OBRA: Construção do Campus Itacoatiara Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM. COMPOSIÇÕES UNITÁRIAS LEIS SOCIAIS0:85,34% DATA BASE: ABRIL/2013 CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL COMP1 LIGAÇÃO PROVISORIA DE AGUA UN 12769 HIDROMETRO 1,5 M3/H UN 1,000 58,70 58,70 9868 TUBO PVC SOLDAVEL EB-892 P/AGUA FRIA PREDIAL DN 25MM M 40,000 1,92 76,80 6116 AJUDANTE DE ENCANADOR H 2,000 6,66 13,32 2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 6,000 8,17 49,02 PREÇO (MATERIAL) 135,50 PREÇO (MAO-DE-OBRA) 62,34 PREÇO TOTAL + LS(SINAPI) 197,84 BDI (%) 24,96% 49,38 PREÇO TOTAL UNIT. (c/ taxa): 247,22 COMP6 TELHA METALICA TIPO SANDUICHE PRÉ-PINTADA BRANCA 6MM M2 1610 MASSA PRONTA P/ VEDACAO TP CARBOLASTICO CINZA DA OTTO BAUMGART CJ 0,004 14,86 0,06 4381 PARAFUSO ROSCA SOBERBA ACO ZINC CABECA CHATA FENDA SIMPLES 8 X 100MM UN 0,082 0,66 0,05 TELHA EM ACO ZIPADA 50MM - MODELO SANDUICHE COM TP-40 M2 1,060 203,76 215,99 6115 AJUDANTE H 0,220 6,04 1,33 12869 TELHADISTA H 0,220 8,17 1,80 PREÇO (MATERIAL) 216,10 PREÇO (MAO-DE-OBRA) 3,13 PREÇO TOTAL + LS(SINAPI) 219,23 BDI (%) 24,96% 54,72 PREÇO TOTAL UNIT. (c/ taxa): 273,95 COMPCM_191 COBERTURA MEIA CIRCUNFERENCIA EM POLICARBONATO M2 1610 MASSA PRONTA P/ VEDACAO TP CARBOLASTICO CINZA DA OTTO BAUMGART CJ 0,004 14,86 0,06 4381 PARAFUSO ROSCA SOBERBA ACO ZINC CABECA CHATA FENDA SIMPLES 8 X 100MM UN 0,082 0,66 0,05 COBERTURA MEIA CIRCUNFERENCIA EM POLICARBONATO M2 1,060 194,33 205,99 6115 AJUDANTE H 0,220 6,04 1,33 12869 TELHADISTA H 0,220 8,17 1,80 PREÇO (MATERIAL) 206,10 PREÇO (MAO-DE-OBRA) 3,13 PREÇO TOTAL + LS(SINAPI) 209,23 BDI (%) 24,96% 52,22 PREÇO TOTAL UNIT. (c/ taxa): 261,45 COMP2 DIVISORIA EM GESSO ACARTONADO M2 367 DIVISORIA DE GESSO ACARTONADO - FORN. E INS TALAÇÃO M2 1,050 65,00 68,25 PREÇO (MATERIAL) 68,25 PREÇO (MAO-DE-OBRA) 0,00

Upload: vanminh

Post on 09-Dec-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP1 LIGAÇÃO PROVISORIA DE AGUA UN

12769 HIDROMETRO 1,5 M3/H UN 1,000 58,70 58,70

9868

TUBO PVC SOLDAVEL EB-892 P/AGUA FRIA PREDIAL

DN 25MM M 40,000 1,92 76,80

6116 AJUDANTE DE ENCANADOR H 2,000 6,66 13,32

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 6,000 8,17 49,02

PREÇO (MATERIAL) 135,50

PREÇO (MAO-DE-OBRA) 62,34

PREÇO TOTAL + LS(SINAPI) 197,84

BDI (%) 24,96% 49,38

PREÇO TOTAL UNIT. (c/ taxa): 247,22

COMP6

TELHA METALICA TIPO SANDUICHE PRÉ-PINTADA

BRANCA 6MM M2

1610

MASSA PRONTA P/ VEDACAO TP CARBOLASTICO

CINZA DA OTTO BAUMGART CJ 0,004 14,86 0,06

4381

PARAFUSO ROSCA SOBERBA ACO ZINC CABECA

CHATA FENDA SIMPLES 8 X 100MM UN 0,082 0,66 0,05

TELHA EM ACO ZIPADA 50MM - MODELO

SANDUICHE COM TP-40 M2 1,060 203,76 215,99

6115 AJUDANTE H 0,220 6,04 1,33

12869 TELHADISTA H 0,220 8,17 1,80

PREÇO (MATERIAL) 216,10

PREÇO (MAO-DE-OBRA) 3,13

PREÇO TOTAL + LS(SINAPI) 219,23

BDI (%) 24,96% 54,72

PREÇO TOTAL UNIT. (c/ taxa): 273,95

COMPCM_191

COBERTURA MEIA CIRCUNFERENCIA EM

POLICARBONATO M2

1610

MASSA PRONTA P/ VEDACAO TP CARBOLASTICO

CINZA DA OTTO BAUMGART CJ 0,004 14,86 0,06

4381

PARAFUSO ROSCA SOBERBA ACO ZINC CABECA

CHATA FENDA SIMPLES 8 X 100MM UN 0,082 0,66 0,05

COBERTURA MEIA CIRCUNFERENCIA EM

POLICARBONATO M2 1,060 194,33 205,99

6115 AJUDANTE H 0,220 6,04 1,33

12869 TELHADISTA H 0,220 8,17 1,80

PREÇO (MATERIAL) 206,10

PREÇO (MAO-DE-OBRA) 3,13

PREÇO TOTAL + LS(SINAPI) 209,23

BDI (%) 24,96% 52,22

PREÇO TOTAL UNIT. (c/ taxa): 261,45

COMP2 DIVISORIA EM GESSO ACARTONADO M2

367

DIVISORIA DE GESSO ACARTONADO - FORN. E INS

TALAÇÃO M2 1,050 65,00 68,25

PREÇO (MATERIAL) 68,25

PREÇO (MAO-DE-OBRA) 0,00

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL + LS(SINAPI) 68,25

BDI (%) 24,96% 17,04

PREÇO TOTAL UNIT. (c/ taxa): 85,29

COMP106 FORRO GESSO ACARTONADO M2

1106 FORRO DE GESSO ACARTONADO FORNEC. E INSTAL. M2 1,050 36,00 37,80

PREÇO (MATERIAL) 37,80

PREÇO (MAO-DE-OBRA) 0,00

PREÇO TOTAL + LS(SINAPI) 37,80

BDI (%) 24,96% 9,43

PREÇO TOTAL UNIT. (c/ taxa): 47,23

COMP107 PISO EM CARPETE M2

10710 CARPETE DE NYLON E = 6MM COLOCADO M2 1,050 50,44 52,96

12890

CORDAO DE NYLON P/ PISO DE CARPETE -

COLOCADO M 0,700 4,69 3,28

20278

ASSENTAMENTO DE CARPETE - SOMENTE MAO DE

OBRA M2 1,300 4,11 5,34

PREÇO (MATERIAL) 56,24

PREÇO (MAO-DE-OBRA) 5,34

PREÇO TOTAL + LS(SINAPI) 61,59

BDI (%) 24,96% 15,37

PREÇO TOTAL UNIT. (c/ taxa): 76,96

COMP108

GRANITO CINZA POLIDO ESPESSURA 2CM,

ASSENTADO COM ARGAMASSA COLANTE DUPLA

COLAGEM M2

1380 CIMENTO BRANCO KG 0,211 2,32 0,49

1381

ARGAMASSA OU CIMENTO COLANTE EM PO PARA

FIXACAO DE PECAS CERAMICAS KG 8,000 0,35 2,80

25931

DISCO DE CORTE DIAMANTADO - 7", PARA

ESMERILHADEIRA, SEGMENTADO, PARA CONCRETO UN 0,010 74,46 0,74

10841 GRANITO CINZA POLIDO PARA PISO E = 2 CM M2 1,050 153,37 161,04

242 AJUDANTE ESPECIALIZADO H 0,500 10,33 5,17

4755 MARMORISTA/GRANITEIRO H 0,500 8,17 4,09

PREÇO (MATERIAL) 165,07

PREÇO (MAO-DE-OBRA) 9,25

PREÇO TOTAL + LS(SINAPI) 174,32

BDI (%) 24,96% 43,51

PREÇO TOTAL UNIT. (c/ taxa): 217,83

COMP109

PISO EM BLOCO SEXTAVADO 30X30CM, ESPESSURA

10CM, ASSENTADO SOBRE COLCHAO DE AREIA

ESPESSURA 6CM M2

367 AREIA GROSSA M3 0,060 48,12 2,91

1379 CIMENTO PORTLAND COMUM CP II- 32 KG 0,564 0,70 0,39

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

11118

BLOCO SEXTAVADO P/ PAVIMENTAÇÃO, EM

CONCRETO DE 35 MPA (TIPO BLOKRET) E = 9,0CM,

DE 30 X 30CM, DEACORDO COM NBR 9780 / 9781 UN 12,000 4,32 51,80

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,400 6,04 2,42

4750 PEDREIRO H 0,200 8,17 1,63

PREÇO (MATERIAL) 55,10

PREÇO (MAO-DE-OBRA) 4,05

PREÇO TOTAL + LS(SINAPI) 59,15

BDI (%) 24,96% 14,76

PREÇO TOTAL UNIT. (c/ taxa): 73,91

COMP110 SOLEIRA GRANITO 15 X 3CM M

20232 SOLEIRA GRANITO 15 X 3CM M 1,000 77,73 77,73

4750 PEDREIRO H 0,150 8,17 1,23

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,100 6,04 0,60

PREÇO (MATERIAL) 77,73

PREÇO (MAO-DE-OBRA) 1,83

PREÇO TOTAL + LS(SINAPI) 79,56

BDI (%) 24,96% 19,86

PREÇO TOTAL UNIT. (c/ taxa): 99,42

COMP_PAC

PINTURA EM RESINA ACRÍLICA PARA PISOS DE ALTA

RESISTENCIA - DUAS DEMÃOS M2

5318 SOLVENTE DILUENTE A BASE DE AGUARRAS L 0,100 8,00 0,80

154 RESINA ACRILICA L 0,269 17,53 4,71

12873 IMPERMEABILIZADOR H 0,200 8,17 1,63

6111 SERVENTE H 0,200 6,04 1,21

PREÇO (MATERIAL) 5,51

PREÇO (MAO-DE-OBRA) 2,84

PREÇO TOTAL + LS(SINAPI) 8,35

BDI (%) 24,96% 2,09

PREÇO TOTAL UNIT. (c/ taxa): 10,44

COMP3

PORTA EM VIDRO TEMPERADO E=10mm, COM

ACIONAMENTO AUTOMATICO, INCLUSO

FERRAGENS E INSTALAÇÃO M2

10507 VIDRO TEMPERADO INCOLOR 10MM M2 1,020 162,17 165,41

8183_ORSE

Kit de automatização de abertura de portas

deslizantes de 3,30m, incluso: mão de obra, central

eletrônica com inversor de frequencia,

motorredutor(es), kit de ferragem, UN 1,000 5.900,00 5.900,00

PREÇO (MATERIAL) 6.065,41

PREÇO (MAO-DE-OBRA) 0,00

LEIS SOCIAIS(%) 130,70% 0,00

PREÇO TOTAL + LS(SINAPI) 6.065,41

BDI (%) 24,96% 1.513,93

PREÇO TOTAL UNIT. (c/ taxa): 7.579,34

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP_PCF

PORTA DE ABRIR-FECH. ANTI-PÂNICO

(60+60)X210CM UN

PORTA ANTI-PANICO COMPLETA UN 1,000 940,52 940,52

6111 SERVENTE H 3,750 6,04 22,65

1214 CARPINTEIRO H 3,750 8,17 30,64

PREÇO (MATERIAL) 940,52

PREÇO (MAO-DE-OBRA) 53,29

PREÇO TOTAL + LS(SINAPI) 993,81

BDI (%) 24,96% 248,05

PREÇO TOTAL UNIT. (c/ taxa): 1.241,86

COMP4

JANELA DE VIDRO TEMPERADO EM ALUMINIO DE

CORRER M2

10502 VIDRO TEMPERADO COR 10MM M2 1,050 202,19 212,30

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 3,500 6,04 21,14

2700 MONTADOR H 3,500 12,43 43,51

PREÇO (MATERIAL) 212,30

PREÇO (MAO-DE-OBRA) 64,65

PREÇO TOTAL + LS(SINAPI) 276,94

BDI (%) 24,96% 69,13

PREÇO TOTAL UNIT. (c/ taxa): 346,07

COMP5

JANELA DE CORRER EM ALUMÍNIO, SÉRIE 25, SEM

BANDEIRA, COM 4 FOLHAS PARA VIDRO M2

597

JANELA ALUMINIO CORRER SERIE 25 FLS P/ VIDRO S/

BANDEIRA 160CM X 110CM M2 1,000 235,72 235,72

242 AJUDANTE ESPECIALIZADO H 1,100 10,33 11,36

4750 PEDREIRO H 0,500 8,17 4,09

6110 SERRALHEIRO H 1,100 8,17 8,99

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,800 6,04 4,83

PREÇO (MATERIAL) 235,72

PREÇO (MAO-DE-OBRA) 29,27

PREÇO TOTAL + LS(SINAPI) 264,99

BDI (%) 24,96% 66,14

PREÇO TOTAL UNIT. (c/ taxa): 331,13

COMP9

ELETROCALHA TIPO LEVE PERFURADA EM "U" -

35X70X300mm M

ELETROCALHA TIPO LEVE PERFURADA EM "U" -

35X70X300mm M 1,000 33,10 33,10

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,500 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,565 6,62 3,74

