a aplicação da técnica proposta e também utilizando a
aplicação do EVM para que uma comparação de métodos pudesse ser feita. Através dos
resultados apresentados no artigo, fica claro que na grande maioria das fases dos estudos de
caso, a técnica proposta por (SALARI E KHAMOOSHI, 2016) se mostrou mais precisa do
que a tradicional técnica de gerenciamento de valor agregado. (Anexos - Artigo 02).
Mais um estudo que considera a Lógica Fuzzy como melhoria no processo de
previsão, planejamento e controle do projeto é o artigo de (RADEK, 2015) que inicialmente
apresenta uma explicação sobre os conjuntos Fuzzy, sua lógica, bem como seus cálculos
necessários para a obtenção de resultados e tem como objetivo comprovar a eficácia da
integração desse método à técnica de EVM; integração esta que tem como objetivo auxiliar
ainda mais aos gerentes de projetos e aqueles que precisam tomar decisões quanto às suas
futuras condições. Este artigo demonstra como indicadores como Índice de Desempenho de
Custos (CPI) e Índice de Desempenho de Cronograma (SPI) podem ser transformados em
variáveis linguísticas que representam a atual situação do projeto e possíveis soluções e
caminhos a seguir. Dessa maneira, esse método considera os riscos e incertezas que o
desenvolvimento do projeto corre, diferente da técnica de gerenciamento de valor agregado.
26
O estudo de caso demonstrado neste artigo é composto por dados reais retirados de projetos
de TI e comprova essa vantagem da técnica proposta sobre a de EVM. (Anexos - Artigo 10).
4.3.1.2 Curvas Sigmodais
O estudo de (GARCIA, GALLEGO, MARTINEZ E SORIA, 2011) foca no método
estatístico de Curvas Sigmodais ou Curvas S, parametrizadas adequadamente e utilizando a
técnica de gerenciamento de valor agregado para um melhor monitoramento do projeto, a fim
de obter sua previsão em termos de custo e prazos; e então, a evolução do projeto é
matematicamente modelada como uma função contínua. Projetos reais de desenvolvimento
de software são utilizados para comprovar a validação e eficácia do método proposto pelos
autores. (Anexos – Artigo 12).
4.3.2 Dados Históricos de Custo
Como já citado anteriormente, (SOUZA, 2015) propõe uma melhoria na técnica
tradicional devido à instabilidade de índices de desempenho de custos durante a execução de
projetos e devido também a uma tendência de piora nos índices de desempenho de custos
quando o projeto se aproxima do término. Este caso já foi discutido na seção 4.1 por
apresentar também um método de estudo sobre a instabilidade do Indicador de Desempenho
de Custo (CPI). O autor deste estudo propõe a utilização de dados históricos de custo para
auxiliar no monitoramento e controle do projeto. Um estudo de caso em 22 projetos de
software foi apresentado e utilizado para comprovar a validação da técnica proposta e testes
de hipóteses com nível de significância de 95% foram realizados, demonstrando que a
proposta do trabalho é mais precisa e eficiente do que a técnica tradicional para calcular os
índices CPI e EAC contidos no EVM. (Anexos – Artigo 05 e Artigo 07).
4.3.3 Indicadores de Desempenho de Qualidade
O autor (SOUZA, 2014) propõe uma outra alternativa para suprir as limitações
encontradas na técnica de gerenciamento de valor agregado: integrar dados de desempenho
de qualidade sobre a técnica tradicional de EVM. Sua validação, que foi feita por meio da
aplicação do método proposto em 20 projetos de software, comprova uma maior precisão
novamente na previsão dos índices CPI (Índice de Desempenho de Custo) e EAC (Estimativa
de Conclusão).
A fim de superar a limitação da técnica de gerenciamento de valor agregado de medir
o desnível entre o planejado e o real em casos de discordâncias no que foi previsto,
27
(ALIVERDI, MOSLEMI E SALEHIPOUR, 2013) criou um método que representa a
integração dessa técnica com gráficos estatísticos de controle de qualidade para controlar de
maneira eficiente os índices obtidos por meio da aplicação do EVM. Dados reais de um
projeto de construção foram utilizados para testar a proposta deste artigo e retornou
resultados promissores que são capazes de demonstrar a eficácia que essa integração pode
proporcionar.
O estudo de (MA E YANG, 2012) também foca na introdução de dados de qualidade
nos cálculos para a previsão de desempenho do projeto a fim de combinar gerenciamento de
custos, gerenciamento de cronogramas e gerenciamento de qualidade. O artigo demonstra,
então, um estudo de caso que compara o modelo proposto (Quality Earned Value
Management) com o EVM e que comprova a melhora na técnica tratada pelos autores.
Os autores (DODSON, DEFAVARI E CARVALHO, 2015) realizaram um estudo
interessante para apoiar aqueles que defendem a integração do componente de qualidade com
o gerenciamento de valor agregado. O artigo apresentado por eles apresenta um estudo de
caso de uma colheita de soja de uma fazenda do Brasil como um projeto de análise. Durante
este estudo de caso, variáveis de qualidade são propostas, calculadas e estudadas. Sendo
assim, ficou comprovado que a técnica do EVM pode ser aplicada de uma maneira mais
eficiente por meio da integração da análise de qualidade ao processo de monitoramento de
projetos.
4.3.4 Análise de Risco
Uma proposta de integração de métodos é, então, trazida por (MORADI, MOUSAVI
E VAHDANI, 2017), que, dessa vez, tem a intenção de promover a integração da tradicional
técnica de gerenciamento de valor agregado com a análise de risco para prever o desempenho
futuro do projeto com uma maior precisão, demonstrando o efeito das situações de risco na
previsão final. Neste trabalho os números Fuzzy também são utilizados para interpretar
índices e avaliações por meio de variáveis linguísticas. Por fim, um estudo de caso de
literatura da indústria de construção civil foi utilizado para testar e validar essa integração e
comprova a sua eficácia em situações de planejamentos de projetos envolvendo situações de
riscos.
5. PERSPECTIVAS PARA NOVOS ESTUDOS
Como foi possível observar ao longo desta revisão sistemática, os autores têm focado
bastante na integração da técnica de Gerenciamento de Valor Agregado com o Índice de
28
Qualidade, buscando uma melhora na prática de gerenciamento de projetos. Esse método é o
que mais aparece nos artigos relevantes a este estudo e, por este motivo, pode apresentar
grandes oportunidades de futuras pesquisas e um aprofundamento sobre o assunto, pois sua
validação já foi diversas vezes comprovada.
O que tem ainda ganhado espaço também são as técnicas de Inteligência Artificial
sendo utilizadas para solucionar casos de previsão de índices de custo e duração durante a
execução de um projeto. Elas estiveram presentes nas referências trazidas aqui, porém
demonstram que existe ainda uma gama de pesquisas, estudos e testes a serem feitos
comprovando a sua eficácia e sua comparação com os atuais e tradicionais métodos
utilizados.
6. CONCLUSÃO
Atualmente muitos autores tem citado, mencionado, estudado e aplicado a técnica de
gerenciamento de valor agregado em suas publicações. Através da busca realizada para a
realização desta revisão sistemática, pode-se perceber que muitas são as referências sobre o
assunto que falam da tradicional técnica utilizada e que a aplicam em diversos ambientes em
que se faz necessário o gerenciamento de projetos.
Entretanto, como a técnica de EVM possui falhas e desvantagens, alguns autores
tratam dessas falhas em seus artigos, explicando-as e propondo uma nova maneira de se obter
sucesso durante as fases de monitoramento e controle do projeto.
Diversas foram as melhorias observadas na fase final da demonstração de resultados
desta revisão sistemática. Realmente a integração da técnica de EVM com o Índice de
Desempenho de Qualidade (QPI) é a proposta de solução que mais aparece dentro os artigos
encontrados. Porém, outras sugestões são levantadas e validadas, como o estudo por meio de
dados históricos de custo, a integração com análise de risco, o uso de controle estatístico,
dentre outras. Há ainda aqueles que focam em novos métodos para uma maior eficiência no
gerenciamento de projetos, como a utilização de técnicas de Inteligência Artificial ou de
modelos Bayesianos, a fim de obter sucesso na previsão do projeto.
Como pode ser visto nos resultados apresentados, a maioria dos autores propõem e
comprovam estudos de melhorias na técnica de EVM; poucos focam um novo método ou
discutem sobre a estabilidade dos índices utilizados nas fórmulas de gerenciamento de valor
agregado.
29
REFERÊNCIAS
[1]CARON, F., RUGGERI, F., PIERINI, B., 2016. “A Bayesian approach to
improving estimate to complete”. International Journal of Project
Management, v.34, pp. 1687-1702.
[2]SALARI, M., KHAMOOSHI, H., 2016. “A better project performance prediction
model using fuzzy time series and data envelopment analysis”. Journal of the
Operational Research Society, v.67, pp.1274-1287.
[3]WAUTERS, MATHIEU; VANHOUCKE, MARIO, 2017. “A Nearest Neighbour
extension to project duration forecasting with Artificial Intelligence”.
European Journal of Operational Research, v.259, pp. 1097-1111.
[4]SOUZA, A.D., ROCHA, A.R.C., DOS SANTOS, D.C.S., 2015. “A proposal for
the improvement of project's cost predictability using earned value
management and historical data of cost - An empirical study”. International
Journal of Software Engineering and Knowledge Engineering, v.25, n.1,
pp.27-50.
[5]SOUZA, A.D. et. al., 2014. “A Proposal for the Improvement of Project's Cost
Predictability Using Earned Value Management and Quality Data - An
Empirical Study”. Communications in Computer and Information Science,
Springer, v.425, pp.170-181.
[6]SOUZA, Adler Diniz, 2013. “A proposal for the improvement of project's cost
predictability using EVM and historical data of cost”. Proceedings -
International Conference on Software Engineering, pp.1447-1449.
[7]SOUZA, A.D., ROCHA, A.R.C, 2013. “A Proposal for the Improvement
Predictability of Cost Using Earned Value Management and Quality Data”.
Communications in Computer and Information Science, Springer, v.364,
pp.190-201.
30
[8]MORADI, N,; MOUSAVI, S.M.; VAHDANI, B., 2017. “An earned value model
with risk analysis for project management under uncertain conditions”.
Journal of Intelligent and Fuzzy Systems, v.32, pp. 97-113.
[9]RADEK, D., 2015. “Fuzzy logic: An instrument for the evaluation of project
status”. Revista de Métodos Cuantitativos para la Economia y la Empresa,
pp.5-23.
[10]YOU, Li, LU, Liu, 2012. “Hybrid artificial neural network and statistical model
for forecasting project total duration in earned value management”.
International Journal of Networking and Virtual Organisations, v.10, n.3/4,
pp.402-413.
[11]CUADRADO-GARCIA, J. L. et. Al, 2011. “Improve Tracking in the Software
Development Projects”. 21st International Workshop on Software
Measurement and the 6th International Conference on Software Process and
Product Measurement, pp.215-220.
[11]KIM, B. C., 2015. “Integrating Risk Assessment and Actual Performance for
Probabilistic Project Cost Forecasting: A Second Moment Bayesian Model”.
IEEE Transactions on Engineering Management, v.62, n.2, pp.158-170.
[13]ALIVERDI, R., MOSLEMI, L.N., SALEHIPOUR, A., 2013. “Monitoring project
duration and cost in a construction project by applying statistical quality
control charts”. International Journal of Project Management, v.31, pp.411-
423.
[14]MA, Xiao; YANG, Bin, 2012. “Optimization study of Earned Value Method in
construction project management”. International Conference on Information
Management, Innovation Management and Industrial Engineering, pp.201-
204.
[15]DODSON, Marcelo; DEFAVARI, Guilherme; DE CARVALHO, Vitor, 2015.
“Quality: The Third Element of Earned Value Management”. Procedia
Computer Science, v.64, pp.932-939.
31
[16]ANBARI, F.T., 2003, "Earned Value Project Management Method and
Extensions", Project Management Journal, v. 4 (Dec 2003), pp. 12 - 23.
[17]CHRISTENSEN, D., SCOTT R. H EISE, 1993, "Cost Performance Index
Stability", National Contract Management Journal, v. 25, pp. 7-15.
[18]HENDERSON, K., OFER ZWIKAEL, 2008, "Does Project Performance
Stability Exist A Re-examination of CPI and Evaluation of SPI(t) Stability, "
Cross Talk, v. 21 (April, 2008), pp. 04-07.
[19]KITCHENHAM, B.A., CHARTERS, S. 2007. Guidelines for Performing
Systematic Literature Reviews in Software Engineering Version 2.3, EBSE
Technical Report. Keele University and University of Durham.
[20]LIPKE, W., 2000, "Statistical Process Control Meets Earned Value", Cross Talk
The Journal of Defense Software Engineering, v. vol 13 nro 6, pp. 16-28 .
[21]LIPKE, W., 2003, "Schedule is different", The Measurable News, v. March &
Summer 2003 (March 2003), pp. 1-7.
[22]LIPKE, W., 2004a, "Connecting Earned Value to the Schedule", The Measurable
News, v. Winter 2004 (Winter 2004), pp. 1-8.
[23]LIPKE, W., 2004b, "Independent Estimates at Completion – Another Method",
Cross Talk The Journal of Defense Software Engineering, v. 17 nro 10
(october 2004), pp. 26-30.
[24]LIPKE, W., 2006a, "Statistical Methods Applied to EVM: The Next Frontier",
Cross Talk Departament of Defense, v. 19, pp. 20-23.
[25]LIPKE, W., K.H., 2006b, "Earned Schedule: An Emerging Enhancement to
Earned Value Management", Cross Talk, v. 19 No 11 (November 2006), pp.
26-30.
[26]LIPKE, W., 2008, "Project Duration Forecasting: Comparing Earned Value
Management Methods to Earned Schedule", Cross Talk The Journal of
Defense Software Engineering, v. 21, n. 12, pp. 19-22.
32
[27]LIPKE, W., ANBARI, HENDERSON, 2009, "Prediction of project outcome, the
application of statistical methods to Earned Value Management and Earned
Schedule performance indexes", International Journal of Project Management,
v. 27, nro 4, pp. 400-407.
[28]MAFRA, S., BARCELOS, R., TRAVASSOS, G. H., 2006, "Aplicando uma
Metodologia Baseada em Evidência na Definição de Novas Tecnologias de
Software". In: Proceedings of the 20th Brazilian Symposium on Software
Engineering (SBES), v. 1, pp. 239-254, Florianópolis, Outubro, 2006.
[29]PMI, 2011, Practice Standard Earned Value Management Pennsylvania, Project
Management Institute.
[30]PMI, 2013, Project Management Body of Knowledge - PMBOK Newton Square,
Project Management Institute.
[31]SILVA, L.F., 2004, Uma abordagem com apoio ferramental para aplicação de
técnicas de leitura baseada em perspectiva, COPPE / PESC - Programa de
Engenharia de Sistemas e Computação, Universidade Federal do Rio de
Janeiro, Rio de Janeiro.
[32]SOUZA, Adler Diniz, ROCHA, Ana Regina Cavalcanti. “Uma Proposta Para
Melhoria Da Previsibilidade De Custo De Projetos, Utilizando A Técnica De
Gerenciamento De Valor Agregado E Dados Históricos De Custo E
Qualidade”. Tese: Doutorado em Engenharia de Sistemas e Computação,
Universidade Federal do Rio de Janeiro – UFRJ, Rio de Janeiro, 2014.
[33]TRANFIELD, D., DENYER, D., SMART, P., 2003. Towards a methodology for
developing evidence-informed management knowledge by means of
systematic review. Br. J. Manag., v.14, pp. 207-222.
[34]VARGAS, R. V., 2013, "Análise de Valor Agregado: Revolucionando o
gerenciamento de prazos e custos", Ed. 6ª, Rio de Janeiro, Brasport.
[35]ZWIKAEL, O., GLOBERSON, S. e Raz, T., 2000, "Evaluation of Models for
Forecasting the Final Cost of a Project.”, Project Management Journal, v.31,
pp. 53-57.
33
[36]GARZA-REYES, Jose Arturo, 2015. “Lean and green e a systematic review of
the state of the art literature”. Journal of Cleaner Production, v.102, pp.18-29.
[37] GOODMAN, L.A. Snowball Sampling. The annals of mathematical
statistics. Vol. 32, No. 1, pp. 148-170, mar. 1961.
34
ANEXOS
35
ANEXO 1 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA
NA BASE DIGITAL SCOPUS
Autor Título da Publicação Evento
01. Salari, M., Khamooshi,
H.
A better project performance prediction
model using fuzzy time series and data
envelopment analysis
Journal of the Operational Research
Society – 2016
02. Salari, M., Bagherpour,
M., Wang, J.
A novel earned value management model
using Z-number
International Journal of Applied
Decision Sciences – 2014
03.
De Souza, A.D., Da
Rocha, A.R.C., Dos
Santos, D.C.S.
A proposal for the improvement of
project's cost predictability using earned
value management and historical data of
cost - An empirical study
International Journal of Software
Engineering and Knowledge
Engineering – 2015
04.
De Souza, A.D.,
Rocha, A.R., Dos
Santos, D.C.S.
A proposal for the improvement of
project's cost predictability using earned
value management and historical data of
cost - An empirical study
Proceedings of the International
Conference on Software Engineering
and Knowledge Engineering, SEKE –
2014
05.
de Souza, A.D., Rocha,
A.R.C., Cristina, D.,
Constantino, B.A.
A Proposal for the Improvement of
Project's Cost Predictability Using Earned
Value Management and Quality Data - An
Empirical Study
Communications in Computer and
Information Science – 2014
06. Diniz De Souza, A.
A proposal for the improvement of
project's cost predictability using EVM
and historical data of cost
Proceedings - International
Conference on Software Engineering
– 2013
07. de Souza, A.D., Rocha,
A.R.C.
A Proposal for the Improvement
Predictability of Cost Using Earned Value
Management and Quality Data
Communications in Computer and
Information Science – 2013
08. Warburton, R.D.H. A time-dependent earned value model for
software projects
International Journal of Project
Management – 2011
9 Chen, S., Zhang, X.
An analytic review of earned value
management studies in the construction
industry
Construction Research Congress:
Construction Challenges in a Flat
World – 2012
10
Bagherpour, M.,
Safari, M., Mohammad
Sharifi, M.
Applying mechanical equilibrium rules in
project cost management
Proceedings of the Institution of
Mechanical Engineers, Part B:
Journal of Engineering Manufacture
– 2016
11. Băncescu, M. Controlling Project Schedule Progress,
Using Control Charts Cybernetics and Systems – 2016
12. Fowler, S., Chen, P.P.
CsPI: A New Way to Evaluate
Cybersecurity Investments: A Position
Paper
IEEE International Conference on
Software Quality, Reliability and
Security Companion, QRS-C – 2017
13.
Seidleck, M.,
Reynolds, S., Krygiel,
J.
Developing forward-looking metrics to
interpret SPI and CPI performance indices
for GSFC projects
IEEE Aerospace Conference
Proceedings – 2016
14. Jagathipriya, N.B.K.,
Bhatia, R.S.
Earned value management - Application
of performance evaluation system for high
value contract management
Journal of Spacecraft Technology –
2012
15. De Marco, A.,
Narbaev, T.
Earned value-based performance
monitoring of facility construction
projects
Journal of Facilities Management –
2013
16. Nevison, J.M.,
Chichakly, K.
Effective corrective action: The
initial/envelope model for managing
projects
Journal of Modern Project
Management – 2017
36
17. Radek, D. Fuzzy logic: An instrument for the
evaluation of project status
Revista de Metodos Cuantitativos
para la Economia y la Empresa –
2015
18.
Kim, S.-C., Kim, Y.-
W., Park, K.S., Yoo,
C.-Y.
Impact of measuring operational-level
planning reliability on management-level
project performance
Journal of Management in
Engineering – 2015
19.
Kim, J., Koo, C., Kim,
C.-J., Hong, T., Park,
H.S.
Integrated CO², cost, and schedule
management system for building
construction projects using the earned
value management theory
Journal of Cleaner Production - 2015
20. Moselhi, O., Azarm, R. Material status index in support Of EVM
ISARC - 30th International
Symposium on Automation and
Robotics in Construction and Mining,
Held in Conjunction with the 23rd
World Mining Congress – 2013
21.
Aliverdi, R., Moslemi
Naeni, L., Salehipour,
A.
Monitoring project duration and cost in a
construction project by applying statistical
quality control charts
International Journal of Project
Management – 2013
22. Kim, B.-C.
Probabilistic Evaluation of Cost
Performance Stability in Earned Value
Management
Journal of Management in
Engineering – 2016
23.
Hanagodimath, A.V.,
Rajashekarswamy,
H.M., Parate, H.R.
Project performance in real time
construction industry - A case study
International Journal of Civil
Engineering and Technology – 2016
24. Mirza, E., Ehsan, N.
Quantification of Project Execution
Complexity and its Effect on Performance
of Infrastructure Development Projects
EMJ - Engineering Management
Journal – 2017
25. Villanueva, J.A.,
Kovach, J.V.
Reducing engineering/design time for
EPC oil and gas projects
IIE Annual Conference and Expo –
2013
26. De Koning, P.,
Vanhoucke, M.
Stability of earned value management do
project characteristics influence the
stability moment of the cost and schedule
performance index
Journal of Modern Project
Management – 2016
27. Petter, J.L., Ritschel,
J.D., White, E.D.
Stability properties in Department of
Defense contracts: Answering the
controversy
Journal of Public Procurement - 2015
28. Kumar, G.P., Asadi,
S.S.
The effect of Earned value Management
on risk assessment using Analytical
Network Process: A case study
International Journal of Civil
Engineering and Technology – 2016
29. Moselhi, O. The use of earned value in forecasting
project durations
Proceedings of the 28th International
Symposium on Automation and
Robotics in Construction, ISARC –
2011
30. Nevison, J.
Working the "educated" plan: How
effective is corrective staffing in a typical
white-collar project
Journal of Modern Project
Management - 2015
37
ANEXO 2 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA
NA BASE DIGITAL COMPENDEX
Autor Título da Publicação Evento
01. Chen, Shu(1); Zhang,
Xueqing(1)
An analytic review of earned value
management studies in the
construction industry
Construction Research Congress:
Construction Challenges in a Flat
World – 2012
02.
de Souza, Adler Diniz(1);
Rocha, Ana Regina
Cavalcanti(1)
A Proposal for the Improvement
Predictability of Cost Using Earned
Value Management and Quality Data
Communications in Computer and
Information Science – 2013
03.
de Souza, Adler Diniz(1);
Rocha, Ana Regina
Cavalcanti(1); Cristina,
Djenane(1); Constantino,
Bruno Augusto(1)
A Proposal for the Improvement of
Project's Cost Predictability Using
Earned Value Management and
Quality Data - An Empirical Study
Communications in Computer and
Information Science – 2014
04.
De Souza, Adler Diniz(1);
Da Rocha, Ana Regina
Cavalcanti(1); Dos Santos,
Djenane Cristina Silveira(2)
A proposal for the improvement of
project's cost predictability using
earned value management and
historical data of cost - An empirical
study
International Journal of Software
Engineering and Knowledge
Engineering – 2015
05. Kim, Byung-Cheol(1)
Probabilistic Evaluation of Cost
Performance Stability in Earned
Value Management
Journal of Management in
Engineering – 2016
06.
Kim, Jimin(1); Koo,
Choongwan(1); Kim, Chan-
Joong(2); Hong,
Taehoon(1); Park, Hyo
Seon(1)
Integrated CO2, cost, and schedule
management system for building
construction projects using the earned
value management theory
Journal of Cleaner Production - 2015
07. Jagathipriya, Niveditha B.
K.(1); Bhatia, R.S.(1)
Earned value management -
Application of performance
evaluation system for high value
contract management
Journal of Spacecraft Technology –
2012
08.
De Souza, Adler Diniz(1);
Rocha, Ana Regina(1); Dos
Santos, Djenane Cristina
Silveira(2)
A proposal for the improvement of
project's cost predictability using
earned value management and
historical data of cost - An empirical
study
Proceedings of the International
Conference on Software Engineering
and Knowledge Engineering, SEKE –
2014
9 Diniz De Souza, Adler(1)
A proposal for the improvement of
project's cost predictability using
EVM and historical data of cost
Proceedings - International
Conference on Software Engineering
– 2013
10 Warburton, Roger D.H.(1) A time-dependent earned value
model for software projects
International Journal of Project
Management – 2011
11.
Seidleck, Mark(1);
Reynolds, Scott(2); Krygiel,
Joseph(2)
Developing forward-looking metrics
to interpret SPI and CPI performance
indices for GSFC projects
IEEE Aerospace Conference
Proceedings – 2016
12.