PREÇO (MATERIAL) 33,10

PREÇO (MAO-DE-OBRA) 9,95

PREÇO TOTAL + LS(SINAPI) 43,05

BDI (%) 24,96% 10,75

PREÇO TOTAL UNIT. (c/ taxa): 53,79

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP11 TOMADA 2P + T - 20A - 250V NO PISO UN

12145 TOMADA 2P + T - 20A - 250V NO PISO UN 1,000 13,60 13,60

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,320 12,42 3,97

6113 AJUDANTE DE ELETRICISTA H 0,320 6,62 2,12

PREÇO (MATERIAL) 13,60

PREÇO (MAO-DE-OBRA) 6,09

PREÇO TOTAL + LS(SINAPI) 19,69

BDI (%) 24,96% 4,92

PREÇO TOTAL UNIT. (c/ taxa): 24,61

COMP14 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 3" UN

1877 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 3" UN 1,000 22,34 22,34

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,000 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,000 6,62 6,62

PREÇO (MATERIAL) 22,34

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 41,38

BDI (%) 24,96% 10,33

PREÇO TOTAL UNIT. (c/ taxa): 51,71

COMP_ABRAÇ ABRAÇADEIRA TIPO CHAVETA 1"

ABRAÇADEIRA TIPO CHAVETA 1" UN 1,000 1,00 1,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,42 1,86

PREÇO (MATERIAL) 1,00

PREÇO (MAO-DE-OBRA) 1,86

PREÇO TOTAL + LS(SINAPI) 2,86

BDI (%) 24,96% 0,71

PREÇO TOTAL UNIT. (c/ taxa): 3,58

COMPCM_236 UN

ESTAÇÃO DE TRATAMENTO DE ESGOTO COMPACTA

PARA TRATAMENTO DE EFLUENTE DOMÉSTICO COM

VAZÃO MÉDIA DE 70M3/DIA-SISTEMA AERÓBIO POR

LODOS ATIVADOS COM SISTEMA DE DESINFECÇÃO

POR CLORAÇÃO. SISTEMA COMPLETO COMPOSTO

POR GRADEAMENTO/BOMBEAMENTO/LODOS

ATIVADOS MONOBLOCO/CLORADOR/MEIDÇÃO DE

VAZÃO/SISTEMA DE AUTOMAÇÃO E EQUIPAMENTOS

RESERVA ( BOMBA SUBMERSA E BOMBA

CENTRIFUGA), FORN. E INSTALAÇÃO UN 1,000 151.847,33 151.847,33

FRETES UN 1,000 19.000,00 19.000,00

PREÇO (MATERIAL) 170.847,33

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI) 170.847,33

BDI (%) 24,96% 42.643,49

PREÇO TOTAL UNIT. (c/ taxa): 213.490,82

ESTAÇÃO DE TRATAMENTO DE ESGOTO COMPACTA PARA TRATAMENTO DE

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_235

PEFURAÇÃO DE POÇO CONFORME ORIENTAÇÃO DA

CPRM - COM PROFUNDIDADE DE 105 M, DIÂMETRO

DE PERFURAÇÃO 15" TUBULAÇÃO GEOMECÂNICA

DE 8", COM BOMBA SUBMERSA DE 10CV, COM

APRESENTAÇÃO DO PERFIL, MEMORIAL

DESCRITIVO, ART E REGISTRO NO IPAAM.

M

PEFURAÇÃO DE POÇO CONFORME ORIENTAÇÃO DA

CPRM - COM PROFUNDIDADE DE 105 M, DIÂMETRO

DE PERFURAÇÃO 15" TUBULAÇÃO GEOMECÂNICA DE

8", COM BOMBA SUBMERSA DE 10CV, COM

APRESENTAÇÃO DO PERFIL, MEMORIAL DESCRITIVO,

ART E REGISTRO NO IPAAM.

M 1,000 650,00 650,00

PREÇO (MATERIAL) 650,00

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI) 650,00

BDI (%) 24,96% 162,24

PREÇO TOTAL UNIT. (c/ taxa): 812,24

COMPCM_163DISJUNTOR TRIPOLAR 60A - 25KA, REF. SIEMENS,

PRIMELETRICA OU LOUSANO - FORN E INSTUN

DISJUNTOR TRIPOLAR 60A - 25KA, REF. SIEMENS,

PRIMELETRICA OU LOUSANO UN 1,000 147,23 147,23

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,400 12,42 4,97

6113 AJUDANTE DE ELETRICISTA H 0,400 6,62 2,65

PREÇO (MATERIAL) 147,23

PREÇO (MAO-DE-OBRA) 7,62

PREÇO TOTAL + LS(SINAPI) 154,85

BDI (%) 24,96% 38,65

PREÇO TOTAL UNIT. (c/ taxa): 193,50

COMPCM_164

DISJUNTOR NORMA DIN CURVA C UNIPOLAR 10 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO - FORN

E INST

UN

20008

DISJUNTOR NORMA DIN CURVA C UNIPOLAR 10 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO

UN 1,000 9,16 9,16

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,400 12,42 4,97

6113 AJUDANTE DE ELETRICISTA H 0,400 6,62 2,65

PREÇO (MATERIAL) 9,16

PREÇO (MAO-DE-OBRA) 7,62

PREÇO TOTAL + LS(SINAPI) 16,78

BDI (%) 24,96% 4,19

PREÇO TOTAL UNIT. (c/ taxa): 20,96

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_165

DISJUNTOR NORMA DIN CURVA C UNIPOLAR 25 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO - FORN

E INST

UN

14544

DISJUNTOR NORMA DIN CURVA C UNIPOLAR 25 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO UN 1,000 9,21 9,21

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,400 12,42 4,97

6113 AJUDANTE DE ELETRICISTA H 0,400 6,62 2,65

PREÇO (MATERIAL) 9,21

PREÇO (MAO-DE-OBRA) 7,62

PREÇO TOTAL + LS(SINAPI) 16,83

BDI (%) 24,96% 4,20

PREÇO TOTAL UNIT. (c/ taxa): 21,03

COMPCM_166

DISJUNTOR NORMA DIN CURVA C TRIPOLAR 32 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO - FORN

E INST

UN

2384

DISJUNTOR NORMA DIN CURVA C TRIPOLAR 32 A

REF. SIEMENS, PRIMELETRICA OU LOUSANO UN 1,000 44,55 44,55

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,400 12,42 4,97

6113 AJUDANTE DE ELETRICISTA H 0,400 6,62 2,65

PREÇO (MATERIAL) 44,55

PREÇO (MAO-DE-OBRA) 7,62

PREÇO TOTAL + LS(SINAPI) 52,17

BDI (%) 24,96% 13,02

PREÇO TOTAL UNIT. (c/ taxa): 65,19

COMPCM_002 DISPOSITIVO DR BIPOLAR 30mA/25A - FORN E INST. UN

DISPOSITIVO DR BIPOLAR 30mA/25A UN 1,000 112,00 112,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,42 1,86

PREÇO (MATERIAL) 112,00

PREÇO (MAO-DE-OBRA) 1,86

PREÇO TOTAL + LS(SINAPI) 113,86

BDI (%) 24,96% 28,42

PREÇO TOTAL UNIT. (c/ taxa): 142,28

COMPCM_167

ELETRODUTO DE AÇO GALVANIZADO, PESADO,

Ø100MM (Ø4") , 6M, COM LUVAS. - FORN E INST

UN

21132

ELETRODUTO DE AÇO GALVANIZADO, PESADO,

Ø100MM (Ø4") , 6M, COM LUVAS. UN 1,000 74,31 74,31

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,000 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,000 6,62 6,62

PREÇO (MATERIAL) 74,31

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 93,35

BDI (%) 24,96% 23,30

PREÇO TOTAL UNIT. (c/ taxa): 116,65

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_168

ELETRODUTO PEAD, ARAME GUIA, 100MM COM

LUVAS, KANAFLEX OU EQUIVALENTE - FORN E INST

M

ELETRODUTO PEAD, ARAME GUIA, 100MM COM

LUVAS, KANAFLEX OU EQUIVALENTE M 1,000 5,39 5,39

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,150 6,62 0,99

PREÇO (MATERIAL) 5,39

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 8,25

BDI (%) 24,96% 2,06

PREÇO TOTAL UNIT. (c/ taxa): 10,30

COMPCM_169ELETRODUTO PEAD, ARAME GUIA, 25MM COM

LUVAS, KANAFLEX OU EQUIVALENTEM

ELETRODUTO PEAD, ARAME GUIA, 25MM COM

LUVAS, KANAFLEX OU EQUIVALENTE M 1,000 7,50 7,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,150 6,62 0,99

PREÇO (MATERIAL) 7,50

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 10,36

BDI (%) 24,96% 2,58

PREÇO TOTAL UNIT. (c/ taxa): 12,94

COMPCM_170

ELETRODUTO PEAD, ARAME GUIA, 50MM COM

LUVAS, KANAFLEX OU EQUIVALENTE - FORN E INST

M

ELETRODUTO PEAD, ARAME GUIA, 50MM COM

LUVAS, KANAFLEX OU EQUIVALENTE M 1,000 9,50 9,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,150 6,62 0,99

PREÇO (MATERIAL) 9,50

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 12,36

BDI (%) 24,96% 3,08

PREÇO TOTAL UNIT. (c/ taxa): 15,44

COMPCM_171

ESCAVAÇÃO MANUAL DE VALAS CAIXAS E

REATERRO M3

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 6,250 6,04 37,75

PREÇO (MATERIAL) 0,00

PREÇO (MAO-DE-OBRA) 37,75

PREÇO TOTAL + LS(SINAPI) 37,75

BDI (%) 24,96% 9,42

PREÇO TOTAL UNIT. (c/ taxa): 47,17

COMPCM_057

ROLO FITA ISOLANTE AUTO FUSÃO

7MMX19MMX10M - FORN E INST UN

404 FITA ISOLANTE AUT FUSÃO 7MMX19MMX10M M 10,000 1,16 11,60

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,42 0,62

PREÇO (MATERIAL) 11,60

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 12,22

BDI (%) 24,96% 3,05

PREÇO TOTAL UNIT. (c/ taxa): 15,27

COMPCM_058

ROLO

FITA ISOLANTE PLASTICA 7MMX19MMX10M -

FONR E INST UN

20110 FITA ISOLANTE PLASTICA 7MMX19MMX10M UN 1,000 2,99 2,99

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,42 0,62

PREÇO (MATERIAL) 2,99

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 3,61

BDI (%) 24,96% 0,90

PREÇO TOTAL UNIT. (c/ taxa): 4,51

COMPCM_17

2

LAMPADA ,VAPOR DE MERCÚRIO, ALTA PRESSÃO,

400W, 127V, 60Hz, E-27 - FORN E INST

UN

3751 LAMPADA ,VAPOR DE MERCÚRIO, ALTA PRESSÃO,

400W, 127V, 60Hz, E-27

UN 1,000 20,11

20,11

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,100 6,62 0,66

PREÇO (MATERIAL) 20,11

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 22,01

BDI (%) 24,96% 5,49

PREÇO TOTAL UNIT. (c/ taxa): 27,51

COMPCM_11

5

LÂMPADA VAPOR DE SÓDIO, 150W-127V-60HZ, E-

40, (PHILIPS, OSRAM, GE, SYLVÂNIA OU

EQUIVALENTE DE MESMO PADRÃO DE QUALIDADE)

- FORN E INST

UN

12216 LAMPADA ,VAPOR DE SÓDIO, ALTA PRESSÃO, 150W,

127V, 60Hz, E-40

UN 1,000 19,55

19,55

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,100 6,62 0,66

PREÇO (MATERIAL) 19,55

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 21,45

BDI (%) 24,96% 5,35

PREÇO TOTAL UNIT. (c/ taxa): 26,81

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_17

6

LUMINÁRIA FECHADA, PARA QUATRO LÂMPADAS A

VAPOR DE SÓDIO DE 150W-127V-60HZ. POSTE DE

FERRO ENGASTADO GALVANIZADO POR IMERSÃO

A QUENTE, 6m DE ALTURA TOTAL, COM JANELA DE

INSPEÇÃO. - FORN E INST

UN

LUMINÁRIA FECHADA, PARA QUATRO LÂMPADAS A

VAPOR DE SÓDIO DE 150W-127V-60HZ. POSTE DE

FERRO ENGASTADO GALVANIZADO POR IMERSÃO A

QUENTE, 6m DE ALTURA TOTAL, COM JANELA DE

INSPEÇÃO.