Bagherpour, Morteza(1);
Safari, Mojtaba(1);
Mohammad Sharifi,
Masoud(1)
Applying mechanical equilibrium
rules in project cost management
Proceedings of the Institution of
Mechanical Engineers, Part B:
Journal of Engineering Manufacture
– 2016
13.
Kim, Sang-Chul(1); Kim,
Yong-Woo(2); Park, Kun
Soo(3); Yoo, Choong-
Yuel(3)
Impact of measuring operational-
level planning reliability on
management-level project
performance
Journal of Management in
Engineering – 2015
38
14.
Aliverdi, Reza(1,2,3);
Moslemi Naeni,
Leila(1,2,3); Salehipour,
Amir(1,2,3)
Monitoring project duration and cost
in a construction project by applying
statistical quality control charts
International Journal of Project
Management – 2013
15. Fowler, Summer(1); Chen,
Peter P.(2)
CsPI: A New Way to Evaluate
Cybersecurity Investments: A
Position Paper
IEEE International Conference on
Software Quality, Reliability and
Security Companion, QRS-C – 2017
16. Mirza, Ebtisam(1); Ehsan,
Nadeem(1)
Quantification of Project Execution
Complexity and its Effect on
Performance of Infrastructure
Development Projects
EMJ - Engineering Management
Journal – 2017
17. Khamooshi, Homayoun(1);
Abdi, Abdollah(2,3)
Project Duration Forecasting Using
Earned Duration Management with
Exponential Smoothing Techniques
Journal of Management in
Engineering – 2017
18. Loop, Robert(1) Schedule metrics reliability and
predictability
AACE International Transactions –
2013
19. Moselhi, O.(1); Azarm,
R.(1)
Material status index in support Of
EVM
ISARC - 30th International
Symposium on Automation and
Robotics in Construction and Mining,
Held in Conjunction with the 23rd
World Mining Congress – 2013
20. Moselhi, Osama(1) The use of earned value in forcasting
project durations
Proceedings of the 28th International
Symposium on Automation and
Robotics in Construction, ISARC –
2011
21. Bncescu, Mioara(1) Controlling Project Schedule
Progress, Using Control Charts Cybernetics and Systems – 2016
22. Wang, Li(1)
Rsearch of the investment departure
early warning model of infrastructure
projects based on BP neural network
Proceedings of the 18th International
Symposium on Advancement of
Construction Management and Real
Estate – 2014
23.
Alarcón, Luis F.(1);
Salvatierra, José L.(2);
Letelier, José A.(3)
Using Last Planner indicators to
identify early signs of project
performance
22nd Annual Conference of the
International Group for Lean
Construction: Understanding and
Improving Project Based Production,
IGLC – 2014
24. Villanueva, Jesus A.(1);
Kovach, Jamison V.(1)
Reducing engineering/design time for
EPC oil and gas projects
IIE Annual Conference and Expo –
2013
39
ANEXO 3 - PUBLICAÇÕES ENCONTRADAS ATRAVÉS DA STRING DE BUSCA
NA BASE DIGITAL IEEE
Autor Título da Publicação Evento
01. J. E. Psaroudakis; A.
Eberhardt
A Discrete Event Simulation Model to
Evaluate Changes to a Software Project
Delivery Process
IEEE 13th Conference on
Commerce and Enterprise
Computing – 2011
02.
T. Zhang; S. X. Chen;
H. B. Gooi; J. M.
Maciejowski
A Hierarchical EMS for Aggregated
BESSs in Energy and Performance-Based
Regulation Markets
IEEE Transactions on Power
Systems – 2017
03. A. Diniz de Souza
A proposal for the improvement of project's
cost predictability using EVM and
historical data of cost
35th International Conference on
Software Engineering (ICSE) - 2013
04. Seong-Jin Kim; Tae-
Hak Kim
A study on the integrated construction cost
management method with reflection of the
characteristics of public construction works
in South Korea
Second International Conference on
Computer Science, Computer
Engineering, and Social Media
(CSCESM) – 2015
05. B. A. Hussein; R.
Ravnå
A template for building adaptable project
risk management games
IEEE 8th International Conference
on Intelligent Data Acquisition and
Advanced Computing Systems:
Technology and Applications
(IDAACS) – 2015
06. L. Zhang; J. Zhu
Aggregation of two kinds of preference
information considering consistency
coordination
IEEE International Conference on
Grey Systems and Intelligent
Services – 2011
07. S. Suenaga; K. Tei; S.
Honiden
Applicability of earned value management
for deadline energy constrained
applications
IEEE International Conference on
Industrial Engineering and
Engineering Management (IEEM) –
2017
08. P. Efe; O. Demirörs Applying EVM in a Software Company:
Benefits and Difficulties
39th Euromicro Conference on
Software Engineering and Advanced
Applications – 2013
9
W. Majerowicz; D.
Emmons; R. Bitten;
S. A. Shinn
Contribution of schedule delays to cost
growth: How to make peace with a
marching army
IEEE Aerospace Conference - 2016
10 T. A. Khalid; E. T.
Yeoh
Controlling software cost using fuzzy
Quality based EVM
International Conference on
Computing, Control, Networking,
Electronics and Embedded Systems
Engineering (ICCNEEE) – 2015
11. S. Fowler; P. P. Chen
CsPI: A New Way to Evaluate
Cybersecurity Investments: A Position
Paper
IEEE International Conference on
Software Quality, Reliability and
Security Companion (QRS-C) –
2017
12. A. S. Gunawan; C.
Fiarni; Y. Ryana
Design for performance monitoring system
using earned value analysis method for
nonprofit organizations case study of
organization X, Indonesia
3rd International Conference on
Science in Information Technology
(ICSITech) – 2017
13. M. Seidleck; S.
Reynolds; J. Krygiel
Developing forward-looking metrics to
interpret SPI and CPI performance indices
for GSFC projects
IEEE Aerospace Conference - 2016
14. J. E. Hannay; H. C.
Benestad; K. Strand
Earned Business Value: See That You
Deliver Value to Your Customer IEEE Software – 2017
40
15. F. Valdés-Souto
Earned Scope Management: A Case of
Study of Scope Performance Using
COSMIC (ISO 19761) with a Real Project
Joint Conference of the International
Workshop on Software
Measurement and the International
Conference on Software Process and
Product Measurement (IWSM-
MENSURA) – 2016
16. N. Jain; K. Kant Earned Value Analysis for real time
wireless sensor network
Seventh International Conference on
Contemporary Computing (IC3) -
2014
17. M. T. McGrath Earned Value Management: Transitioning
from discouragement to a glimmer of hope IEEE Aerospace Conference - 2012
18.
T. Schäffler; M.
Foehr; A. Lüder; K.
Supke
Engineering process evaluation: Evaluation
of the impact of internationalisation
decisions on the efficiency and quality of
engineering processes
IEEE International Symposium on
Industrial Electronics – 2013
19. P. H. Southekal; G.
Levin
Formulation and Empirical Validation of a
GQM Based Measurement Framework
International Symposium on
Empirical Software Engineering and
Measurement – 2011
20.
J. L. Cuadrado-
Garcia; J. J.
Cuadrado-Gallego;
M. A. Herranz-
Martinez; P.
Rodriguez-Soria
Improve Tracking in the Software
Development Projects
Joint Conference of the 21st
International Workshop on Software
Measurement and the 6th
International Conference on
Software Process and Product
Measurement – 2011
21. B. C. Kim
Integrating Risk Assessment and Actual
Performance for Probabilistic Project Cost
Forecasting: A Second Moment Bayesian
Model
IEEE Transactions on Engineering
Management – 2015
22. W. Liggett; H.
Hunter; M. Jones
Navigating an earned value management
validation led by NASA: A contractor's
perspective and helpful hints
IEEE Aerospace Conference - 2017
23. Xiao Ma; Bin Yang
Optimization study of Earned Value
Method in construction project
management
International Conference on
Information Management,
Innovation Management and
Industrial Engineering - 2012
24. M. E. Kuhl; M. K.
Perez Graciano
Project planning and predictive Earned
Value analysis via simulation
Proceedings of the Winter
Simulation Conference – 2014
25. Z. Jing-jing; W. Guo-
qing; Z. Wei
Research on four-electrical railway project
cost estimate based on the WBS standard
templates
International Conference on
Management Science and
Engineering 20th Annual
Conference Proceedings – 2013
26. M. F. Siu; M. Lu
Scheduling simulation-based techniques for
earned value management on resource-
constrained schedules under delayed
scenarios
Winter Simulation Conference
(WSC) – 2011
27. V. Kaulgud; V. S.
Sharma
Software Development Analytics:
Experiences and the Way Forward
30th IEEE/ACM International
Conference on Automated Software
Engineering Workshop (ASEW) –
2015
28. G. Rodriguez; A.
Soria; M. Campo
Supporting Virtual Meetings in Distributed
Scrum Teams
IEEE Latin America Transactions –
2012
29. R. K. Thornley
Sustainable strategic alignment of actual
project portfolio execution: Application
and exploratory case study
International Technology
Management Conference – 2012
41
30. C. Y. Laporte; R. V.
O'Connor
Systems and Software Engineering
Standards for Very Small Entities:
Implementation and Initial Results
9th International Conference on the
Quality of Information and
Communications Technology - 2014
31.
S. A. Shinn; J.
McKeever; V. Ruark;
J. Bryson; W.
Majerowicz; L.
Wunderlick; G. Klein;
P. Nair
The Business Change Initiative: A novel
approach to improved cost and schedule
management
IEEE Aerospace Conference - 2016
32. A. M. Redmond; A.
Zarli
The concept selection of lean software and
system engineering tools for smart cities
International Conference on
Engineering, Technology and
Innovation (ICE/ITMC) - 2017
33. H. Ying
The Highway Construction Cost Control
Model Based on the Improved Earned
Value Method Theory
International Conference on Smart
City and Systems Engineering
(ICSCSE) - 2016
34. J. Cai; Z. Chen
The Research on Communication Networks
Construction Based on Earned Value
Analysis Method
International Conference on
Network and Information Systems
for Computers - 2015
35.
Zurisadai Benjamin
Osorio MartÃnez; E.
Irrazabal; J. Garzás
Toward improving Agile Mantema:
Measurement, control and evaluation of
maintenance projects in SMEs
6th Iberian Conference on
Information Systems and
Technologies CISTI – 2011
36. M. Morad; S. M. El-
Sayegh
Use of Earned Value Management in the
UAE Construction Industry
International Conference on
Industrial Engineering, Management
Science and Application ICIMSA -
2016
37. R. Hans
Using a web-based application to teach
students Earned Value Management
concepts
International Conference on
Computer, Communications, and
Control Technology I4CT – 2015
38. T. M. Korman; H.
Johnston
Using game-based learning and simulations
to enhance engineering and management
education
IEEE Frontiers in Education
Conference FIE - 2013
39. P. H. Southekal; G.
Levin
Validation of a generic GQM based
measurement framework for software
projects from industry practitioners
IEEE 10th International Conference
on Cognitive Informatics and
Cognitive Computing (ICCI-CC'11)
– 2011
42
ANEXO 4 - PUBLICAÇÕES SELECIONADAS ATRAVÉS DA STRING DE BUSCA
E DA APLICAÇÃO DOS FILTROS, SEM A TÉCNICA DE SNOWBALLING
Autor Título da Publicação Evento Base
Digital
01. Salari, M.,
Khamooshi, H.
A better project performance
prediction model using fuzzy time
series and data envelopment analysis
Journal of the Operational
Research Society 2016
Scopus
02. Souza, A.D., Rocha,
A.R.C., Santos,
D.C.S.
A proposal for the improvement of
project's cost predictability using
earned value management and
historical data of cost - An empirical
study
- International Journal of
Software Engineering and
Knowledge Engineering
2015;
- Proceedings of the
International Conference
on Software Engineering
and Knowledge
Engineering, SEKE 2014
Scopus
Compendex
03. Souza, A.D., Rocha,
A.R.C., Cristina, D.,
Constantino, B.A.
A Proposal for the Improvement of
Project's Cost Predictability Using
Earned Value Management and
Quality Data - An Empirical Study
Communications in
Computer and
Information Science 2014
Scopus
Compendex
04. Souza, A.D. A proposal for the improvement of
project's cost predictability using
EVM and historical data of cost
Proceedings -
International Conference
on Software Engineering
2013
Scpopus
Compendex
IEEE
05. Souza, A.D., Rocha,
A.R.C.
A Proposal for the Improvement
Predictability of Cost Using Earned
Value Management and Quality Data
Communications in
Computer and
Information Science 2013
Scopus
Compendex
06. Radek, D. Fuzzy logic: An instrument for the
evaluation of project status
Revista de Metodos
Cuantitativos para la
Economia y la Empresa
2015
Scopus
43
07. Garcia J.L.C.;
Gallego J.J.C.;
Martinez M.A.H.;
Soria P.R.
Improve Tracking in the Software
Development Projects
- Joint Conference of the
21st International
Workshop on Software
Measurement, IWSM
2011
- 6th International
Conference on Software
Process and Product
Measurement,
MENSURA 2011
IEEE
08. Kim B.C. Integrating Risk Assessment and
Actual Performance for Probabilistic
Project Cost Forecasting: A Second
Moment Bayesian Model
IEEE Transactions on
Engineering Management
2015
IEEE
09. Aliverdi, R.,
Moslemi Naeni, L.,
Salehipour, A.
Monitoring project duration and cost
in a construction project by applying
statistical quality control charts
International Journal of
Project Management
2013
Scopus
Compendex
10. Ma, X.; Yang, B. Optimization study of Earned Value
Method in construction project
management
International Conference
on Information
Management, Innovation
Management and
Industrial Engineering,
ICIII 2012
IEEE
44
APÊNDICES
45
APÊNDICE A – RESUMOS DAS PUBLICAÇÕES SELECIONADAS
ARTIGO 01
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A Bayesian approach to improving estimate to complete;
Caron, Franco; Ruggeri, Fabrizio; Pierini, Beatrice;
International Journal of Project Management 2016.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo apresenta uma técnica de gerenciamento de projetos que integra uma abordagem
Bayesiana de três fontes de conhecimento: opiniões de especialistas, dados de projetos
anteriores e o desempenho atual do projeto em andamento. Três projetos de petróleo e gás
foram utilizados para testar a validação desta proposta.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma nova técnica para o gerenciamento de projetos.
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da nova técnica de gerenciamento de projetos
O modelo Bayesiano utiliza uma probabilidade aplicável conhecida como probabilidade
subjetiva, onde as opiniões de especialistas no assunto, mais especificamente, as suas
suposições e conhecimentos tácitos obtidos através de processos anteriormente observados são
a base para a discussão do atual projeto. Em seguida, dados resultantes ao longo do
desenvolvimento do projeto são atribuídos a esses conhecimentos, proporcionando uma nova
distribuição que auxiliará no gerenciamento do projeto.
O Teorema de Bayes pode ser declarado por meio da seguinte expressão (Eq. 1):
Equação 1
46
Onde:
• f (μ) é a distribuição prévia do parâmetro de interesse para inferência; • μ: resume a opinião subjetiva inicial do especialista sobre a probabilidade do
parâmetro μ; • L (μ; y1, y2, ..., yn) é a verossimilhança, obtida após a coleta dos n dados
experimentais y1, y2, ..., yn; • f (µ | y1, y2, ..., yn) é a distribuição posterior, isto é, a distribuição que expressa o
conhecimento adquirido sobre o parâmetro μ após atualizar os julgamentos subjetivos
iniciais com os dados experimentais.
Nesse estudo, foi aplicado o modelo Bayesiano em projetos de petróleo e gás e dois índices de
desempenho foram utilizados (Eq. 2):
Equação 2
onde ND(c)TN significa Desvio Normalizado (custo) no atual momento e ND(t)TN significa
Desvio Normalizado (tempo) no atual momento; quando se refere ao indicador de
desempenho em geral, sem distinção de tempo ou custo, será mencionado apenas ND.
No modelo Bayesiano, a inferência utilizada é o Desvio Normalizado de custo e tempo
avaliados na conclusão, apresentada na Eq. 3:
Equação 3
onde ACTF e TF indicam o custo real final e a duração do projeto, enquanto BAC e SAC
indicam o custo planejado e a duração do projeto, respectivamente.
3.1.1 Distribuição Prévia
Como já citado, no Teorema de Bayes, a distribuição prévia se refere ao conhecimento que o
especialista possui. Num gerenciamento de projetos, a equipe responsável conta com duas
fontes de informação: pareceres/suposições e registros de dados de projetos parecidos já
concluídos anteriormente. Integrando essas duas fontes, uma suposição para o NDTF pode ser
alcançada. Em termos matemáticos, essa integração pode ser obtida da seguinte maneira:
atribuir um valor variando de 0 a 1 a um peso ε, a distribuição prévia é obtido como a soma
ponderada da distribuição das opiniões dos especialistas e a distribuição do cluster de projetos
semelhantes (Eq. 4):
Equação 4
47
Onde:
• ∙ é um ponto genérico da distribuição anterior; • (E (∙) é a avaliação da distribuição de opiniões em um ponto genérico ∙ ; • ΠS (∙) é a avaliação da distribuição do cluster de projetos similares em um ponto
genérico; • ε é o peso.
3.1.2 Distribuição de Opiniões de Especialistas
A suposição dos especialistas pode ser representada por uma distribuição normal da variável
que está sendo analisada. Sendo assim, dois parâmetros precisam ser considerados: a média e
a variância (μE e σE2).
Dessa forma, é utilizado o Processo de Hierarquia Analítica (AHP) para se obter
conhecimentos provindos de especialistas sobre o assunto. AHP é utilizado a fim de suportar o
método do intervalo. Com a intenção de obter distribuição de um certo parâmetro X, o
domínio de definição de X tem que ser subdividido em intervalos e cada especialista expressa
sua preferência por um intervalo especificado através de um comparação de pares entre os
intervalos.
3.1.3 Distribuição de Projetos Semelhantes
O segundo componente de distribuição é a distribuição de agrupamento de projetos anteriores
semelhantes ao atual., a fim de diminuir um pouco das incertezas e eliminar o excesso de
otimismo.
Neste momento, é importante avaliar os parâmetros da distribuição, μS e σS, do cluster de
projetos semelhantes ao atual, considerando n projetos com custo real ou desvio de tempo de
NDTFi planejado (Eq. 5 e Eq. 6):
Equação 5
Equação 6
3.1.4 Definição do peso ε
O próximo parâmetro demonstrado, a fim de identificar a distribuição prévia é a variável de
peso ε. Quando a variável ε aumenta, o peso da distribuição dos especialistas aumenta,
enquanto o peso da distribuição de projetos semelhantes diminui. Indicando com a letra k, o
progresso alcançado pelo projeto atual Neste Momento, em decimais (por exemplo, 0,2, 0,15,
0,8), um intervalo possível para o valor atribuído ao peso ε é expresso pela Equação 7:
ε = [0,1] Equação 7
48
3.1.5 Distribuição Prévia
Após a identificação dos parâmetros μE, σE e μS, σS e a atribuição de um valor ao peso ε, a
distribuição prévia é completamente definida, vide Equação 8 abaixo:
Equação 8
A distribuição prévia trata-se, portanto, da mistura de duas distribuições normais. Essa
distribuição pode-se apresentar de três formas diferentes:
• Normal;
• Normal Distorcida;
• Binomial.
3.1.6 Função de Verossimelhança
A hipótese inicial é de que ND (c) TN e ND (t) TN têm uma distribuição normal. A relação
entre o desempenho final desconhecido e o registrado no Tempo Agora (Time Now) pode ser
expressa do seguinte modo (Eq. 9):
Equação 9
• “x” é a observação no “Tempo Agora”;
• “μ” é o parâmetro final desconhecido;
• “σ(t)” é o desvio padrão;
• “e” é o erro que, no caso de uma função de verossimilhança normal, é distribuída
normalmente por padrão, isto é, e ~ N (0,1).
O indicador de distância também pode resultar num valor baixo, médio ou alto dependendo da
diferença entre a observação no “Time Now” e o valor esperado da distribuição prévia que
resume a opinião prévia (Eq. 10):
Equação 10
• Δc refere-se à “distância de custo” ;
• ΔT refere-se à “distância do tempo”;
• Ep [ND (c) TF] é o valor esperado da distribuição prévia do desempenho final do
custo;
• Ep [ND (t) TF] é o valor esperado da distribuição prévia do desempenho final do
tempo.
• SAC é o Agendamento na Conclusão: se for expressa em meses, fornece o delta em
meses.
49
Na Tabela 1, as classes para o indicador de distância e o indicador do progresso do projeto são
definidos:
Tabela 1: Classes de progresso e distância.
Assim que a classe (baixa, média, alta) do progresso do projeto e da distância no “Time Now”
for identificada, um valor correspondente pode ser atribuído ao desvio padrão, como mostra a
Tabela 2:
Tabela 2: Desvio padrão para a função de verossimilhança.
Logo após o Índice de Desempenho do “Time Now” e o desvio padrão da Tabela 2 terem sido
avaliados, a função de verossimilhança é completamente definida. Indicando ND(c)TN ou
ND(t)TN com x e o parâmetro de inferência com μ, a expressão da função de verossimilhança é
dada na seguinte Equação 11:
Equação 11
3.1.5 Distribuição Posterior
Combinando a distribuição anterior e a função de verossimilhança, de acordo com o teorema
de Bayes, a seguinte distribuição posterior pode ser obtida (Eq. 12):
Equação 12
A função posterior é uma mistura da distribuição posterior de projetos similares ΠS (μ | x)
com a distribuição posterior de opiniões de especialistas ΠE (μ | x) através do peso posterior
ε⁎. Esses três componentes são definidos nas equações a seguir (Eq. 13):
50
Equação 13
As equações abaixo esclarecem a expressão de DE e DS, que são úteis para calcular o peso
posterior ε⁎ (Eq. 14).
Equação 14
Finalmente, a expressão de variância e desvio padrão da distribuição posterior pode ser
avaliada através das equações abaixo (Eq. 15):
Equação 15
Onde:
• EE (μ | x) é o valor esperado da distribuição posterior dos especialistas;
• ES (μ | x) é o valor esperado da distribuição posterior de projetos semelhantes;
• σ²E (μ | x) é a variância da distribuição posterior dos especialistas;
• σ²S (μ | x) é a variância da distribuição posterior de projetos semelhantes.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
51
ARTIGO 02
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA
DO ARTIGO:
A better project performance prediction model using fuzzy time series
and data envelopment analysis. Salari, M., Khamooshi, H. Journal of
the Operational Research Society, 2016.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo apresenta uma extensão baseada na técnica no gerenciamento de valor agregado
(EVM) é uma metodologia crítica de gerenciamento de projetos que avalia e prevê o
desempenho do projeto a partir das perspectivas de custo e cronograma. A nova estrutura
teórica apresentada neste artigo estima o desempenho futuro de um projeto com base nos
dados de desempenho anteriores. O modelo se beneficia de um modelo de previsão de séries
temporais difusas no processo de estimativa. Além disso, a estimativa baseada em fuzzy é
desenvolvida usando termos lingüísticos para interpretar diferentes condições possíveis de
projetos. Eventualmente, a análise por envoltória de dados é aplicada para determinar o
modelo superior de previsão do desempenho do projeto. Múltiplos casos ilustrativos e dados
simulados foram utilizados para análise comparativa e para ilustrar a aplicabilidade do
modelo teórico a situações reais.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma melhoria na técnica de gerenciamento de valor
agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado
Diferentes medidas no EVM são usadas para auxiliar os gerentes de projeto no controle do
projeto através de uma avaliação precisa do valor ganho e do progresso alcançado. Essa
função é executada comparando os valores planejados com os reais correspondentes. As
métricas aplicadas mais significativas no EVM são CPI, métrica de desempenho do
cronograma (SPI) e estimativa na conclusão pela duração (EACt) e estimativa na conclusão
do custo (EAC).
A questão crítica é qual valor de índice apresenta melhor o fator de desempenho futuro ou
52
qual fator de desempenho (FP) deve ser usado no denominador de EAC e EACt. É preciso
fazer algumas suposições para escolher o valor apropriado de PF, em outras palavras,
encontrar a abordagem mais confiável e prática para determinar ou prever a FP é um desafio
quando se assume que o futuro não será necessariamente o mesmo que o passado. Nesse
artigo, concentrou-se em prever os valores futuros para SPI ou CPI, que também podem ser
usados como FP na estimativa do tempo total e custo do projeto. Neste trabalho, sugeri-se o
uso de abordagem fuzzy de séries temporais como uma abordagem eficaz para estimar o
desempenho futuro do projeto, que é explicado e discutido na próxima seção.