UN 1,000 711,80

711,80

73341

GUINDAUTO CAPAC 3,5T APROX 2M ALCANCE VERT

7M (CP) SOBRE CHASSIS DE CAMINHAO (EXCL ESTE)

EXCL OPERADOR H 1,500 20,44 30,66

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 5,000 12,42 62,10

6113 AJUDANTE DE ELETRICISTA H 5,000 6,62 33,10

PREÇO (MATERIAL) 742,46

PREÇO (MAO-DE-OBRA) 95,20

PREÇO TOTAL + LS(SINAPI) 837,66

BDI (%) 24,96% 209,08

PREÇO TOTAL UNIT. (c/ taxa): 1.046,74

COMPCM_17

3

MASSA DE CALAFETAÇÃO ISOLAÇÃO 15KV,

500GRAMAS - FORN E INST

UN

11604 MASSA DE CALAFETAÇÃO ISOLAÇÃO 15KV,

500GRAMAS

UN 1,000 10,54

10,54

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,42 1,24

PREÇO (MATERIAL) 10,54

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 11,78

BDI (%) 24,96% 2,94

PREÇO TOTAL UNIT. (c/ taxa): 14,72

COMP_DISP DISPOSITIVO DE PROTEÇÃO CONTRA SURTOS

(D.P.S.) 275V DE 8 A 40KA

UN

3939 DISPOSITIVO DE PROTEÇÃO CONTRA SURTOS(DPS)

275V DE 8 A 40KA

UN 1,000 110,00

110,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,000 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,000 6,62 6,62

PREÇO (MATERIAL) 110,00

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 129,04

BDI (%) 24,96% 32,21

PREÇO TOTAL UNIT. (c/ taxa): 161,25

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_175

QGD-2-FORNECIMENTO E MONTAGEM DE

ARMÁRIO DE DISTRIBUIÇÃO METÁLICO DE

SOBREPOR, 1000X800X250MM, EM CHAPA DE AÇO

14; ESPELHO EM POLICARBONATO; ISOLAÇÃO IP54 ;

TRATAMENTO: BANHO QUÍMICO DESENGRAXANTE

E FOSFOTIZAÇÃO À BASE DE FOSFATO DE FERRO;

CAIXA E TAMPA: COR BEGE (RAL 7032), PLACA DE

MONTAGEM, EM CHAPA DE AÇO 12: COR LARANJA

(RAL 2004), PINTURA ELETROSTÁTICA EPOXÍ A PÓ;

TODOS OS CIRCUITOS IDENTIFICADOS ATRAVÉS DE

ANILHAS CONFORME NUMERAÇÃO NO PROJETO;

NA PARTE EXTERNA DA PORTA, PROTETORES DE

SURTO DE TENSÃO 20KA INCLUSIVE O NEUTRO;

280V; EXCELENTE ESTÉTICA E ESPAÇO SUFICIENTE

PARA RETIRADA E COLOCAÇÃO DE COMPONENTES;

BARRAMENTO PRINCIPAL ELETROLÍTICOS

COBREADOS TRIFÁSICOS PINTADOS NAS CORES:

FASE R-VERMELHA, FASE S- BRANCA, FASE T-

MARRON, NEUTRO- AZUL CLARO, TERRA- VERDE:

BARRAMENTO DE COBRE ELETROLÍTICO PINTADO,

15X2MM(1 1/2"X1/8"), IN=155A, ICC=20KA,

CONTENDO: PLAQUETA DE POLICARBONATO NA

PORTA IDENTIFICANDO O QUADRO E A TENSÃO

220/127V, E DEMAIS ACESSÓRIOS, CEMAR,

SIEMENS OU EQUIVALENTE. DE ACORDO COM

DIAGRAMA UNIFILAR

UN

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

MATCM_171

ARMÁRIO DE DISTRIBUIÇÃO METÁLICO DE

SOBREPOR, 1000X800X250MM, EM CHAPA DE AÇO

14; ESPELHO EM POLICARBONATO; ISOLAÇÃO IP54 ;

TRATAMENTO: BANHO QUÍMICO DESENGRAXANTE

E FOSFOTIZAÇÃO À BASE DE FOSFATO DE FERRO;

CAIXA E TAMPA: COR BEGE (RAL 7032), PLACA DE

MONTAGEM, EM CHAPA DE AÇO 12: COR LARANJA

(RAL 2004), PINTURA ELETROSTÁTICA EPOXÍ A PÓ;

TODOS OS CIRCUITOS IDENTIFICADOS ATRAVÉS DE

ANILHAS CONFORME NUMERAÇÃO NO PROJETO; NA

PARTE EXTERNA DA PORTA, PROTETORES DE SURTO

DE TENSÃO 20KA INCLUSIVE O NEUTRO; 280V;

EXCELENTE ESTÉTICA E ESPAÇO SUFICIENTE PARA

RETIRADA E COLOCAÇÃO DE COMPONENTES;

BARRAMENTO PRINCIPAL ELETROLÍTICOS

COBREADOS TRIFÁSICOS PINTADOS NAS CORES:

FASE R-VERMELHA, FASE S- BRANCA, FASE T-

MARRON, NEUTRO- AZUL CLARO, TERRA- VERDE:

BARRAMENTO DE COBRE ELETROLÍTICO PINTADO,

15X2MM(1 1/2"X1/8"), IN=155A, ICC=20KA,

CONTENDO: PLAQUETA DE POLICARBONATO NA

PORTA IDENTIFICANDO O QUADRO E A TENSÃO

220/127V, E DEMAIS ACESSÓRIOS, CEMAR,

SIEMENS OU EQUIVALENTE. DE ACORDO COM

DIAGRAMA UNIFILAR

UN 1,000 1.280,00 1.280,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 10,000 12,42 124,20

6113 AJUDANTE DE ELETRICISTA H 10,000 6,62 66,20

PREÇO (MATERIAL) 1.280,00

PREÇO (MAO-DE-OBRA) 190,40

PREÇO TOTAL + LS(SINAPI) 1.470,40

BDI (%) 24,96% 367,01

PREÇO TOTAL UNIT. (c/ taxa): 1.837,41

COMPCM_142

ARAME DE AÇO GALVANIZADO N.º12 AWG - FORN

E INST KG

342 ARAME DE AÇO GALVANIZADO N.º12 AWG KG 1,000 9,20 9,20

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,42 1,24

PREÇO (MATERIAL) 9,20

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 10,44

BDI (%) 24,96% 2,61

PREÇO TOTAL UNIT. (c/ taxa): 13,05

COMP_BLT BLOCO TELEFONICO BLI-10 C/CANALETA UN

BLOCO TELEFONICO BLI-10 C/CANALETA UN 1,000 3,80 3,80

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,500 12,42 6,21

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6113 AJUDANTE DE ELETRICISTA H 0,500 6,62 3,31

PREÇO (MATERIAL) 3,80

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 13,32

BDI (%) 24,96% 3,32

PREÇO TOTAL UNIT. (c/ taxa): 16,64

COMPCM_024 BOX CURVO DE ALUMINIO 50MM UN

BOX CURVO DE ALUMINIO 50MM UN 1,000 26,68 26,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,030 12,42 0,37

6113 AJUDANTE DE ELETRICISTA H 0,030 6,62 0,20

PREÇO (MATERIAL) 26,68

PREÇO (MAO-DE-OBRA) 0,57

PREÇO TOTAL + LS(SINAPI) 27,25

BDI (%) 24,96% 6,80

PREÇO TOTAL UNIT. (c/ taxa): 34,05

COMPCM_025 BOX RETO DE ALUMINIO 50MM UN

BOX RETO DE ALUMINIO 50MM UN 1,000 7,68 7,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,030 12,42 0,37

6113 AJUDANTE DE ELETRICISTA H 0,030 6,62 0,20

PREÇO (MATERIAL) 7,68

PREÇO (MAO-DE-OBRA) 0,57

PREÇO TOTAL + LS(SINAPI) 8,25

BDI (%) 24,96% 2,06

PREÇO TOTAL UNIT. (c/ taxa): 10,31

COMP_BAR1 BUCHA/ARRUELA ALUMINIO 1" UN

855

BUCHA E ARRUELA ALUMINIO FUNDIDO P/

ELETRODUTO 25MM (1'') CJ 1,000 1,03 1,03

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,040 12,42 0,50

6113 AJUDANTE DE ELETRICISTA H 0,040 6,62 0,26

PREÇO (MATERIAL) 1,03

PREÇO (MAO-DE-OBRA) 0,76

PREÇO TOTAL + LS(SINAPI) 1,79

BDI (%) 24,96% 0,45

PREÇO TOTAL UNIT. (c/ taxa): 2,24

COMP_BAR2 BUCHA/ARRUELA ALUMINIO 2" UN

843

BUCHA E ARRUELA ALUMINIO FUNDIDO P/

ELETRODUTO 50MM (2'') CJ 2,29 CJ 1,000 2,29 2,29

2436

00000856 BUCHA E ARRUELA ALUMINIO FUNDIDO

P/ ELETRODUTO 60MM (2 1/ H 0,060 12,42 0,75

6113 AJUDANTE DE ELETRICISTA H 0,060 6,62 0,40

PREÇO (MATERIAL) 2,29

PREÇO (MAO-DE-OBRA) 1,14

PREÇO TOTAL + LS(SINAPI) 3,43

BDI (%) 24,96% 0,86

PREÇO TOTAL UNIT. (c/ taxa): 4,29

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_177CABEÇOTE, ALUMÍNIO FUNDIDO Ø50MM (Ø2") , 135°-FORN E INST

UN

MATCM_173 CABEÇOTE, ALUMÍNIO FUNDIDO Ø50MM (Ø2") ,

135° UN 1,000 6,70 6,70

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,42 1,24

PREÇO (MATERIAL) 6,70

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 7,94

BDI (%) 24,96% 1,98

PREÇO TOTAL UNIT. (c/ taxa): 9,92

COMPCM_178 CABO CFTV RG-59 - FONR E INST M

MATCM_174 CABO CFTV RG-59 M 1,000 2,46 2,46

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,065 12,42 0,81

6113 AJUDANTE DE ELETRICISTA H 0,065 6,62 0,43

PREÇO (MATERIAL) 2,46

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 3,70

BDI (%) 24,96% 0,92

PREÇO TOTAL UNIT. (c/ taxa): 4,62

COMPCM_179 CABO COAXIAL 75OHMS - FORN E INST M

MATCM_175 CABO COAXIAL 75OHMS M 1,000 0,90 0,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,065 12,42 0,81

6113 AJUDANTE DE ELETRICISTA H 0,065 6,62 0,43

PREÇO (MATERIAL) 0,90

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 2,14

BDI (%) 24,96% 0,53

PREÇO TOTAL UNIT. (c/ taxa): 2,67

COMPCM_18

1

CABO UTP-4 PARES, 24 AWG CATEGORIA 6,

QUATRO PARES FLEXÍVEL - FORN E INST M

MATCM_177 CABO UTP-4 PARES, 24 AWG CATEGORIA 6, QUATRO

PARES FLEXÍVEL M 1,000 2,15 2,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,065 12,42 0,81