A previsão de desempenho sempre desempenhou um papel significativo planejamento e
controle de projetos, e continua fazendo isso no futuro.Essa capacidade de previsão fornece
aos gerentes de projeto a capacidade de minimizar o risco, melhorar o desempenho do
gerenciamento de projetos e possivelmente levar a uma entrega mais bem-sucedida de um
projeto. Há muitas maneiras de fazer previsões do futuro ou previsão. Séries temporais
difusas, como um método de previsão, fornecem uma abordagem prática para prever uma
variável de comportamento de interesse em situações em que nem uma tendência passada é
aparente nem um padrão específico em variações são visualizados.
Considerando o objetivos de previsão, a série temporal fuzzy é utilizada aqui para prever o
custo futuro e agendar o desempenho do projeto. Para elaborar é necessário estabelecer os
seguintes parâmetros ou passos:
• Determinar o universo do discurso;
• Dividir o universo em intervalos longos iguais;
• Determinar as lógicas Fuzzy e adequar ao universo;
• Preparar os dados;
• Adquirir a lógica relação entre os dados históricos;
• Calcular as saídas previstas;
• Avaliar e interpretar os resultados previstos;
Além disso, lida de forma eficaz com as fontes de dados que são imprecisas e vagas. Uma
série temporal difusa com os recursos mencionados é descrito como modelo de previsão de
série temporal fuzzy de enésima ordem.
3.2. Avaliação de Saídas
Como indicado acima nos passos propostos por Song e Chissom (1993), os valores previstos
devem ser avaliados de forma a mostrar a precisão da predição. A precisão da previsão
(outputs) é comumente avaliada em termos de erro quadrático médio (MSE), erro percentual
absoluto médio (MAPE) e erro absoluto médio (MAE), onde MSE, o MAPE ou o MAE
indicam o melhor método de previsão.
53
Onde, n indica o número de erros ou pontos de dados. Vale ressaltar que todas as estimativas
de erros acima mencionadas métodos de edição, exceto o MAPE, escalou a saída.
3.3. Análise envoltória de dados
Análise envoltória de dados (DEA) é um método estabelecido usado para avaliar o
desempenho de sistemas similares e para identificar a eficiência relativa de cada um. DEA é
um tipo não paramétrico de método de programação para avaliar um determinado conjunto
de unidades de tomada de decisão. Existem dois tipos de modelos de envelope:
• Orientados para entrada ou saída. No modelo orientado para produção, o nível de
todos as entradas permanecem constantes e o modelo mede aumentos radiais
mínimos nas saídas.
Nesta aplicação particular, modelos de séries temporais fuzzy são comparados para uma
estimativa ótima do desempenho do projeto. Portanto, uma abordagem DEA orientada a
resultados é empregada para avaliar a eficiência relativa de modelos de séries temporais em
relação à estimativa de desempenho do projeto com base em três índices de erro - MSE,
MAE e MAPE. A este respeito, um modelo orientado a resultados apresentado por Lovell e
Pastor (1999) é utilizado para examinar a eficiência relativa dos modelos de séries temporais.
O modelo proposto por Lovell e Pastor (1999) pode ser mostrado da seguinte forma:
Assume-se que a variável com a maior eficiência, maior valor nos critérios, obtém o maior
valor de τ, que é igual a unidade. No entanto, a maioria os tempos, a equação é usada de
maneira a determinar o eficiência das variáveis em relação a mais de um critério. Nesses
casos, o modelo DEA tenta determinar a ordem de variáveis em termos de eficiência o
melhor modelo com o valores mais altos em todos ou na maioria dos critérios.
Neste trabalho, o modelo DEA empregado avalia a relação eficiência dos modelos de séries
temporais e fornece três saídas, derivado de índices de erro. A formulação do modelo é dada
na equação abaixo:
54
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
55
ARTIGO 03
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A Nearest Neighbour extension to project duration forecasting
with Artificial Intelligence. Wauters, Mathieu; Vanhoucke,
Mario. European Journal of Operational Research 2017.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo apresenta uma extensão baseada na técnica do vizinho mais próximo para a
previsão de controle de projetos com o Gerenciamento de Valor Agregado. Este estudo
também relata a estabilidade da previsão dos vários métodos de inteligência artificial e de
suas contrapartes híbridas vizinhas mais próximas. Um experimento computacional é
realizado a fim de que os métodos propostos sejam testados e validados. Os experimentos
indicam que a técnica de vizinho mais próximo produz os melhores resultados de
estabilidade e é capaz de melhorar os métodos de IA quando o conjunto de treinamento é
semelhante ou diferente do conjunto de testes.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma melhoria na técnica de gerenciamento de valor
agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado
O k-NN explora dados históricos provindos de projetos ou simulações anteriores. Com a
utilização de instâncias de treinamento (instâncias conhecidas) mais recentes, é possível
prever a duração final de uma nova observação do projeto.
Na fórmula abaixo, Y denota um vetor de M atributos indexados por J e representa instâncias
invisíveis do conjunto de treinamento. Este, por sua vez, consiste em n observações (Xi, Oi)
onde i indexa o exemplo de treinamento i e Oi denota o valor de saída da instância de
treinamento i. Os k vizinhos mais próximos de y são encontrados calculando a distância entre
cada ponto do conjunto de treinamento i e a instância y. A fórmula para calcular a distância
euclidiana entre uma instância de treinamento i e o novo exemplo é fornecida abaixo (Eq. 1).
56
Equação 1
Uma vez que k vizinhos mais próximos tenham sido identificados, o valor de saída previsto
da instância y é calculado como a média dos valores de saída de k vizinhos mais próximos
(Eq. 2).
Equação 2
O conjunto consistindo de observações conhecidas é referido como o conjunto de
treinamento, enquanto as observações desconhecidas constituem o conjunto de teste. O
conjunto de treinamento, por sua vez, é subdividido em um segundo conjunto de treinamento
menor e um conjunto de validação. Um modelo do método de IA é criado com base no
pequeno conjunto de treinamento. Logo em seguida, o desempenho do modelo desse
conjunto de treinamento é testado no conjunto de validação. A validação cruzada é um
método de IA utilizado para esses testes, onde a divisão de treinamento e validação é repetida
várias vezes.
Neste documento, os seguintes métodos de inteligência artificial são incluídos para comparar:
• Árvores de Decisão: Através desse método, é possível dividir o espaço da solução em
espaços menores, a fim de maximizar uma determinada medida (por exemplo,
entropia) Essa divisão pode ocorrer várias vezes e é conhecido como particionamento
recursivo. Porém, essa técnica sofre de overfitting e viés de seleção, problemas que
podem ser corrigidos através da implementação de uma estrutura de inferência
condicional que faz uso de testes de permutação. Uma das desvantagens desse
método é que ele é bastante instável, pois uma pequena alteração nos dados pode
levar a um ponto de divisão diferente no nó superior, alterando a estrutura da
subárvore subsequente.
• Bagging e Florestas Aleatórias: O Bagging é um método de conjunto que supera essa
desvantagem citada nas Árvores de Decisão. Bagging faz uma seleção de modo
aleatório da variável de divisão de todos os precedentes disponíveis. Dessa maneira,
Bagging pode ser considerado um caso especial de Florestas Aleatórias, onde a
seleção de predecessor aleatório é restrita a um certo número de indicadores em vez
de todos eles.
• Boosting: Esse método é capaz de transformar algoritmos fracos em algoritmos mais
fortes. A ênfase é colocada em instâncias mais difíceis de prever. Para problemas de
regressão, o gradiente descendente impulsionado (Friedman, 2001) é aplicado.
• Máquinas de Vetor de Suporte: Tem a função de mapear os precedentes para um
espaço maior, onde a regressão linear é executada. A separabilidade linear entre os
pontos de treinamento no espaço de características de alta dimensão é obtida pelas
funções do kernel. Smola e Schölkopf (2004).
Resumindo, a inclusão da técnica do vizinho mais próximo ocorre na fase de testes. Assim,
os melhores parâmetros para o método AI são encontrados. Como mencionado no parágrafo
57
anterior, o método AI é utilizado no conjunto de treinamento maior e seu desempenho é
avaliado por meio das observações no conjunto de testes.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
58
ARTIGO 04
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A proposal for the improvement of project's cost predictability
using earned value management and historical data of cost – An
empirical study. Souza, A.D., Da Rocha, A.R.C., Santos, D.C.S.
International Journal of Software Engineering and Knowledge
Engineering 2015 e Proceedings of the International Conference
on Software Engineering and Knowledge Engineering, SEKE
2014.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo Semelhante ao artigo 06.
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável): Semelhante ao artigo 06.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
59
ARTIGO 05
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A Proposal for the Improvement Predictability of Cost Using
Earned Value Management and Quality Data – An empirical
study. Souza, A.D., Rocha, A.R.C., Cristina, D., Constantino,
B.A. Communications in Computer and Information Science
2014.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo Semelhante ao Artigo 07.
2.1
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável): Semelhante ao Artigo 07.
3.1
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
60
ARTIGO 06
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A proposal for the improvement of project's cost predictability
using earned value management and historical data of cost.
Souza, Adler Diniz. International Conference on Software
Engineering 2013.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Embora a técnica de Gerenciamento de Valor Agregado tenha sido muito utilizada nos
últimos anos a fim de prever custos e cronogramas de um projeto, ela apresenta algumas
vulnerabilidades. Tais como: (i) os dados de desempenho de custos nem sempre têm
distribuição normal, o que dificulta as projeções confiáveis; (ii) instabilidade de índices de
desempenho de custos durante a execução de projetos e (iii) há uma tendência de piora nos
índices de desempenho de custos quando o projeto se aproxima do término. Esse artigo
propõe uma melhoria na técnica a fim de melhorar a previsão dos custos do projeto,
utilizando a integração de dados históricos de desempenho de custos de processos. A técnica
proposta foi aplicada em projetos reais com o objetivo de avaliar a precisão e variação em
comparação com a técnica tradicional. Testes de hipóteses com nível de significância de 95%
foram realizados e a técnica proposta foi mais precisa do que a técnica tradicional para
calcular o Índice de Desempenho de Custo (CPI) e as Estimativas na Conclusão (EAC).
2.2 Objetivo – Descrição do objetivo do artigo
Propor uma melhoria na técnica de gerenciamento de valor agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado (EVM)
O desenvolvimento de uma previsão da EAC envolve estimativas ou previsões de eventos e
condições futuras para o projeto com base em informações e conhecimentos disponíveis até o
momento; informações sobre o desempenho do trabalho, sobre o desempenho do passado do
projeto e qualquer informação que possa impactá-lo no futuro. Os dados históricos dos custos
do processo são informações que podem afetar o desempenho futuro do índice de
desempenho de custos e não são usadas para fazer essas projeções. Este artigo propõe a
integração do EVM com os dados históricos de CPIAcum dos processos. É possível usar a
equação abaixo para calcular o CPIAcum projetado para o final da execução do projeto (Eq.
1):
61
Equação 1
Onde:
• EVAcumProject e ACAcumProject: são respectivamente o EVAcum e ACAcum
tradicionais do projeto, que podem ser calculados usando as equações EVM
tradicionais,. • BACPN: pode ser calculado adicionando todas as atividades de PV do processo. Pode
ser calculado utilizando a equação abaixo (Eq. 2):
Equação 2
• EVAcumPN e ACAcumPN: são respectivamente o EVAcum e ACAcum de cada
processo. Pode ser calculado adicionando cada EV e AC de atividades executadas do
processo; • PN ACExpected: é o ACAcum esperado por cada processo depois de ser executado.
A fórmula de ACExpected usa o CPIAcum histórico de cada processo e pode ser
calculada usando a equação abaixo (Eq. 3):
Equação 3
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
62
ARTIGO 07
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
A Proposal for the Improvement Predictability of Cost Using
Earned Value Management and Quality Data. Souza, A.D.,
Rocha, A.R.C. Communications in Computer and Information
Science 2013.
2. Dados derivados das características de interesse declaradas no objetivo de estudo
2.1 Geral – Resumo da publicação
Embora a técnica de Gerenciamento de Valor Agregado tenha sido muito utilizada nos
últimos anos a fim de prever custos e cronogramas de um projeto, ela apresenta algumas
vulnerabilidades. Tais como: (i) há instabilidade no custo e indicadores de desempenho do
tempo durante o Projeto e (ii) há uma tendência de deterioração nos indicadores de custo e
tempo quando os projetos estão perto de seu fim. Esse artigo propõe uma melhoria na técnica
a fim de melhorar a previsão dos custos do projeto, utilizando a integração de dados
históricos de desempenho de qualidade. Essa técnica proposta é avaliada e comparada com a
técnica tradicional de EVM, mostrando ser mais precisa para o cálculo do Índice de
desempenho de custo (CPI) e da Estimativa de Conclusão (EAC).
2.2 Objetivo – Descrição do objetivo do artigo
Propor uma melhoria na técnica de gerenciamento de valor agregado (EVM).
3. Dados derivados das características de interesse declaradas nas questões secundárias
de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado (EVM
A técnica proposta se baseia em duas medidas básicas, que servirão de base para gerar
medidas e indicadores de desempenho. Total esperado de não-conformidade (TENC)
representa o NC total esperado para um determinado projeto; ele é a linha de base da
qualidade do processo. Dado o tamanho do projeto, seu cálculo se dá pela fórmula (Eq. 1):
TENC = Size * INCH Equação 1
Onde:
• O tamanho do software pode ser dado por pontos de função, pontos de caso ou outra
medida de tamanho desde que a técnica usada em todos os projetos seja a mesma; • O INCH é a taxa de não conformidade do projeto obtida através da seguinte fórmula
(Eq. 2):
63
Equação 2
O indicador TENC é gerado para cada processo que passe pela técnica proposta e é baseado
em dados históricos de vários projetos.
Este indicador possui complementos que são TENC ($), simbolizando o custo associado a
ele, e o TENC(h), que simboliza o esforço associado a ele. Para calcular esse último, deve
utilizar da fórmula abaixo (Eq. 3):
TENC(h) = TENC * AEE Equação 3
Onde:
• O AEE é o esforço necessário estimado para corrigir o não cumprimento e pode ser
calculado através da seguinte fórmula (Eq. 4): •
Equação 4
Já para o cálculo do TENC($), que representa o custo necessário para corrigir o não
cumprimento, deve-se usar a equação abaixo (Eq. 5):
TENC($) = TENC * Man Hour Cost Equação 5
Onde:
• Man Hour Cost é a variável referente ao custo das horas trabalhadas em cima da
técnica por um determinado projeto.
O INC (não-cumprimento identificado) representa o NC detectado que corresponde a um
processo em especial considerando-se um projeto específico; seu cálculo se dá pela equação
abaixo (Eq. 6):
Equação 6
Todos esses cálculos podem ajudar a analisar o atual desempenho do projeto, porém, não
permitem que suas previsões futuras sejam definidas. A previsão da qualidade pode ser
obtida calculando indicadores de desempenho usando as medidas apresentadas. Entre esses
indicadores estão:
• Índice de Desempenho de Qualidade: representa a eficiência da qualidade de um
processo. Ao se obter uma determinada data, o indicador mostra se o não-
cumprimento é maior ou menor do que o esperado, permitindo, também, o cálculo de
projeções futuras sobre o desempenho da qualidade através do NC Estimado para a
Conclusão, conforme mostra a Figura 1. O cálculo desse índice se dá pela formula
(Eq. 7):
64
Equação 7
• ENC (d): representa o NC total esperado para uma determinada data. No final da
execução do projeto, ENC (d) deve ser igual a TENC; • INC (d) representa o NC total identificado para uma determinada data. Os valores
abaixo de 1 para o indicador significam que um número maior de não-cumprimento
do esperado está sendo encontrado. Os valores acima de 1 indicam que um número
menor de não conformidade do que é esperado está sendo encontrado.
Figura 1: Projeções TENC usando QPI
O objetivo do indicador de desempenho de qualidade é prever a quantidade de não-
cumprimento futuro, considerando o desempenho atual, e avaliar o impacto do desempenho
de qualidade nos custos do projeto. No entanto, é importante que o processo utilizado seja
conhecido, estável e que seus auditores tenham as habilidades necessárias para realizar suas
atividades.
Para avaliar a viabilidade do TENC, o progresso do projeto e as extensões das mudanças
ocorridas em relação à qualidade, num determinado intervalo de tempo, serão utilizados na
linha de base da qualidade, ou a medida TENC, e sua projeção chamada Estimativa de NC
para Conclusão, que pode ser obtida através do cálculo da fórmula seguinte (Eq. 8):
Equação 8
A técnica proposta sugere ainda que a Estimativa de NC para Conclusão possa ser usada para
obter Variações de Não-cumprimento (NCV) no TENC. Essa medida demonstra o quão
diferente é a qualidade esperada; segue equação abaixo (Eq. 9):
NCV = TENC – NCEC Equação 9
65
Baseado no NCV, a variação do custo deveria ser calculada e incorporada à Estimativa para
Conclusão do projeto. Isso pode ser feito através da adição da variação do custo de não-
cumprimento para o tradicional EAC, como está representado na seguinte fórmula (Eq. 10):
Equação 10
Onde:
• ECX ($) é a variação do custo de não conformidade, correspondente ao custo
(positivo ou negativo) da variação de não conformidade. A variação do não-
cumprimento (NCV), está sendo medida no eixo X da fig. 1, e será representado pela
Estimativa de custo extra para concluir (ECX ($)) (Eq. 11):
ECX($) = TENC($) – NCEC($) Equação 11
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
66
ARTIGO 08
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
An earned value model with risk analysis for project management under uncertain conditions. Moradi, Navid; Mousavi, S. Meysam; Vahdani, Behnam. Journal of Intelligent and Fuzzy Systems 2017.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo defende que, ao contrário do Gerenciamento de Valor Agregado, a análise de
risco considera as condições de risco para o desempenho futuro do projeto. Dessa maneira,
este trabalho propõe a integração da técnica de EVM com a análise de risco para uma melhor
previsão do desempenho futuro do projeto. Um projeto de construção é utilizado neste artigo
para demonstrar a utilização da técnica proposta.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma melhoria na técnica de gerenciamento de valor
agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado
Este estudo considera o gerenciamento de risco para complementar a técnica de
gerenciamento de valor agregado. De acordo com as possíveis variações no status futuro do
projeto, algumas fórmulas são sugeridas abaixo a fim de se considerar o efeito dos riscos nas
previsões finais:
3.2 Estimativa de custo ajustado fuzzy com valor de intervalo na conclusão
(AEAC)
Se o custo na conclusão estiver sob a influência dos índices atuais de desempenho de custo, o
Fuzzy-AEAC com valor de intervalo é obtido da seguinte forma (Eq. 1):
67
Equação 1
• Se o custo na conclusão estiver sob a influência dos índices atuais de desempenho de
custo e cronograma, o AEAC fuzzy com valor de intervalo é obtido da seguinte
forma;
• Se a duração das atividades remanescentes estiver progredindo com base no plano, o
valor de intervalo difuso de será obtido da maneira a seguir (Eq. 2):
Equação 2
3.3 Estimativa de programação ajustada difusa com valor de intervalo na
conclusão (AEAC(t)) (Eq. 3)
68
Equação 3
• : Se a duração das atividades remanescentes for influenciada pela tendência da
, o valor de intervalo Fuzzy de é obtido da maneira a seguir; (Eq. 4)
• : Se a duração das atividades remanescentes for influenciada pela tendência da
, o valor de intervalo Fuzzy de é obtido da maneira a seguir; (Eq. 5)
Equação 4
69
Equação 5
A classificação dos números difusos com valores de intervalos é calculada da seguinte forma
(Eq. 6):
Equação 6
- Interpretações relacionadas à comparação entre BAC e :
- O custo na conclusão do projeto será menor do que seu custo orçado.
- O custo na conclusão do projeto irá além de seu custo orçado.
- O custo na conclusão será igual ao seu custo orçado.
70
- Interpretações relacionadas à comparação entre PD e :
- O tempo de conclusão do projeto diminuirá em relação ao tempo planejado.
- O tempo de conclusão do projeto irá além do tempo planejado.
- O tempo de conclusão será igual ao tempo planejado.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
71
ARTIGO 09
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Fuzzy logic: An instrument for the evaluation of project status.
Radek, D. Revista de Metodos Cuantitativos para la Economia y la
Empresa 2015.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo demonstra uma descrição sobre os números Fuzzy, a lógica Fuzzy e os cálculos
do processo. Os autores focam na ideia de transformar os resultados de índices como o
Índice de Desempenho de Custo (CPI) e Índice de Desempenho de Cronogramas (SPI) em
expressões linguísticas que permitem a intepretação do status do projeto e a previsão de seu
desempenho.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma melhoria na técnica de gerenciamento de valor
agregado (EVM), utilizando os números Fuzzy.
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado
A melhoria proposta utiliza a lógica Fuzzy que consiste nos três pontos abaixo:
1. Fuzzification: Transforma variáveis reais em variáveis linguísticas usando os seus
atributos;
2. Inferência Fuzzy: Define o comportamento de um sistema usando regras definidas;
3. Defuzzification: Transfere os resultados em valores para expressões linguísticas que
permitem a interpretação do status do projeto.
Um exemplo dessa interpretação, demonstrado no estudo de caso do artigo, pode ser
demonstrado da seguinte maneira:
• Tem-se valores calculados para os indicadores de custo e de cronograma, como a
tabela seguinte.
72
A aplicação prática da integração do EVM com Fuzzy está representada em um problema
centrado no círculo gráfico em que o projeto está localizado (ponto (1,1)), quanto menores os
problemas do status do projeto (ponto (1,1)), maiores os problemas do status do projeto.
Os desvios dos índices comparados ao centro do gráfico podem representar seu atual status e
possíveis futuros caminhos a serem traçados.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
73
ARTIGO 10
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Hybrid artificial neural network and statistical model for forecasting project total duration in earned value management. Li, You; Liu, Lu. International Journal of Networking and Virtual Organisations 2012.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este artigo propõe uma nova abordagem híbrida, que inclui a rede neural artificial e o método
de simulação de número aleatório, a fim de prever o indicador de cronograma agregado de
cada período com base no status de vários períodos anteriores. Em seguida, um método
estatístico é aplicado para estimar a duração total do projeto e seus intervalos em cada
período. Resultados de experimentos comprovaram que este modelo híbrido proposto supera
o método de EVM.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma nova técnica de gerenciamento de projetos,
utilizando redes neurais, simulação de número aleatório e estatística.
3. Dados derivados das características de interesse declaradas nas questões
secundárias de pesquisa (quando aplicável):
Este estudo propõe uma nova técnica de gerenciamento de projetos através de um método
de cálculo estatístico baseado em no SPIt, partindo das seguintes equações (Eq. 1):
Equação 1
Onde:
• CL corresponde ao limite de confiança;
• indexp corresponde aos valores de índices periódicos;
74
• indexc corresponde aos índices cumulativos;
• SPI consiste no índice referente ao estudo;
• Z corresponde ao valor da distribuição t, mas também σ como o desvio padrão de
SPI;
• n consiste no número de observações;
• AF trata-se do fator de ajuste da população finita.
A partir destas, as alterações são realizadas alterando a utilização de formas curtas pelas de
formas longas e trabalhando em cima de duas hipóteses:
Na primeira hipótese, o índice de desempenho do cronograma do projeto com relação a parte
inacabada é diferente do SPIc,t cumulativa quando comparado ao IEACt clássica, descrito na
fórmula abaixo (Eq 2):
Equação 2
Neste caso, o índice de desempenho é igual ao valor de previsão , o qual é capaz de
medir o desempenho da forma inacabada de maneira mais eficiente que o SPIc,t .
Na segunda hipótese, os valores periódicos de EVp,t+1 , ACp,t+1 estão em conformidade com
a distribuição normal com o μ e σ2 , sendo μ a média do número T mais próximo do
periódico EVp,i, ACp,i , ESp,i (i=t-T-1,.....t) respectivamente, onde σ2 corresponde ao seu
desvio. Essa segunda ideia tem o princípio de expressar através do T, o desempenho da parte
futura do projeto mais inacabada de modo a obter os últimos valores de EV, AC e ES, mas
também uma possibilidade de prever melhor esse futuro desempenho.