6113 AJUDANTE DE ELETRICISTA H 0,065 6,62 0,43

PREÇO (MATERIAL) 2,15

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 3,39

BDI (%) 24,96% 0,85

PREÇO TOTAL UNIT. (c/ taxa): 4,23

COMPCM_18

2

CURVA 90º PVC RÍGIDO, 32MM, COM LUVAS, TIGRE

OU EQUIVALENTE - FORN E INST UN

1884 CURVA 90º PVC RÍGIDO, 32MM, COM LUVAS, TIGRE

OU EQUIVALENTE UN 1,000 3,36 3,36

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,250 12,42 3,11

6113 AJUDANTE DE ELETRICISTA H 0,250 6,62 1,66

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MATERIAL) 3,36

PREÇO (MAO-DE-OBRA) 4,76

PREÇO TOTAL + LS(SINAPI) 8,12

BDI (%) 24,96% 2,03

PREÇO TOTAL UNIT. (c/ taxa): 10,15

COMPCM_16

1

CURVA 90º PVC RÍGIDO, 50MM, COM LUVAS, TIGRE

OU EQUIVALENTE - FORN E INST UN

1875 CURVA 90º PVC RÍGIDO, 50MM, COM LUVAS, TIGRE

OU EQUIVALENTE UN 1,000 5,21 5,21

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,380 12,42 4,72

6113 AJUDANTE DE ELETRICISTA H 0,380 6,62 2,52

PREÇO (MATERIAL) 5,21

PREÇO (MAO-DE-OBRA) 7,24

PREÇO TOTAL + LS(SINAPI) 12,45

BDI (%) 24,96% 3,11

PREÇO TOTAL UNIT. (c/ taxa): 15,55

COMPCM_18

3

CURVA DE AÇO GALVANIZADO, PESADO, Ø50MM

(Ø2") , 90°, RAIO LONGO, COM LUVAS - FORN E

INST UN

2631 CURVA DE AÇO GALVANIZADO, PESADO, Ø50MM

(Ø2") , 90°, RAIO LONGO, COM LUVAS UN 1,000 6,25 6,25

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,400 12,42 4,97

6113 AJUDANTE DE ELETRICISTA H 0,400 6,62 2,65

PREÇO (MATERIAL) 6,25

PREÇO (MAO-DE-OBRA) 7,62

PREÇO TOTAL + LS(SINAPI) 13,87

BDI (%) 24,96% 3,46

PREÇO TOTAL UNIT. (c/ taxa): 17,33

COMPCM_156

CAIXA DE PASSAGEM EM ALVENARIA,

120X120X100CM COM TAMPA DE CONCRETO E

ALÇAS, COM BRITA PARA DRENAGEM UN

370 AREIA MEDIA M3 0,481 45,00 21,65

1106

CAL HIDRATADA, DE 1A. QUALIDADE, PARA

ARGAMASSA KG 18,570 1,00 18,57

1379 CIMENTO PORTLAND COMUM CP II- 32 KG 110,880 0,73 80,94

4721 PEDRA BRITADA N. 1 OU 19 MM M3 0,288 139,77 40,25

39 ACO CA-60 - 5,0MM KG 10,900 4,52 49,27

7271 TIJOLO CERAMICO FURADO 8 FUROS 10 X 20 X 20CM UN 343,000 0,50 171,50

1379 CIMENTO P/ TAMPA KG 23,184 0,73 16,92

370 AREIA P/ TAMPA M3 0,062 45,00 2,80

4734 SEIXO P/ TAMPA M3 0,060 155,61 9,37

21141 AÇO 3/16" P/ TAMPA M2 1,440 7,93 11,42

1346

CHAPA MADEIRA COMPENSADA P/ FORMA

CONCRETO M2 0,240 30,14 7,23

5064 PREGO KG 0,100 6,15 0,62

337 ARAME RECOZIDO KG 1,000 8,05 8,05

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 33,766 6,04 203,95

4750 PEDREIRO H 15,000 8,17 122,55

PREÇO (MATERIAL) 438,59

PREÇO (MAO-DE-OBRA) 326,50

PREÇO TOTAL + LS(SINAPI) 765,08

BDI (%) 24,96% 190,97

PREÇO TOTAL UNIT. (c/ taxa): 956,05

COMP_PILAR

PILARETE DE AMARRAÇÃO COMPLETO, CONCRETO,

FERRAGEM E FÔRMA M3

370 AREIA MEDIA M3 0,800 45,00 36,00

1379 CIMENTO PORTLAND COMUM CP II- 32 KG 350,000 0,70 245,00

39 ACO CA-60 - 5,0MM KG 24,850 3,93 97,66

4734 SEIXO P/ TAMPA M3 0,700 190,98 133,69

1346

CHAPA MADEIRA COMPENSADA P/ FORMA

CONCRETO M2 2,500 30,14 75,35

5064 PREGO KG 1,000 6,00 6,00

337 ARAME RECOZIDO KG 1,000 7,88 7,88

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 35,000 6,04 211,40

4750 PEDREIRO H 35,000 8,17 285,95

PREÇO (MATERIAL) 601,58

PREÇO (MAO-DE-OBRA) 497,35

PREÇO TOTAL + LS(SINAPI) 1.098,93

BDI (%) 24,96% 274,29

PREÇO TOTAL UNIT. (c/ taxa): 1.373,22

COMP_ADM1 ENGENHEIRO CIVIL MÊS

2707 ENGENHEIRO OU ARQUITETO /PLENO - DE OBRA MÊS 220,00 75,70 16.653,56

PREÇO TOTAL + LS(SINAPI) 16.653,56

BDI (%) 24,96% 4.156,73

PREÇO TOTAL UNIT. (c/ taxa): 20.810,29

COMP_ADM2 MESTRE DE OBRAS MÊS

4069 MESTRE DE OBRAS H 220,00 23,06 5.073,20

PREÇO TOTAL + LS(SINAPI) 5.073,20

BDI (%) 24,96% 1.266,27

PREÇO TOTAL UNIT. (c/ taxa): 6.339,47

COMP_ADM3 VIGIA MÊS

10508 VIGIA H 220,00 12,07 2.655,40

PREÇO (MAO-DE-OBRA) 2.655,40

PREÇO TOTAL + LS(SINAPI) 2.655,40

BDI (%) 24,96% 662,79

PREÇO TOTAL UNIT. (c/ taxa): 3.318,19

COMP_ADM4 TECNICO DE SEGURANÇA DO TRABALHO MÊS

7596 TECNICO DE SEGURANÇA DO TRABALHO H 180,00 24,78 4.459,60

PREÇO (MAO-DE-OBRA) 4.459,60

PREÇO TOTAL + LS(SINAPI) 4.459,60

BDI (%) 24,96% 1.113,12

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL UNIT. (c/ taxa): 5.572,72

COMP_ADM5 ALMOXARIFE MÊS

253 ALMOXARIFE H 220,00 12,01 2.642,20

PREÇO (MAO-DE-OBRA) 2.642,20

PREÇO TOTAL + LS(SINAPI) 2.642,20

BDI (%) 24,96% 659,49

PREÇO TOTAL UNIT. (c/ taxa): 3.301,69

COMP_ALIM DESPESAS COM ALIMENTAÇÃO MÊS

Nº PESSOAS UND 100,00

DIAS MÊS DIAS 24,00

QUENTINHA UND 2.400,00

PREÇO UND 2.400,00 10,00 24.000,00

BDI (%) 24,96% 5.990,40

29.990,40

COMP_TRAN DESPESAS COM TRANSPORTE DE FUNCIONÁRIOS MÊS

Nº PESSOAS UND 100,00

DIAS MÊS DIAS 24,00

VALE TRANSPORTE UND 4.800,00

PREÇO UND 4.800,00 3,00 14.400,00

BDI (%) 24,96% 3.594,24

17.994,24

COMP_EL1 ABRAÇADEIRA TIPO D 4" UN

4372 ABRAÇADEIRA TIPO D 4" UN 1,00 4,65 4,65

6113 AJUDANTE DE ELETRICISTA H 0,05 6,62 0,33

PREÇO (MATERIAL) 4,65

PREÇO (MAO-DE-OBRA) 0,33

PREÇO TOTAL + LS(SINAPI) 4,98

BDI (%) 24,96% 1,24

PREÇO TOTAL UNIT. (c/ taxa): 6,22

COMP_EL2 BANCADA TP E TC'S UN

BANCADA TP E TC'S UN 1,00 275,62 275,62

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 275,62

PREÇO (MAO-DE-OBRA) 3,31

PREÇO TOTAL + LS(SINAPI) 278,93

BDI (%) 24,96% 69,62

PREÇO TOTAL UNIT. (c/ taxa): 348,55

COMP_EL3 BOX GIRATÓRIO RETO 1" UN

BOX GIRATÓRIO RETO 1" UN 1,00 13,54 13,54

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 13,54

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MAO-DE-OBRA) 0,66

PREÇO TOTAL + LS(SINAPI) 14,20

BDI (%) 24,96% 3,54

PREÇO TOTAL UNIT. (c/ taxa): 17,75

COMP_EL4 BUCHA PASSA-MURO INT/INT UN

BUCHA PASSA-MURO INT/INT UN 1,00 264,97 264,97

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,35 12,42 4,35

6113 AJUDANTE DE ELETRICISTA H 0,35 6,62 2,32

PREÇO (MATERIAL) 264,97

PREÇO (MAO-DE-OBRA) 2,32

PREÇO TOTAL + LS(SINAPI) 267,29

BDI (%) 24,96% 66,71

PREÇO TOTAL UNIT. (c/ taxa): 334,00

COMP_EL5 CABO ALUMINIO NÚ 2AWG KG

CABO ALUMINIO NÚ 2AWG KG 1,05 8,79 9,23

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,35 12,42 4,35

6113 AJUDANTE DE ELETRICISTA H 0,35 6,62 2,32

PREÇO (MATERIAL) 9,23

PREÇO (MAO-DE-OBRA) 6,66

PREÇO TOTAL + LS(SINAPI) 15,89

BDI (%) 24,96% 3,97

PREÇO TOTAL UNIT. (c/ taxa): 19,86

COMP_EL6 CABO MUFLA 15KV 25mm2 KG

CABO MUFLA 15KV 25mm2 M 1,05 21,99 23,09

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 23,09

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 25,95

BDI (%) 24,96% 6,48

PREÇO TOTAL UNIT. (c/ taxa): 32,42

COMP_EL7 CAIXA MEDIDOR TRIFASICO UN

1061 CAIXA MEDIDOR TRIFASICO UN 1,00 86,02 86,02

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 86,02

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 95,54

BDI (%) 24,96% 23,85

PREÇO TOTAL UNIT. (c/ taxa): 119,39

COMP_EL8 CHAPA METALICA BUCHA PASSA MURO UN

CHAPA METALICA BUCHA PASSA MURO UN 1,00 190,90 190,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MATERIAL) 190,90

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 193,76

BDI (%) 24,96% 48,36

PREÇO TOTAL UNIT. (c/ taxa): 242,12

COMP_EL9 CHAVE SECCINADORA 15KV UN

CHAVE SECCINADORA 15KV UN 1,00 2.264,08 2.264,08

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 2.264,08

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 2.283,12

BDI (%) 24,96% 569,87

PREÇO TOTAL UNIT. (c/ taxa): 2.852,99

COMP_EL10 CHAVE XS-100A 15KV UN

CHAVE XS-100A 15KV UN 1,00 179,77 179,77

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 179,77

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 189,29

BDI (%) 24,96% 47,25

PREÇO TOTAL UNIT. (c/ taxa): 236,54

COMP_EL11 CHUMBADOR CBA 1/4" UN

11976 CHUMBADOR CBA 1/4" UN 1,00 3,65 3,65

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 3,65

PREÇO (MAO-DE-OBRA) 0,99

PREÇO TOTAL + LS(SINAPI) 4,64

BDI (%) 24,96% 1,16

PREÇO TOTAL UNIT. (c/ taxa): 5,80

COMP_EL12 COMANDO RA1 UN

COMANDO RA1 UN 1,00 514,40 514,40

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 514,40

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 523,92

BDI (%) 24,96% 130,77

PREÇO TOTAL UNIT. (c/ taxa): 654,69

COMP_EL13 CONECTOR ESTRIBO UN

CONECTOR ESTRIBO UN 1,00 13,44 13,44

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,20 12,42 2,48

PREÇO (MATERIAL) 13,44

PREÇO (MAO-DE-OBRA) 2,48

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL + LS(SINAPI) 15,92

BDI (%) 24,96% 3,97

PREÇO TOTAL UNIT. (c/ taxa): 19,89

COMP_EL14CRUZETA DE MADEIRA DE LEI, COMPRIM= 2,4M

SECAO TRANSVERSAL 90 X 115MMUN

10510

CRUZETA DE MADEIRA DE LEI, COMPRIM= 2,4M

SECAO TRANSVERSAL 90 X 115MM UN 1,00 96,28 96,28

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 96,28

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 115,32

BDI (%) 24,96% 28,78

PREÇO TOTAL UNIT. (c/ taxa): 144,10

COMP_EL15 DISJUNTOR PLB 15KV C/ BOBINA 127V UN

DISJUNTOR PLB 15KV C/ BOBINA 127V UN 1,00 16.343,03 16.343,03

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,30 12,42 3,73

6113 AJUDANTE DE ELETRICISTA H 0,30 6,62 1,99

PREÇO (MATERIAL) 16.343,03

PREÇO (MAO-DE-OBRA) 5,71

PREÇO TOTAL + LS(SINAPI) 16.348,74

BDI (%) 24,96% 4.080,65

PREÇO TOTAL UNIT. (c/ taxa): 20.429,39

COMP_EL16 DISJUNTOR SIEMENS 1600A UN

DISJUNTOR SIEMENS 1600A UN 1,00 7.680,61 7.680,61

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 7.680,61

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 7.699,65

BDI (%) 24,96% 1.921,83

PREÇO TOTAL UNIT. (c/ taxa): 9.621,48

COMP_EL17 ENVELOPAMENTO REDE SUBTERRANEA M3

79478 ESCAVACAO MANUAL M3 1,00 17,70 17,70

83441 REATERRO COMPACTADO M3 1,00 21,14 21,14

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 35,00 12,42 434,70

6113 AJUDANTE DE ELETRICISTA H 24,02 6,62 159,02

PREÇO (MATERIAL) 0,00

PREÇO (MAO-DE-OBRA) 632,56

PREÇO TOTAL + LS(SINAPI) 632,56

BDI (%) 24,96% 157,89

PREÇO TOTAL UNIT. (c/ taxa): 790,45

COMP_EL18 FIO DE COBRE DURO 16mm2 KG

FIO DE COBRE DURO 16mm2 KG 1,05 46,48 48,80

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 48,80

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 51,66

BDI (%) 24,96% 12,89

PREÇO TOTAL UNIT. (c/ taxa): 64,55

COMP_EL19 GRAMPO DE CERCA KG

5076

GRAMPO DE ACO P/ FIXACAO CERCA DE ARAME

FARPADO KG 1,05 7,47 7,84

6115 AJUDANTE H 0,15 6,04 0,91

PREÇO (MATERIAL) 7,84

PREÇO (MAO-DE-OBRA) 0,91

PREÇO TOTAL + LS(SINAPI) 8,75

BDI (%) 24,96% 2,18

PREÇO TOTAL UNIT. (c/ taxa): 10,93

COMP_EL20

GRAMPO LINHA VIVA, DE ALUMINIO CABO

PRINCIPAL ( 10 - 120MM2) DERIVACAO (10 -

70MM2)