Além disso, acredita-se que é possível obter valores aos periódicos EV, AC, ES números
aleatórios normais com os parâmetros de μ e σ2. Desta forma, propõe uma nova técnica a
partir de dois estágios:
3.1 Procedimento de Previsão ANN
Esse primeiro estágio conta com o emprego de dois nós de entrada, sendo uma camada
oculta e uma ANN de arquitetura do nó de saída para prever EVp,t+1. Neste trabalho, além do
ANN, são utilizados algoritmos de retropropagação como forma de treinar uma rede e dessa
forma possibilitar um sucesso das redes neurais.
Esse treinamento, de acordo com a segunda hipótese, atua com 1000 números, sendo esses
aleatórios, de distribuição normal para os periódicos EVp,t+1, ACp,t+1 e ESp,t+1,
respectivamente. Dessa forma, criou-se 1000 padrões, onde admitiu-se que cada ternário
correspondia de maneira aleatória a um padrão, de modo que cada um desses abrangia dentro
de suas possibilidades combinações entre EV, AC e ES de modo a criar uma simulação do
desempenho real. Então, utilizando da Teoria de Validação Cruzada, é selecionado de
maneira aleatória o conjunto de aprendizado, mas também o conjunto de validação e o
conjunto de teste do conjunto de treinamento, onde EVp,t+1 e ACp,t+1 são nós de entrada e
de ESp,t+1 sáida, Por fim, via modo de treinamento de padrão, após aprendizado e validação,
75
esse conjunto de teste é preenchido na ANN bem treinada, obtendo o valor de previsão
e assim .
3.2 Estimativa Estatística para Duração Total
Nesse segundo estágio, é utilizado o valor de previsão para cada período e dessa
forma calcular o índice do desempenho do projeto , aplicando nessa etapa a
primeira hipótese, utilizando desse índice para determinar o SPI da parte futura inacabada,
como sugerido anteriormente.
De maneira resumida, essa etapa da metodologia visa colocar o valor de previsão dentro de
um quadro estatístico como forma de realizar estimativas de intervalos para a duração total,
essa simulação de número aleatórios constituí um cenário capaz de simular tendências de
capacidade de desempenho, as quais são ajustadas ao diferentes ternários de EV, AC e ES.
Simultaneamente, é criado um para cada PFt prevendo assim a duração total do
projeto.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
76
ARTIGO 11
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Improve Tracking in the Software Development Projects; J. L.
Cuadrado-Garcia; J. J. Cuadrado-Gallego; M. A. Herranz-
Martinez; P. Rodriguez-Soria; Joint Conference of the 21st
International Workshop on Software Measurement, IWSM 2011
and the 6th International Conference on Software Process and
Product Measurement, MENSURA 2011
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este artigo tende a aprimorar a técnica de EVM através da utilização de curvas sigmóides ou
curvas S, gerando uma evolução do projeto modelando-o matematicamente como uma
função contínua. O método proposto neste estudo é então testado e validado através de um
conjunto de projetos da área de desenvolvimento de software.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor um aprimoramento na técnica EVM de gerenciamento
de projetos.
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta de aprimoramento da técnica EVM
O método EVM quando se utiliza de variáveis em função do tempo, como custos, horas
trabalhadas e porcentagem de trabalho, normalmente tem sua representação gráfica com uma
curva e forma de S ou sigmóide. Dessa forma através do projeto, o autor pretende solucionar
problemas com relação a equação diferencial que origina a curva ‘S’, de modo a criar uma
evolução na estimativa dos custos totais e podendo adaptá-lo a qualquer projeto. A
necessidade de solucionar esse problema se deve ao sistema ser limitado a crescimentos
exponenciais do projeto, dessa forma propõe uma equação logística afim de gerar estimativas
mais realistas (Eq. 1).
Equação 1
77
Nessa equação logística, P(t) e α correspondem a parâmetros, em meio a isso adiciona-se um
fator de feedback negativo com o intuito de reduzir a taxa de crescimento quando o sistema
aproxima-se da sua capacidade de carga (k), ou quando está próximo ao valor de k. Em meio
a isso, obtém-se a solução dessa equação (Eq. 2):
Equação 2
A partir dessa equação, já solucionada, tem-se α como parâmetro correspondente à largura da
curva, mas também ao seu declive, sendo totalmente aconselhável substituí-la por uma
variável especificando o tempo para continuar, o qual deve ser entre 10-90% do limite k. A
variável normalmente que serve como substituta ao α, consiste na Δt, período denominado
como recurso “comprimento”, onde (Eq. 3):
Δt =ln(80)α→ resultando em,
Equação 3
Além disso, fatores como tµ consiste em uma variável referente ao tempo necessário para a
curva atingir metade do limite k, também chamado de ponto médio da tendência crescente;
nesse ponto o modelo logístico é simétrico e definido tanto por tµ, quanto pelo limite k e Δt.
No gerenciamento de projetos a variável P(t) consiste no custo ou esforço do projeto. Para
um bom planejamento do projeto requer que o gerenciamento do custo seja acumulado e
dessa maneira não é viável a utilização de P0, sendo mais apropriado iniciar pelas condições
iniciais, onde P= 0 tende a t=0. A partir destes parâmetros iniciais, tem-se um crescimento
linear até o momento em que o tempo se torna muito grande a ponto de P≈P∞ e t=tf , sendo
de extrema importância seja diferente de t∞ uma vez que essa diferença representa a
igualdade entre a soma dos custos e o custo total do projeto. Então é possível dizer que k ≈ Pf
, obtendo assim a seguinte equação (Eq. 4).
Equação 4
Após todos ajustes realizados na equação logística acredita-se que esta seja capaz de gerar os
parâmetros Pf, Δt e tµ necessário para um bom ajuste. Então, através destes desenvolver uma
equação da curva S capaz de indicar o comportamento de cada um ou se o orçamento do
projeto funciona.
Por fim, com a possibilidade de obter cada parâmetro assim como a equação da curva S,
torna-se viável a implementação dessa equação logística ao método EVM, com o intuito da
realização através da curva obtida de previsões mais realistas e com uma simulação do
projeto até a sua conclusão, as quais tendem a ser mais vulneráveis.
78
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
79
ARTIGO 12
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Integrating Risk Assessment and Actual Performance for Probabilistic Project Cost Forecasting: A Second Moment Bayesian
Model. Kim, Byung-Cheol. IEEE Transactions on Engineering
Management 2015.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este artigo apresenta uma técnica de gerenciamento dos projetos que se utiliza do modelo
Bayesiano como base para realizá-lo. Primeiramente, apresenta um modelo que realiza a
junção de dados avaliativo de risco de custo do projeto com dados reais de desempenho,
dentro de um intervalo. Em um segundo modelo, integra entre o desempenho agregado
passado e futuro com a fração do projeto já concluída até o momento, este método atua na
variabilidade particular do desempenho dos custos, atuando de forma mais realista a projeção
desse gerenciamento. Por fim, esses modelos são implementados através de fórmulas
algébricas capazes de realizar a coleta de dados sem sobrecarregar o sistema ou a análise
estatística sofisticadas.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma nova técnica para gerenciamento de projetos
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
O modelo Bayesiano consiste em um ideal básico e intuitivo. Inicialmente, atua na
distribuição da linha base de um projeto de modo a estimá-la e tendo como base uma
avaliação prévia do custo do projeto. Esse método permite que se altere a distribuição prévia
do custo do projeto pela a atual e com novos dados do desempenho do mesmo.
Desse modo, através de uma estrutura matemática para realizar essa atualização, a qual pode
escrita a partir da Lei de Bayes (Eq. 1):
Equação 1
Onde, P(ϴ) consiste na distribuição prévia dos parâmetros ϴ, P (D| ϴ) é a probabilidade
condicional de um determinado resultado D que seria observado, dado ϴ; Além disso, P (D)
80
é a distribuição marginal do resultado D; e P (ϴ | D) é a distribuição posterior de ϴ dada D.
Por fim, adaptando a mesma a função ja conhecida EAC, usando CPI, temos (Eq. 2):
Equação 2
Onde, p (EAC) consiste em uma distribuição prévia, podendo ser atulida pela CPI em termos
de probabilidade condicional p(CPIm|EAC). Também tem-se, a distribuição marginal da
medida p(CPIm).
Essa adaptação do método SBS, Bayesiano, a técnica EAC utiliza-se do CPI como principal
medida do desempenho de custo de modo a referencia com COI, indice de superação dos
custos, onde (Eq. 3):
COI = CPI – 1 = AC/EV. Equação 3
Essa substituição do parâmetro CPI pelo COI se deve ao COI evoluir ao longo do tempo, mas
também ao fato desta ser variável aleatória com distribuição de probabilidade. Em meio a
isso, o COI possuí variáveis transitórias denominadas COI em progresso (COIm), com a
condição de m<N, onde N consiste no número de WPs do projeto. e variáveis de quando este
está completo COIconclusão (COIC).
Dessa maneira, o COI a distribuição prévia de EAC pode ser demonstrada como (Eq. 4):
Equação 4
Onde, COIc refere-se a variável relativa de possíveis excessos de custo em relação ao BAC,
mas também através desta obtém-se uma nova perspectiva sobre a previsão EAC. Outro fator
a ser citado é que o COIc atua como o problema de previsão do EAC originando dessa
maneira (Eq. 5):
Equação 5
Essa fórmula pode ser denominada com o EAC Bayesiano.
Com relação a distribuição prévia da COIc, sabe-se que a média da variação prévia do
mesmo pode ser calculada diretamente de uma média da distribuição de custos do projeto de
linha base, as quais podem ser obtidas através de uma simulação de técnicas como a de
Monte Carlo. A partir de então, juntamente com o método SMB esta tende a aproximar sua
81
distribuição normal com o custo do projeto, denotando parâmetros como a média(µB) e o
desvio padrão(ơB) do custo da distribuição. Como complementar ao método, utiliza-se de
BAC quando se inclui uma reserva referente a contingência CR e dessa maneira adiciona-se
o custo esperado, onde BAC = (μB + CR), de modo a calcular a média e o desvio padrão do
COIc pela expressão (Eq. 6):
Equação 6
Já em consideração a COIc posterior, utiliza-se também de fórmulas para gerar para gerar
dessa vez média e variância referente ao COIm, o qual quando possui seus parâmetros m
WPs, pode ser aproximado da distribuição normal. Dessa forma, tanto COIm quanto COIc
podem ser distribuídos normalmente, sendo assim é possível obter uma função de densidade
condicional com relação a uma distribuição normal bivariada, através do COIc posterior
como condição ao COIm. Então, a partir dessa distribuição bivariada torna-se cálculos de
EAC Bayesiano simplificados.
Por fim, com relação aos parâmetros de entrada e de saída desse modelo SMB, sabe-se que
trabalhando primeiramente na questão de entrada, esse modelo possui dois principais
elementos sendo eles a estimativa do segundo momento do custo total de Wp, as quais são
utilizadas para gerar a distribuição de todos os COIm e COIc. Como segundo elemento,
temos as medições reais dos COI’s, os quais são utilizados durante o projeto para projetar um
desempenho real e através de uma base bayesiana bivariada gerar a distribuição do COIc
condicional a medição de COIm = D.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
82
ARTIGO 13
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA
DO ARTIGO:
Monitoring project duration and cost in a construction project by
applying statistical quality control charts. Aliverdi, R., Moslemi Naeni,
L., Salehipour, A. International Journal of Project Management, 2013.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este estudo apresenta uma extensão do método de valor agregado no monitoramento e
análise do desempenho do projeto e do progresso do projeto. Embora, permita medição do
progresso do projeto, e pode revelar qualquer desvio de tempo e custo do plano, sua
capacidade de relatar o nível de desvio aceito não é bem estudado. Este estudo apresentou
uma abordagem para superar essa limitação, aplicando gráficos estatísticos de controle de
qualidade para monitorar índices de valor. Para este propósito, os índices de desempenho de
tempo e custo do projeto de um projeto de construção real foram monitorados através de
gráficos de controle.
2.2 Objetivo – Descrição do objetivo do artigo
Este artigo tem como objetivo propor uma melhoria na técnica de gerenciamento de valor
agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado
Controle Estatístico de Processo (CEP) é a aplicação de métodos estatísticos para monitorar
um processo com a finalidade de garantindo que produz produtos ou serviços em
conformidade. Todo processo experimenta variações., onde estas podem ser categorizadas
como controladas e não controladas. Variações controladas ou variações de causas comuns
são naturais para o processo. Na verdade, elas são inerentes ao processo e não são
consideradas tão importantes em comparação com variações não controladas. Por outro lado,
variações não controladas ou variações especiais de causa não são tipicamente apresentadas
no processo. É importante encontrar a causa de variações não controladas. O SPC é
desenvolvido para distinguir entre essas duas fontes de variações de processo.
Por este motivo, o SPC inclui um conjunto de ferramentas e técnicas, entre as quais os
gráficos estatísticos de controle de processos são uma das técnicas mais importantes.
83
Introduzido por Shewhart, os gráficos de controle têm sido amplamente aplicados a uma
variedade de indústrias e processos, esses gráficos de controle de Shewhart agora são
considerados como uma das principais ferramentas de monitoramento das variações e
mudanças nos processos. Pressupostos fundamentais das cartas de controle de Shewhart são:
• As medidas (amostras) nas quais os gráficos de controle são aplicados devem ser
estatisticamente distribuídos normalmente ou menos podendo ser aproximado pela
distribuição normal.
• As medições devem ser estatisticamente independentes entre si, sendo assim uma
medição observada não deve afetam outras medições.
Entre os gráficos de controle de Shewhart, gráficos de controle individuais que são
conhecidos como gráficos de controle XmR ou ImR podem ser aplicadas com sucesso para o
propósito deste estudo, de modo a monitorar estatisticamente a duração e o custo dos
projetos. As razões são:
• Os índices associados, ou seja, SPI e CPI são quantificável e pode levar valores
contínuos
• Estes EV e vários outros índices EV são observados semanalmente ou mensais.
Aplicando ImR, gráficos de controle para amostras SPI e CPI, mostra-se as variações
observado nos índices são causa comum da variação ou especial de causar tal variação. A
partir disso e também dependendo do grau de variações de causas especiais, o julgamento em
relação ao cronograma de custo do desempenho do projeto pode ser feito.
3.1.1 Limites de controle para cartas de controle individuais
O gráfico de controle ImR que monitora se existe uma variação de causa especial entre
amostras de tamanhos pequenos é composto de dois gráficos. O primeiro gráfico é chamado
"IX" e mostra o valor de cada amostra. O segundo gráfico ou faixa móvel, "MR", monitora a
variação entre dois gráficos consecutivos. (Eq. 1)
84
Equação 1
Onde,
• xi é cada observação individual e MRi = | xi − xi − 1 |.
3.1.2 Métodos para construir cartas de controle de ImR para amostras
distribuídas de forma não normal
De acordo com os limites de controle dos gráficos de controle IX e MR, é fácil perceber que
a distribuição estatística normal não é apresentada nas equações associadas. Entre vários
métodos para aplicar gráficos de controle de Shewhart para dados não distribuídos
normalmente, um método simples, consiste em transformar os dados não normais em dados
normalmente distribuídos.
Como os índices de VE devem ser medidos e monitorados por especialistas em projetos que
não estão muito familiarizados com estatísticas avançadas, e com relação ao fato de que os
gráficos de controle de ImR estão disponíveis para o propósito deste estudo, é preferível
empregar transformação.Duas importantes transformações são prospostas por Box-Cox e
Johnson. Na transformação Box – Cox, uma variável aleatória, X, é energizada para um
valor. Este valor é chamado λ e é o parâmetro de Box – Cox transformação. A transformação
Box – Cox é mostrada na equação abaixo (Eq. 2):
Equação 2
Onde,
• λ pode ter qualquer valor entre −5 e + 5. No caso de X = 0, a transformação funciona
de acordo com o logaritmo natural.
Vários softwares estatísticos, incluindo o Minitab, podem forneça o melhor valor de λ na
transformação Box – Cox. Uma desvantagem da transformação Box-Cox é que ela é
aplicável apenas a dados positivos. Apesar de Box-Cox, a transformação de Johnson pode ser
aplicada com sucesso a dados negativos. A transformação de Johnson é muito mais
complicada do que Box-Cox, embora também possa ser realizada por quase todos software
85
estatístico, incluindo o Minitab. Semelhante ao Box-Cox, o Minitab pode trazer a melhor
transformação de Johnson em dados normalmente distribuídos.
3.1.3 Aplicando gráficos de controle ImR para monitorar a duração e custo em
um projeto de construção
Partindo dos fundamentais de Shewhart em relação às amostras normalmente distribuídas, é
importante saber que se as amostras coletadas de medidas SPI e CPI seguem distribuição
estatística normal. No caso, se outras cartas de controle, ao em vez de cartas de controle do
Shewhart, forem implementadas, deve-se entender a distribuição estatística das amostras
como a etapa central. A razão é que todo gráfico de controle é desenvolvido de acordo com
várias suposições entre as quais o o mais importante é a distribuição estatística das amostras.
Então, para realizar esse monitoramento foram utilizados de dois softwares, o Minitab e o
Easyfit. Apesar da capacidade do Minitab de calcular e desenhar gráficos de controle, sua
capacidade de eterminar a distribuição estatística de amostras é limitada a apenas várias
distribuições conhecidas. A capacidade até cai mais quando o usuário deve ajustar as
distribuições uma a uma, enquanto o Minitab valida escolha. Por outro lado, o Easyfit é
desenvolvido com o propósito de determinar a distribuição estatística das amostras.
4. Relevância do Artigo
1 2 3 4 5
Pouco Relevante Excelente
86
ARTIGO 14
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Optimization study of Earned Value Method in construction project management. Ma, Xiao; Yang, Bin. International Conference on Information Management, Innovation Management and Industrial Engineering, ICIII 2012.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este artigo melhora o Método do Valor Agregado tradicional, introduzindo custos de
qualidade. Desta forma, torna o sistema de critérios de avaliação do EVM mais completos
introduz um índice de desempenho de qualidade no sistema de critérios de avaliação,
combinando o gerenciamento de custos, de cronogramas e de qualidade. O trabalho então
conduziu um estudo de caso para comparar o método proposto ao tradicional.
2.2 Objetivo – Descrição do objetivo do artigo
Propor uma melhoria na técnica de gerenciamento de valor agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado (EVM)
O chamado custo de qualidade refere-se à despesa paga para garantir e melhorar a qualidade
dos produtos e despesas perdidas para cumprir o padrão de qualidade.
Na técnica proposta da melhoria do método de valor agregado, será introduzido o custo de
qualidade como variável. Sendo assim, destacam-se três variáveis: O QBCWP (Custo de
Trabalho Orçado de Qualidade Realizado) é o custo de qualidade do orçamento do trabalho
acumulado realmente realizado no momento; QACWP (Qualidade do Custo real de trabalho
realizado), custo de qualidade real do trabalho efetivamente realizado acumulado; QBCWS
(Custo de Trabalho Programado de Qualidade Programado), custo de qualidade orçamentado
do trabalho acumulado realizado no momento.
O novo sistema de índice de desempenho é:
• Índice de desempenho da programação de qualidade: sua fórmula é QSPI = BCWP /
BCWS, com SPI maior, menor ou igual a 1, indicando o progresso em frente, atraso
ou coincidindo com o cronograma programado. Quando QSPI <l, devemos analisar
87
cuidadosamente a causa do atraso na programação e tomar medidas oportunas para
acelerar o progresso; quando QSPI> eu, também devemos analisar a causa [14]. Se o
progresso for executado antes do cronograma, porque o nível de qualidade diminui,
então devemos tomar medidas para elevar a qualidade, mesmo que o cronograma seja
atrasado.
• Índice de desempenho de custo de qualidade: sua fórmula é QCPI = BCWP /
ACWP, com QCPI maior, menor ou igual a I, indicando o custo decrescente,
aumentando ou coincidindo com o custo programado. Quando QCPI <I, devemos
analisar cuidadosamente a causa do aumento de custo para ver se é por causa do
cronograma e tomar medidas para diminuir o custo de acordo com a situação real.
Quando QCPI> 1, também devemos analisar a causa da diminuição do custo. Se diz
respeito à qualidade, devemos tornar a qualidade a prioridade.
• Índice de desempenho de qualidade: sua fórmula é QPI = QACW P / ACWP, com
QPI maior, menor ou igual a I, indicando que a economia de qualidade diminui,
aumenta ou coincide com o valor programado. Quando QPI> Qj, devemos analisar a
causa do aumento do custo de qualidade. Se for devido ao aumento da desagregação
da construção, podemos reduzir o custo de repartição e aumentar o custo de
prevenção para reduzir o custo de qualidade; Se é por causa do aumento do custo do
exame, podemos reduzir o custo do exame para reduzir o custo de qualidade. Quando
QPI <S Qj, também devemos analisar a causa e manter os fatores que não causaram a
redução do padrão de qualidade (QPI <S Qi) e melhorar o método de gerenciamento.
Comparando o método proposto com o método tradicional de EVM, percebe-se que o
primeiro além de indicar a execução do programa, também indica, por exemplo, que o
aumento do custo do projeto pode ter sido causado, em boa parte, pelo aumento do custo de
qualidade. Ou seja, esse método proposto é capaz de proporcionar a gestão de projetos
integrando cronograma, custos e qualidade.
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente
88
ARTIGO 15
ROTEIRO PARA RESUMO DOS ARTIGOS
1. Dados de identificação
REFERÊNCIA
COMPLETA DO
ARTIGO:
Quality: The Third Element of Earned Value Management.
Dodson, Marcelo; Defavari, Guilherme; de Carvalho, Vitor.
Procedia Computer Science 2015.
2. Dados derivados das características de interesse declaradas no
objetivo de estudo
2.1 Geral – Resumo da publicação
Este trabalho visa contribuir para estudos buscando adicionar o componente de qualidade
para o método de gestão de valor agregado, usando como fundo um estudo de caso em
operação agrícola. Assim, este estudo de caso considerado colheita de soja em uma fazenda
localizada no Brasil como um projeto. Propõe-se uma metodologia para calcular o valor
agregado de qualidade (QEV). Propõe-se fórmulas para estimar a variação de qualidade
(QV), número do índice de qualidade (QIN) e índice de desempenho de qualidade (QPI).
Foram identificados cinco indicadores de qualidade da colheita de soja que foram usadas
para ilustrar o método proposto. Além disso, ele foi avaliado a possibilidade de utilizar o
EVM para avaliar o desempenho operacional das culturas.
2.2 Objetivo – Descrição do objetivo do artigo
Propor uma melhoria na técnica de gerenciamento de valor agregado (EVM).
3. Dados derivados das características de interesse declaradas nas
questões secundárias de pesquisa (quando aplicável):
3.1 Proposta da melhoria na técnica de gerenciamento de valor agregado (EVM)
Destaca-se como propósito do Valor Agregado de Qualidade (QEV) a medida da capacidade
do projeto de entregar os requisitos de qualidade definidos pelo stakeholder do projeto, ao
longo da execução do mesmo. Para validar a técnica a ser demonstrada, serão repassados
cada passo para a sua execução já aplicados ao modelo da colheita de soja.
O primeiro passo trata-se de identificar os indicadores de qualidade que se aplica a cada
atividade do processo. A partir desse momento, um plano de gerenciamento de qualidade foi
elaborado seguindo o Guia PMBOK 4ª. O próximo passo trata-se de definir os limites para
cada requisito de qualidade listado. Aqui também é inserido o Índice de Desempenho de
Qualidade, como pode ser visto na Figura 1.
89
Figura 1: Demonstrações do Índice de Desempenho de Qualidade
Após definir os limites, a equipe de gerenciamento de qualidade monitora e controla o
projeto juntamente com a equipe de gerenciamento de custos e tempo. Foram coletados
dados antes e depois da colheita de soja, de um mesmo local, para que seja possível calcular
a porcentagem de amostras que se encontrava entre o Limite de Especificação Inferior (LSL)
e o Limite de Especificação Superior (USL).
Numa próxima etapa, será calculo o Valor Agregado de Qualidade para determinada tarefa.
Destaca-se ainda que todos os dias os dados de custos e prazos foram coletados juntamente
com os dados de qualidade.
Como ilustração de toda essa aplicação da técnica ao modelo escolhido, a tabela 2 apresenta
todas as combinações possíveis entre cronograma, custos e qualidade.
Figura 2: Combinações entre cronograma, custos e qualidade.
Concluindo o estudo, este artigo teve como objetivo contribuir para inclusão do componente
de qualidade no método EVM. O objetivo secundário era apresentar a possibilidade de usar o
EVM para avaliar o desempenho operacional da agricultura, como é mostrado no gráfico a
seguir.
90
4. Relevância do Artigo
1 2 3 4 X
Pouco Relevante Excelente