UN

11837

GRAMPO LINHA VIVA, DE ALUMINIO CABO

PRINCIPAL ( 10 - 120MM2) DERIVACAO (10 -

70MM2) UN 1,00 21,77 21,77

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 21,77

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 24,63

BDI (%) 24,96% 6,15

PREÇO TOTAL UNIT. (c/ taxa): 30,77

COMP_EL21 ISOLADOR PEDESTAL 15KV UN

12364 ISOLADOR TENSAO P/ 15KV UN 1,00 48,47 48,47

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 48,47

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 51,33

BDI (%) 24,96% 12,81

PREÇO TOTAL UNIT. (c/ taxa): 64,14

COMP_EL22 LUMINÁRIA DE EMERGÊNCIA UN

LUMINÁRIA DE EMERGÊNCIA UN 1,00 61,89 61,89

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 61,89

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 64,75

BDI (%) 24,96% 16,16

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL UNIT. (c/ taxa): 80,91

COMP_EL23 MANILHA SAPATILHA UN

MANILHA SAPATILHA UN 1,00 7,36 7,36

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 7,36

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 10,22

BDI (%) 24,96% 2,55

PREÇO TOTAL UNIT. (c/ taxa): 12,77

COMP_EL24 MÃO FRANCESA CRUZETA UN

MÃO FRANCESA CRUZETA UN 1,00 2,66 2,66

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 2,66

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 5,52

BDI (%) 24,96% 1,38

PREÇO TOTAL UNIT. (c/ taxa): 6,90

COMP_EL25 MOLDE SOLDA EXOTERMICA UN

MOLDE SOLDA EXOTERMICA UN 1,00 66,77 66,77

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 66,77

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 69,63

BDI (%) 24,96% 17,38

PREÇO TOTAL UNIT. (c/ taxa): 87,00

COMP_EL26 MUFLA EXTERNA 15KV 25MM² UN

4127 MUFLA EXTERNA 15KV 25MM² UN 1,00 266,07 266,07

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 266,07

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 268,93

BDI (%) 24,96% 67,12

PREÇO TOTAL UNIT. (c/ taxa): 336,05

COMP_EL27 MUFLA INTERNA 15KV 25MM² UN

4154 MUFLA INTERNA 15KV 25MM² UN 1,00 325,08 325,08

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 325,08

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 327,94

BDI (%) 24,96% 81,85

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL UNIT. (c/ taxa): 409,79

COMP_EL28 PARAFUSO MAQUINA 5/8 X 300mm UN

439 PARAFUSO MAQUINA 5/8 X 300mm UN 1,00 4,13 4,13

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

PREÇO (MATERIAL) 4,13

PREÇO (MAO-DE-OBRA) 1,86

PREÇO TOTAL + LS(SINAPI) 5,99

BDI (%) 24,96% 1,50

PREÇO TOTAL UNIT. (c/ taxa): 7,49

COMP_EL29 PARA-RAIO POLIMERICO 15KV UN

PARA-RAIO POLIMERICO 15KV UN 1,00 137,18 137,18

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 137,18

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 156,22

BDI (%) 24,96% 38,99

PREÇO TOTAL UNIT. (c/ taxa): 195,21

COMP_EL30 PLACA DE ADVERTENCIA UN

PLACA DE ADVERTENCIA UN 1,00 40,52 40,52

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

PREÇO (MATERIAL) 40,52

PREÇO (MAO-DE-OBRA) 1,86

PREÇO TOTAL + LS(SINAPI) 42,38

BDI (%) 24,96% 10,58

PREÇO TOTAL UNIT. (c/ taxa): 52,96

COMP_EL31 QUADRO COMANDO 50X50X30 UN

QUADRO COMANDO 50X50X30 UN 1,00 350,32 350,32

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 350,32

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 369,36

BDI (%) 24,96% 92,19

PREÇO TOTAL UNIT. (c/ taxa): 461,55

COMP_EL32QUADRO COMANDO RELÉ PROTEÇÃO SECUNDÁRIA

50/51NUN

QUADRO COMANDO RELÉ PROTEÇÃO SECUNDÁRIA

50/51N UN 1,00 4.011,73 4.011,73

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 2,50 12,42 31,05

6113 AJUDANTE DE ELETRICISTA H 2,50 6,62 16,55

PREÇO (MATERIAL) 4.011,73

PREÇO (MAO-DE-OBRA) 47,60

PREÇO TOTAL + LS(SINAPI) 4.059,33

BDI (%) 24,96% 1.013,21

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL UNIT. (c/ taxa): 5.072,54

COMP_EL33 SEAL TUBO 1" M

SEAL TUBO 1" M 1,00 8,04 8,04

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 8,04

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 10,90

BDI (%) 24,96% 2,72

PREÇO TOTAL UNIT. (c/ taxa): 13,62

COMP_EL34 SOLDA EXOTERMICA 115 UN

SOLDA EXOTERMICA 115 UN 1,00 10,98 10,98

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 10,98

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 13,84

BDI (%) 24,96% 3,45

PREÇO TOTAL UNIT. (c/ taxa): 17,29

COMP_EL35 SUPORTE ISOLADOR PEDESTAL 15KV UN

7572 SUPORTE ISOLADOR PEDESTAL 15KV UN 1,00 8,61 8,61

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 8,61

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 18,13

BDI (%) 24,96% 4,53

PREÇO TOTAL UNIT. (c/ taxa): 22,66

COMP_EL36 SUPORTE MUFLA UN

SUPORTE MUFLA UN 1,00 52,24 52,24

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 52,24

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 61,76

BDI (%) 24,96% 15,42

PREÇO TOTAL UNIT. (c/ taxa): 77,18

COMP_EL37 TELA DE PROTEÇÃO 13X13 M2

10919 TELA DE PROTEÇÃO 13X13 M2 1,00 15,48 15,48

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 15,48

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 25,00

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 6,24

PREÇO TOTAL UNIT. (c/ taxa): 31,24

COMP_EL38 TELA DE PROTEÇÃO 25X25 M2

TELA DE PROTEÇÃO 25X25 M2 1,00 208,46 208,46

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,50 12,42 6,21

6113 AJUDANTE DE ELETRICISTA H 0,50 6,62 3,31

PREÇO (MATERIAL) 208,46

PREÇO (MAO-DE-OBRA) 9,52

PREÇO TOTAL + LS(SINAPI) 217,98

BDI (%) 24,96% 54,41

PREÇO TOTAL UNIT. (c/ taxa): 272,39

COMP_EL39 TERMINAL CONCENTRICO EMENDA 3/8 UN

TERMINAL CONCENTRICO EMENDA 3/8 UN 1,00 24,17 24,17

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 24,17

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 27,03

BDI (%) 24,96% 6,75

PREÇO TOTAL UNIT. (c/ taxa): 33,78

COMP_EL40 TERMINAL CONCENTRICO RETO 3/8 UN

TERMINAL CONCENTRICO RETO 3/8 UN 1,00 9,28 9,28

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 9,28

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 12,14

BDI (%) 24,96% 3,03

PREÇO TOTAL UNIT. (c/ taxa): 15,17

COMP_EL41 TRANSFORMADOR DE CORRENTE 15KV 300/5 UN

TRANSFORMADOR DE CORRENTE 15KV 300/5 UN 1,00 1.079,99 1.079,99

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 1.079,99

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 1.099,03

BDI (%) 24,96% 274,32

PREÇO TOTAL UNIT. (c/ taxa): 1.373,35

COMP_EL42 TRANSFORMADOR DE POTENCIAL 15KV 127V UN

TRANSFORMADOR DE POTENCIAL 15KV 127V UN 1,00 2.324,43 2.324,43

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 2.324,43

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 2.343,47

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 584,93

PREÇO TOTAL UNIT. (c/ taxa): 2.928,40

COMP_EL43 TUBO TIPO KANAFLEX 4" M

TUBO TIPO KANAFLEX 4" M 1,05 38,13 40,04

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,35 12,42 4,35

6113 AJUDANTE DE ELETRICISTA H 0,35 6,62 2,32

PREÇO (MATERIAL) 40,04

PREÇO (MAO-DE-OBRA) 6,66

PREÇO TOTAL + LS(SINAPI) 46,70

BDI (%) 24,96% 11,66

PREÇO TOTAL UNIT. (c/ taxa): 58,36

COMP_EL44 VENTILAÇÃO COM PAINEL TELADO 13X13 M2

568 CANTONEIRA DE FERRO M 3,30 41,56 137,22

10997 ELETRODO OK KG 1,00 12,75 12,75

10919 TELA DE AÇO SOLDADA M2 1,05 15,48 16,25

7307 APARELHAMENTO COM ZARCAO L 0,80 13,08 10,46

6160 SOLDADOR H 1,50 9,97 14,96

6115 AJUDANTE SOLDADOR H 1,50 6,04 9,06

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 176,69

PREÇO (MAO-DE-OBRA) 43,06

PREÇO TOTAL + LS(SINAPI) 219,75

BDI (%) 24,96% 54,85

PREÇO TOTAL UNIT. (c/ taxa): 274,60

COMP_EL45 VERGALHÃO DE COBRA NÚ 3/8" UN

VERGALHÃO DE COBRA NÚ 3/8" UN 1,05 87,23 91,59

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,00 12,42 12,42

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 91,59

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 110,63

BDI (%) 24,96% 27,61

PREÇO TOTAL UNIT. (c/ taxa): 138,25

COMP83 PAPELEIRA CROMADA - FORNECIMENTO E INSTALACAO UND

11703 PAPELEIRA CROMADA UN 1,00 22,47 22,47

4750 PEDREIRO H 0,05 8,17 0,41

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,05 6,04 0,30

PREÇO (MATERIAL) 22,47

PREÇO (MAO-DE-OBRA) 0,71

PREÇO TOTAL + LS(SINAPI) 23,18

BDI (%) 24,96% 5,79

PREÇO TOTAL UNIT. (c/ taxa): 28,97

COMP84 PORTA TOALHA EM METAL CROMADO, TIPO HASTE OU BARRA un

21102 PORTA TOALHA EM METAL CROMADO, TIPO HASTE OU BARRAUN 1,00 30,64 30,64

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,35 8,17 2,86

246 AUXILIAR DE ENCANADOR OU BOMBEIRO HIDRAULICOH 0,35 7,12 2,49

PREÇO (MATERIAL) 30,64

PREÇO (MAO-DE-OBRA) 5,35

PREÇO TOTAL + LS(SINAPI) 35,99

BDI (%) 24,96% 8,98

PREÇO TOTAL UNIT. (c/ taxa): 44,97

COMP85 BARRA P/DEFICIENTE FISICO B6 PADRAO AGETOP un

370 AREIA MEDIA M3 0,00 45,00 0,14

4721 PEDRA BRITADA N. 1 OU 19 MM M3 0,04 113,89 4,90

7568 BUCHA NYLON S-10 C/ PARAFUSO ACO ZINC ROSCA SOBERBA CAB CHATA 5,5 XUN 8,00 0,47 3,76

1379 CIMENTO PORTLAND COMUM CP II- 32 KG 1,66 0,73 1,21

2471 TUBO INDUST.S/COSTURA 1.1/4"X2,25MM m 0,90 56,48 50,83

2472 PINTURA ELETROSTATICA M2 0,11 5,09 0,56

1330 CHAPA ACO GROSSA PRETA 1/4"(6,35MM) 49,797KG/M2KG 1,15 2,70 3,09

4750 PEDREIRO H 1,02 8,17 8,35

6110 SERRALHEIRO H 4,33 8,17 35,34

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,08 6,04 0,49

PREÇO (MATERIAL) 64,50

PREÇO (MAO-DE-OBRA) 44,18

PREÇO TOTAL + LS(SINAPI) 108,68

BDI (%) 24,96% 27,13

PREÇO TOTAL UNIT. (c/ taxa): 135,80

COMP86 VALVULA DESCARGA P/MICTORIO DIAM. 3/4" - 1/2" UN

3143 FITA VEDA ROSCA EM ROLOS 18MMX25M UN 0,07 3,45 0,24

21112 VALVULA DESCARGA P/ MICTORIO UN 1,00 117,19 117,19

246 AUXILIAR DE ENCANADOR OU BOMBEIRO HIDRAULICOH 0,61 7,12 4,34

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,61 8,17 4,98

PREÇO (MATERIAL) 117,43

PREÇO (MAO-DE-OBRA) 9,33

PREÇO TOTAL + LS(SINAPI) 126,76

BDI (%) 24,96% 31,64

PREÇO TOTAL UNIT. (c/ taxa): 158,40

COMP87 REGISTRO PVC ESFERA VS ROSCAVEL DN 3/4" UN

3146 FITA VEDA ROSCA EM ROLOS 18MMX10M UN 0,12 1,50 0,18

6032 REGISTRO PVC ESFERA VS ROSCAVEL DN 3/4" UN 1,00 11,67 11,67

6116 AJUDANTE DE ENCANADOR H 0,60 6,66 4,00

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,70 8,17 5,72

PREÇO (MATERIAL) 11,85

PREÇO (MAO-DE-OBRA) 9,72

PREÇO TOTAL + LS(SINAPI) 21,57

BDI (%) 24,96% 5,38

PREÇO TOTAL UNIT. (c/ taxa): 26,95

COMP88 REGISTRO PVC ESFERA VS ROSCAVEL DN 2" UN

11671 REGISTRO PVC ESFERA VS ROSCAVEL DN 2" UN 1,00 38,92 38,92

3146 FITA VEDA ROSCA EM ROLOS 18MMX10M UN 0,18 1,50 0,27

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6116 AJUDANTE DE ENCANADOR H 0,70 6,66 4,66

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,90 8,17 7,35

PREÇO (MATERIAL) 39,19

PREÇO (MAO-DE-OBRA) 12,02

PREÇO TOTAL + LS(SINAPI) 51,21

BDI (%) 24,96% 12,78

PREÇO TOTAL UNIT. (c/ taxa): 63,99

COMP89 INSTALACAO DE CHUVEIRO ELETRICO UN

3148 FITA VEDA ROSCA EM ROLOS 18MMX50M UN 0,01 6,55 0,07

1368 CHUVEIRO ELETRICO COMUM PLASTICO TP DUCHA 110/220VUN 1,00 22,83 22,83

6115 AJUDANTE H 0,30 6,04 1,81

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,45 12,42 5,59

PREÇO (MATERIAL) 22,90

PREÇO (MAO-DE-OBRA) 7,40

PREÇO TOTAL + LS(SINAPI) 30,30

BDI (%) 24,96% 7,56

PREÇO TOTAL UNIT. (c/ taxa): 37,86

COMP90 RALO SEMI-ESFERICO FOFO TP ABACAXI D = 150MM P/ LAJES, CALHAS ETC UN

11709 RALO SEMI-ESFERICO FOFO TP ABACAXI D = 150MM P/ LAJES, CALHAS ETCUN 1,00 17,50 17,50

246 AUXILIAR DE ENCANADOR OU BOMBEIRO HIDRAULICOH 0,50 7,12 3,56

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,50 8,17 4,09

PREÇO (MATERIAL) 17,50

PREÇO (MAO-DE-OBRA) 7,65

PREÇO TOTAL + LS(SINAPI) 25,15

BDI (%) 24,96% 6,28

PREÇO TOTAL UNIT. (c/ taxa): 31,42

COMP92 REGISTRO OU REGULADOR P/ GAS COZINHA UN

11756 REGISTRO OU REGULADOR P/ GAS COZINHA MARCA ALIANCA REF 76506/1UN 1,00 19,13 19,13

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,40 8,17 3,27

PREÇO (MATERIAL) 19,13

PREÇO (MAO-DE-OBRA) 3,27

PREÇO TOTAL + LS(SINAPI) 22,40

BDI (%) 24,96% 5,59

PREÇO TOTAL UNIT. (c/ taxa): 27,99

COMP93 CENTRAL DE GÁS (1+1 CILIND.45 KG) UN

370 AREIA MEDIA M3 0,71 45,00 31,95

39 ACO CA-60 - 5,0MM KG 1,90 3,93 7,47

4721 PEDRA BRITADA N. 1 OU 19 MM M3 0,11 139,77 15,37

1379 CIMENTO PORTLAND COMUM CP II- 32 KG 149,32 0,70 104,52

11161 CAL HIDRATADA P/ PINTURA KG 77,56 1,00 77,56

2692 DESMOLDANTE PARA FORMA DE MADEIRA L 0,22 7,96 1,75

3767 LIXA P/ PAREDE OU MADEIRA UN 1,54 0,31 0,48

6085 SELADOR ACRILICO L 1,85 3,81 7,05

5061 PREGO DE ACO 18 X 27 KG 0,26 6,00 1,56

20206 PECA DE MADEIRA (MASSARANDUBA) APARELHADA 2 X 10CMM 2,02 3,33 6,73

123 ADITIVO IMPERMEABILIZANTE PEGA NORMAL P/ ARGAMASSA TIPO SIKA1 OU VEDACL 0,50 3,00 1,50

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6188 TABUA MADEIRA 3A QUALIDADE 2,5 X 30CM (1 X 12") NAO APARELHADAM2 2,86 18,26 52,22

7355 TINTA LATEX ACRILICA GL 3,70 38,70 143,19

7696 TUBO ACO GALV C/ COSTURA DIN 2440/NBR 5580 CLASSE MEDIA DN 2" (50MM) EM 11,76 37,64 442,65

10485 VIBRADOR DE IMERSAO C/ MOTOR ELETRICO 2HP MONOFASICO QUALQUER DIAM C/H 0,01 1,57 0,02

3671 JUNTA DILATACAO PLASTICA P/ PISO H=20MM E=3,0MMM 5,22 1,50 7,83

34 ACO CA-50 3/8" (9,52 MM) KG 9,49 3,45 32,74

2742 PECA DE MADEIRA ROLICA D = 15CM P/ ESCORAMENTOSM 3,96 6,92 27,40

4718 PEDRA BRITADA N. 2 OU 25 MM M3 0,02 135,00 2,70

10613 TIJOLO CERAMICO FURADO 3 FUROS 10 X 15 X 30CM UN 150,71 0,29 43,71

614 GRADE DE PROTECAO FERRO CHATO (20 KG/M2) M2 0,90 584,31 525,88

4750 PEDREIRO H 14,34 8,17 117,16

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 22,74 6,04 137,35

6115 AJUDANTE H 4,67 6,04 28,21

4783 PINTOR H 4,63 8,17 37,83

4243 OPERADOR DE BETONEIRA H 0,12 12,16 1,46

PREÇO (MATERIAL) 1.534,27

PREÇO (MAO-DE-OBRA) 322,00

PREÇO TOTAL + LS(SINAPI) 1.856,27

BDI (%) 24,96% 463,33

PREÇO TOTAL UNIT. (c/ taxa): 2.319,60

COMP94 TUBO PVC PBA 12 JE NBR 5647 P/REDE AGUA DN 65/DE 75 MM M

9845 TUBO PVC PBA 12 JE NBR 5647 P/REDE AGUA DN 65/DE 75 MMM 1,30 12,68 16,48

20083 SOLUCAO LIMPADORA FRASCO PLASTICO C/ 1000CM3UN 0,00 28,61 0,02

122 ADESIVO PVC FRASCO C/ 850G UND 0,00 24,15 0,05

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,40 8,17 3,27

246 AUXILIAR DE ENCANADOR OU BOMBEIRO HIDRAULICOH 0,40 7,12 2,85

PREÇO (MATERIAL) 16,56

PREÇO (MAO-DE-OBRA) 6,12

PREÇO TOTAL + LS(SINAPI) 24,16

BDI (%) 24,96% 6,03

PREÇO TOTAL UNIT. (c/ taxa): 30,19

COMP95

REDUCAO FIXA TIPO STORZ LATAO P/ INST.

PREDIAL COMBATE A INCENDIO ENGATE RAPIDO

2.1/2" X 1.1/2" UN

20972

REDUCAO FIXA TIPO STORZ LATAO P/ INST. PREDIAL

COMBATE A INCENDIO ENGATE RAPIDO 2.1/2" X

1.1/2" UN 1,00 51,82 51,82

6115 AJUDANTE H 0,32 6,04 1,95

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,40 8,17 3,27

PREÇO (MATERIAL) 51,82

PREÇO (MAO-DE-OBRA) 5,22

PREÇO TOTAL + LS(SINAPI) 57,04

BDI (%) 24,96% 14,24

PREÇO TOTAL UNIT. (c/ taxa): 71,28

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP96

MANGUEIRA DE INCENDIO C/ CAPA SIMPLES

TECIDA FIO POLIESTER TUBO INT BORRACHA SINT

ABNT TP 1 P/ INSTPR, COMP C/ UNIOES E EMPAT

INT LATAO C/ ENG RAP E ANEIS EXP P/ EMP MANG

COBRE D = 2 1/2 L = 30M UN

21037

MANGUEIRA DE INCENDIO C/ CAPA SIMPLES TECIDA

FIO POLIESTER TUBO INT BORRACHA SINT ABNT TP 1

P/ INSTPR, COMP C/ UNIOES E EMPAT INT LATAO C/

ENG RAP E ANEIS EXP P/ EMP MANG COBRE D = 2

1/2 L = 30M UN 1,00 583,87 583,87

6115 AJUDANTE H 0,20 6,04 1,21

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,20 8,17 1,63

PREÇO (MATERIAL) 583,87

PREÇO (MAO-DE-OBRA) 2,84

PREÇO TOTAL + LS(SINAPI) 586,71

BDI (%) 24,96% 146,44

PREÇO TOTAL UNIT. (c/ taxa): 733,16

COMP97 TAMPAO STORZ COM CORRENTE 2. 1/2" UN

10905

TAMPAO LATAO C/ CORRENTE P/ INSTALACAO

PREDIAL COMBATE A INCENDIO ENGA UN 1,00 41,64 41,64

6115 AJUDANTE H 0,20 6,04 1,21

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,20 8,17 1,63

PREÇO (MATERIAL) 41,64

PREÇO (MAO-DE-OBRA) 2,84

PREÇO TOTAL + LS(SINAPI) 44,48

BDI (%) 24,96% 11,10

PREÇO TOTAL UNIT. (c/ taxa): 55,58

COMP98

ADAPTADOR EM LATAO P/ INSTALACAO PREDIAL

DE COMBATE A INCENDIO ENGATE RAPIDO 2 1/2" X

ROSCA INTERNA 5 FIOS 2 1/2" UN

10899

ADAPTADOR EM LATAO P/ INSTALACAO PREDIAL DE

COMBATE A INCENDIO ENGATE UN 1,00 33,46 33,46

6115 AJUDANTE H 0,20 6,04 1,21

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,20 8,17 1,63

PREÇO (MATERIAL) 33,46

PREÇO (MAO-DE-OBRA) 2,84

PREÇO TOTAL + LS(SINAPI) 36,30

BDI (%) 24,96% 9,06

PREÇO TOTAL UNIT. (c/ taxa): 45,36

COMP99

TUBO ACO PRETO C/ COSTURA DIN 2440/NBR 5580

CLASSE MEDIA DN 65MM ( 2.1/2" ) E = 3,75MM -

6,68KG/M M

21023

TUBO ACO PRETO C/ COSTURA DIN 2440/NBR 5580

CLASSE MEDIA DN 65MM ( 2.1/2" ) E = 3,75MM -

6,68KG/M M 1,40 30,41 42,57

3146 FITA VEDA ROSCA EM ROLOS 18MMX10M UN 0,14 1,50 0,21

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 1,80 8,17 14,71

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6116 AJUDANTE DE ENCANADOR H 1,80 6,66 11,99

PREÇO (MATERIAL) 42,79

PREÇO (MAO-DE-OBRA) 26,69

PREÇO TOTAL + LS(SINAPI) 69,48

BDI (%) 24,96% 17,34

PREÇO TOTAL UNIT. (c/ taxa): 86,82

COMP100 BOMBA CENTRIFUGA 5,0 CV UN

738 BOMBA CENTRIFUGA C/ MOTOR ELETRICO TRIFASICO 5CV BOCAIS 2" X 1.1/2" X 1" DANCOR SERIE CAM MOD.618 - TJM HM/ Q = 40M / 25M3/H A 47M / 16M3/H**CAIXA**"UN 1,00 1.732,38 1.732,38

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 2,00 12,42 24,84

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 3,00 8,17 24,51

PREÇO (MATERIAL) 1.732,38

PREÇO (MAO-DE-OBRA) 49,35

PREÇO TOTAL + LS(SINAPI) 1.781,73

BDI (%) 24,96% 444,72

PREÇO TOTAL UNIT. (c/ taxa): 2.226,45

COMP111 ELEVADOR UN

ELEVADOR UN 1,00 88.624,22 88.624,22

PREÇO (MATERIAL) 88.624,22

PREÇO (MAO-DE-OBRA) 0,00

PREÇO TOTAL + LS(SINAPI) 88.624,22

BDI (%) 24,96% 22.120,61

PREÇO TOTAL UNIT. (c/ taxa): 110.744,83

COMP112

QUADRO BRANCO DE USO PROFISSIONAL

CONFECCIONADO EM MDF SOBREPOSTO POR

LAMINADO MELAMÍNICO, ACABAMENTO

BRILHOSO, MOLDURA EM ALUMNÍNIO ANODIZADO

- DIM: 300 X 120 - FORNECIMENTO E INSTALAÇÃO UN

MATCM10850 QUADRO DE FORMICA 3,00X1,20m FORN. E INSTAL. UN 1,00 438,50 438,50

11950 BUCHA NYLON S-6 C/ PARAFUSO ACO ZINC CAB CHATA ROSCA SOBERBA 4,2 X 45MUN 4,00 0,21 0,84

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,40 6,04 2,42

PREÇO (MATERIAL) 439,34

PREÇO (MAO-DE-OBRA) 2,42

PREÇO TOTAL + LS(SINAPI) 441,76

BDI (%) 24,96% 110,26

PREÇO TOTAL UNIT. (c/ taxa): 552,02

COMPCM_75

ALCA,PREFORMADA,ESTAI,CABO,ACO,3/8 POL,NTD-

02-M-2 ITEM 2-FORN E INST UN

MATCM_75

ALCA,PREFORMADA,ESTAI,CABO,ACO,3/8 POL,NTD-

02-M-2 ITEM 2 UN 1,00 5,59 5,59

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 5,59

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 7,49

BDI (%) 24,96% 1,87

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL UNIT. (c/ taxa): 9,36

COMPCM_188ARMACAO,SECUNDARIA,1 ESTRIBO ,COMPLETA - FORN E INST UN

MATCM_183 ARMACAO,SECUNDARIA,1 ESTRIBO ,COMPLETA UN 1,00 6,43 6,43

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 6,43

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 8,33

BDI (%) 24,96% 2,08

PREÇO TOTAL UNIT. (c/ taxa): 10,41

COMP_ARR

FORNECIMENTO DE ARRUELA QUADRADA ACO

GALV D = 38MM ESP= 3MM DFURO= 18 MM UN

379

ARRUELA QUADRADA ACO GALV D = 38MM ESP=

3MM DFURO= 18 MM UN 1,00 1,08 1,08

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,40 6,04 2,42

PREÇO (MATERIAL) 1,08

PREÇO (MAO-DE-OBRA) 2,42

PREÇO TOTAL + LS(SINAPI) 3,50

BDI (%) 24,96% 0,87

PREÇO TOTAL UNIT. (c/ taxa): 4,37

COMPCM_139

ABRACADEIRA, PLASTICA REUTILIZAVEL, 9 X 251

MM, DIAM 20 - 62 MM - FORN E INST UN

MATCM_139

ABRACADEIRA, PLASTICA REUTILIZAVEL, 9 X 251 MM,

DIAM 20 - 62 MM UN 1,00 0,11 0,11

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,06 12,42 0,70

PREÇO (MATERIAL) 0,11

PREÇO (MAO-DE-OBRA) 0,70

PREÇO TOTAL + LS(SINAPI) 0,81

BDI (%) 24,96% 0,20

PREÇO TOTAL UNIT. (c/ taxa): 1,01

COMPCM_78

BRACO, REDE COMPACTA, TIPO L, COM PRENSA-

CABO MONTADO - FORN E INST UN

MATCM_78

BRACO, REDE COMPACTA, TIPO L, COM PRENSA-

CABO MONTADO UN 1,00 53,33 53,33

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,20 12,42 2,48

6113 AJUDANTE DE ELETRICISTA H 0,20 6,62 1,32

PREÇO (MATERIAL) 53,33

PREÇO (MAO-DE-OBRA) 3,81

PREÇO TOTAL + LS(SINAPI) 57,14

BDI (%) 24,96% 14,26

PREÇO TOTAL UNIT. (c/ taxa): 71,40

COMPCM_79 BRAÇO, TIPO C, PARA REDE COMPACTA 15KV UN

MATCM_79 BRAÇO, TIPO C, PARA REDE COMPACTA 15KV UN 1,00 68,45 68,45

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,20 12,42 2,48

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6113 AJUDANTE DE ELETRICISTA H 0,20 6,62 1,32

PREÇO (MATERIAL) 68,45

PREÇO (MAO-DE-OBRA) 3,81

PREÇO TOTAL + LS(SINAPI) 72,26

BDI (%) 24,96% 18,04

PREÇO TOTAL UNIT. (c/ taxa): 90,29

COMPCM_80

CABO ELÉTRICO, 3#50mm2+9,5mm, XLPE, CLASSE

15KV, REDE COMPACTA - FORN E INST M

955

CABO ELÉTRICO, 3#50mm2+9,5mm, XLPE, CLASSE

15KV, REDE COMPACTA M 1,00 31,37 31,37

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,19 12,42 2,32

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 31,37

PREÇO (MAO-DE-OBRA) 2,98

PREÇO TOTAL + LS(SINAPI) 34,35

BDI (%) 24,96% 8,58

PREÇO TOTAL UNIT. (c/ taxa): 42,93

COMP_81

CABO, ELETRICO, COBERTO, ALUMINIO, XLPE, 15

KV, 50 MM2 - FORN E INST M

MATCM_81

CABO, ELETRICO, COBERTO, ALUMINIO, XLPE, 15 KV,

50 MM2 M 1,00 16,50 16,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,15 12,42 1,86

6113 AJUDANTE DE ELETRICISTA H 0,15 6,62 0,99

PREÇO (MATERIAL) 16,50

PREÇO (MAO-DE-OBRA) 2,86

PREÇO TOTAL + LS(SINAPI) 19,36

BDI (%) 24,96% 4,83

PREÇO TOTAL UNIT. (c/ taxa): 24,19

COMPCM_84

CAPA ISOLANTE PARA CONECTOR ESTRIBO TIPO

CUNHA - FORN E INST UN

MATCM_84

CAPA ISOLANTE PARA CONECTOR ESTRIBO TIPO

CUNHA UN 1,00 0,85 0,85

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 0,85

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 2,75

BDI (%) 24,96% 0,69

PREÇO TOTAL UNIT. (c/ taxa): 3,44

COMPCM_86

CINTA,ACO GALV,POSTE CIRCULAR,160MM,

COMPLETA - FORN E INST UN

MATCM_86

CINTA,ACO GALV,POSTE CIRCULAR,160MM,

COMPLETA UN 1,00 13,61 13,61

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 13,61

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 15,51

BDI (%) 24,96% 3,87

PREÇO TOTAL UNIT. (c/ taxa): 19,39

COMPCM_87

CINTA,ACO GALV,POSTE CIRCULAR,170MM,

COMPLETA - FORN E INST UN

MATCM_87

CINTA,ACO GALV,POSTE CIRCULAR,170MM,

COMPLETA UN 1,00 14,68 14,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 14,68

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 16,58

BDI (%) 24,96% 4,14

PREÇO TOTAL UNIT. (c/ taxa): 20,72

COMPCM_88

CINTA,ACO GALV,POSTE CIRCULAR,180MM,

COMPLETA - FORN E INST UN

MATCM_88

CINTA,ACO GALV,POSTE CIRCULAR,180MM,

COMPLETA UN 1,00 15,00 15,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 15,00

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 16,90

BDI (%) 24,96% 4,22

PREÇO TOTAL UNIT. (c/ taxa): 21,12

COMPCM_89

CINTA,ACO GALV,POSTE CIRCULAR,190MM,

COMPLETA - FORN E INST UN

MATCM_89

CINTA,ACO GALV,POSTE CIRCULAR,190MM,

COMPLETA UN 1,00 14,83 14,83

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 14,83

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 16,73

BDI (%) 24,96% 4,18

PREÇO TOTAL UNIT. (c/ taxa): 20,91

COMPCM_90

CINTA,ACO GALV,POSTE CIRCULAR,200MM,

COMPLETA - FORN E INST UN

MATCM_90

CINTA,ACO GALV,POSTE CIRCULAR,200MM,

COMPLETA UN 1,00 15,47 15,47

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 15,47

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 17,37

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 4,34

PREÇO TOTAL UNIT. (c/ taxa): 21,71

COMPCM_91

CINTA,ACO GALV,POSTE CIRCULAR,210MM,

COMPLETA - FORN E INST UN

MATCM_91

CINTA,ACO GALV,POSTE CIRCULAR,210MM,

COMPLETA UN 1,00 15,65 15,65

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 15,65

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 17,55

BDI (%) 24,96% 4,38

PREÇO TOTAL UNIT. (c/ taxa): 21,94

COMPCM_92

CINTA,ACO GALV,POSTE CIRCULAR,220MM,

COMPLETA - FORN E INST UN

MATCM_92

CINTA,ACO GALV,POSTE CIRCULAR,220MM,

COMPLETA UN 1,00 15,99 15,99

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 15,99

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 17,89

BDI (%) 24,96% 4,47

PREÇO TOTAL UNIT. (c/ taxa): 22,36

COMPCM_186COMPOSTO,ANTI-OXIDO, 250G - FORN E APLIC BIS

MATCM_182 COMPOSTO,ANTI-OXIDO, 250G BIS 1,00 1,00 1,00

6113 AJUDANTE DE ELETRICISTA H 1,00 6,62 6,62

PREÇO (MATERIAL) 1,00

PREÇO (MAO-DE-OBRA) 6,62

PREÇO TOTAL + LS(SINAPI) 7,62

BDI (%) 24,96% 1,90

PREÇO TOTAL UNIT. (c/ taxa): 9,52

COMPCM_93 CONECTOR COM ESTRIBO TIPO CUNHA - FORN E INST UN

MATCM_93 CONECTOR COM ESTRIBO TIPO CUNHA UN 1,00 13,15 13,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 13,15

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 15,05

BDI (%) 24,96% 3,76

PREÇO TOTAL UNIT. (c/ taxa): 18,81

COMPCM_94

CONECTOR, DERIVAÇÃO DE COMPREESÃO

FORMATO H, L. 25 - 70MM2, D. 16 - 35MM2. -

FORN E INST UN

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

MATCM_94

CONECTOR, DERIVAÇÃO DE COMPREESÃO FORMATO

H, L. 25 - 70MM2, D. 16 - 35MM2. UN 1,00 1,20 1,20

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 1,20

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 3,10

BDI (%) 24,96% 0,77

PREÇO TOTAL UNIT. (c/ taxa): 3,88

COMPCM_95

CONECTOR, DERIVAÇÃO DE COMPREESÃO

FORMATO H, L. 50MM2, D. 50MM2. - FORN E INST UN

MATCM_95

CONECTOR, DERIVAÇÃO DE COMPREESÃO FORMATO

H, L. 50MM2, D. 50MM2. UN 1,00 1,20 1,20

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 1,20

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 3,10

BDI (%) 24,96% 0,77

PREÇO TOTAL UNIT. (c/ taxa): 3,88

COMPCM_98 ELO-FUSIVEL,DISTRIBUICAO,COM BOTAO, 12 K - FORN E INST UN

MATCM_98 ELO-FUSIVEL,DISTRIBUICAO,COM BOTAO, 12 K UN 1,00 2,93 2,93

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 2,93

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 4,83

BDI (%) 24,96% 1,21

PREÇO TOTAL UNIT. (c/ taxa): 6,04

COMPCM_99

ESPACADOR, ISOLANTE, PARA REDE COMPACTA, 15

KV - FORN E INST UN

MATCM_99

ESPACADOR, ISOLANTE, PARA REDE COMPACTA, 15

KV UN 1,00 12,17 12,17

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 12,17

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 14,07

BDI (%) 24,96% 3,51

PREÇO TOTAL UNIT. (c/ taxa): 17,59

COMPCM_100

ESTRIBO, PARA REDE COMPACTA 15KV - FORN E

INST UN

MATCM_100 ESTRIBO, PARA REDE COMPACTA 15KV UN 1,00 6,79 6,79

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MATERIAL) 6,79

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 8,69

BDI (%) 24,96% 2,17

PREÇO TOTAL UNIT. (c/ taxa): 10,86

COMPCM_057

ROLO FITA ISOLANTE AUTO FUSÃO

7MMX19MMX10M - FORN E INST UN

MATCM_057 FITA ISOLANTE AUT FUSÃO 7MMX19MMX10M UN 1,00 13,91 13,91

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,05 12,42 0,62

PREÇO (MATERIAL) 13,91

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 14,53

BDI (%) 24,96% 3,63

PREÇO TOTAL UNIT. (c/ taxa): 18,16

COMPCM_058

ROLO

FITA ISOLANTE PLASTICA 7MMX19MMX10M -

FONR E INST UN

MATCM_058 FITA ISOLANTE PLASTICA 7MMX19MMX10M UN 1,00 6,18 6,18

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,05 12,42 0,62

PREÇO (MATERIAL) 6,18

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 6,80

BDI (%) 24,96% 1,70

PREÇO TOTAL UNIT. (c/ taxa): 8,50

COMPCM_101

GANCHO-OLHAL,ACO GALVANIZADO,ROTURA

5000KGF,NTD-02-018 - FORN E INST UN

MATCM_101

GANCHO-OLHAL,ACO GALVANIZADO,ROTURA

5000KGF,NTD-02-018 UN 1,00 7,23 7,23

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 7,23

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 9,13

BDI (%) 24,96% 2,28

PREÇO TOTAL UNIT. (c/ taxa): 11,41

COMPCM_102GRAMPO ANCORAGEM POLIMERICO - FORN E INST UN

MATCM_102 GRAMPO ANCORAGEM POLIMERICO UN 1,00 26,30 26,30

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 26,30

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 28,20

BDI (%) 24,96% 7,04

PREÇO TOTAL UNIT. (c/ taxa): 35,24

COMPCM_103GRAMPO,LINHA VIVA,BRONZE - FORN E INST UN

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

MATCM_103 GRAMPO,LINHA VIVA,BRONZE UN 1,00 19,70 19,70

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 19,70

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 21,60

BDI (%) 24,96% 5,39

PREÇO TOTAL UNIT. (c/ taxa): 27,00

COMPCM_104

HASTE,ATERRAMENTO,CANTONEIRA

ACO,ZINC,5X25X25X2400MM - FORN E INST UN

MATCM_104

HASTE,ATERRAMENTO,CANTONEIRA

ACO,ZINC,5X25X25X2400MM UN 1,00 18,47 18,47

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 18,47

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 20,37

BDI (%) 24,96% 5,09

PREÇO TOTAL UNIT. (c/ taxa): 25,46

COMPCM_105

ISOLADOR, ANCORAGEM/SUSPENSÃO,

POLIMERICO, GARFO-OLHAL, 15KV, 5000DAN -

FORN E INST UN

MATCM_105

ISOLADOR, ANCORAGEM/SUSPENSÃO, POLIMERICO,

GARFO-OLHAL, 15KV, 5000DAN UN 1,00 38,50 38,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 38,50

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 40,40

BDI (%) 24,96% 10,08

PREÇO TOTAL UNIT. (c/ taxa): 50,49

COMPCM_106

ISOLADOR, PINO, MONOCORPO, POLIMERICO,

15KV, DIAM 140MM ALT 135MM, ROSCA 25MM -

FORN E INST UN

MATCM_106

ISOLADOR, PINO, MONOCORPO, POLIMERICO, 15KV,

DIAM 140MM ALT 135MM, ROSCA 25MM UN 1,00 38,50 38,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 38,50

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 40,40

BDI (%) 24,96% 10,08

PREÇO TOTAL UNIT. (c/ taxa): 50,49

COMPCM_107

ISOLADOR,PINO,PORCELANA,15KV,102X117MM,RO

SCA 25MM,DT/PC0 - FORN E INST UN

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

MATCM_107

ISOLADOR,PINO,PORCELANA,15KV,102X117MM,ROS

CA 25MM,DT/PC0 UN 1,00 10,22 10,22

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 10,22

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 12,12

BDI (%) 24,96% 3,03

PREÇO TOTAL UNIT. (c/ taxa): 15,15

COMPCM_108

ISOLADOR,ROLDANA,PORCELANA76X79 MM,DT/PC-

02-025 - FORN E INST UN

MATCM_108

ISOLADOR,ROLDANA,PORCELANA76X79 MM,DT/PC-

02-025 UN 1,00 2,35 2,35

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 2,35

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 4,25

BDI (%) 24,96% 1,06

PREÇO TOTAL UNIT. (c/ taxa): 5,32

COMPCM_109

ISOLADOR,SUSPENSAO,VIDRO TEMPERADO,GARFO-

OLHAL,160MM, 50 - FORN E INST UN

MATCM_108

ISOLADOR,ROLDANA,PORCELANA76X79 MM,DT/PC-

02-025 UN 1,00 2,35 2,35

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 2,35

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 4,25

BDI (%) 24,96% 1,06

PREÇO TOTAL UNIT. (c/ taxa): 5,32

COMPCM_110

LACO, PREFORMADO, PARA

ESPACADOR/SEPARADOR, CABO MENSAGEIRO

9,5MM - FORN E INST UN

MATCM_110

LACO, PREFORMADO, PARA

ESPACADOR/SEPARADOR, CABO MENSAGEIRO

9,5MM UN 1,00 0,90 0,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 0,90

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 2,80

BDI (%) 24,96% 0,70

PREÇO TOTAL UNIT. (c/ taxa): 3,50

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_111

LACO, PREFORMADO, PLASTICO PARA

ESPACADOR/SEPARADOR, CABO AL. COBERTO

15KV, 50-95 MM2 UN

MATCM_111

LACO, PREFORMADO, PLASTICO PARA

ESPACADOR/SEPARADOR, CABO AL. COBERTO 15KV,

50-95 MM2 UN 1,00 2,90 2,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 2,90

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 4,80

BDI (%) 24,96% 1,20

PREÇO TOTAL UNIT. (c/ taxa): 6,00

COMPCM_112

LACO, PREFORMADO, ROLDANA, CABO CA, 35

MM2, ISOL 45 MM - FORN E INST UN

MATCM_112

LACO, PREFORMADO, ROLDANA, CABO CA, 35 MM2,

ISOL 45 MM UN 1,00 1,15 1,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 1,15

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 3,05

BDI (%) 24,96% 0,76

PREÇO TOTAL UNIT. (c/ taxa): 3,82

COMPCM_113

LACO, PREFORMADO, ROLDANA, CABO CA, 70/95

MM2, ISOL 45 MM - FORN E INST UN

MATCM_113

LACO, PREFORMADO, ROLDANA, CABO CA, 70/95

MM2, ISOL 45 MM UN 1,00 2,00 2,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 2,00

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 3,90

BDI (%) 24,96% 0,97

PREÇO TOTAL UNIT. (c/ taxa): 4,88

COMPCM_114

LACO,PREFORMADO,TOPO,SIMPLES,ISOL

102MM,CABO CAA 4 AWG - FORN E INST UN

MATCM_114

LACO,PREFORMADO,TOPO,SIMPLES,ISOL

102MM,CABO CAA 4 AWG UN 1,00 10,40 10,40

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

6113 AJUDANTE DE ELETRICISTA H 0,10 6,62 0,66

PREÇO (MATERIAL) 10,40

PREÇO (MAO-DE-OBRA) 1,90

PREÇO TOTAL + LS(SINAPI) 12,30

BDI (%) 24,96% 3,07

PREÇO TOTAL UNIT. (c/ taxa): 15,38

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMPCM_117

MANILHA-SAPATILHA,ACO GALVANIZADO,PSTC-

5247/17111 PLP - FORN E INST UN

MATCM_117

MANILHA-SAPATILHA,ACO GALVANIZADO,PSTC-

5247/17111 PLP UN 1,00 8,18 8,18

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

PREÇO (MATERIAL) 8,18

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 9,42

BDI (%) 24,96% 2,35

PREÇO TOTAL UNIT. (c/ taxa): 11,77

COMPCM_118

OLHAL,PARAFUSO,ACO GALVANIZADO,RUPTURA

5000KGF - FORN E INST UN

MATCM_118

OLHAL,PARAFUSO,ACO GALVANIZADO,RUPTURA

5000KGF UN 1,00 8,32 8,32

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,10 12,42 1,24

PREÇO (MATERIAL) 8,32

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 9,56

BDI (%) 24,96% 2,39

PREÇO TOTAL UNIT. (c/ taxa): 11,95

COMPCM_119

PARAFUSO, CABEÇA ABAULADA, AÇO ZINCADO,

M16X45X38MM - FORN E INST UN

MATCM_119

PARAFUSO, CABEÇA ABAULADA, AÇO ZINCADO,

M16X45X38MM UN 1,00 2,08 2,08

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,05 12,42 0,62

PREÇO (MATERIAL) 2,08

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 2,70

BDI (%) 24,96% 0,67

PREÇO TOTAL UNIT. (c/ taxa): 3,38

COMPCM_120

PARAFUSO, CABEÇA QUADRADA, AÇO ZINCADO,

M16X200x120MM - FORN E INST UN

MATCM_120

PARAFUSO, CABEÇA QUADRADA, AÇO ZINCADO,

M16X200x120MM UN 1,00 3,74 3,74

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,05 12,42 0,62

PREÇO (MATERIAL) 3,74

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 4,36

BDI (%) 24,96% 1,09

PREÇO TOTAL UNIT. (c/ taxa): 5,45

COMP_RED REDUCAO EXCENTRICA PVC LEVE C/ BOLSA P/ ANEL DN 150 X 100MM UN

20034 REDUCAO EXCENTRICA PVC LEVE C/ BOLSA P/ ANEL DN 150 X 100MMUN 1,00 124,24 124,24

6116 AJUDANTE DE ENCANADOR H 0,45 6,66 3,00

2696 ENCANADOR OU BOMBEIRO HIDRAULICO H 0,45 8,17 3,68

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MATERIAL) 124,24

PREÇO (MAO-DE-OBRA) 6,67

PREÇO TOTAL + LS(SINAPI) 130,91

BDI (%) 24,96% 32,68

PREÇO TOTAL UNIT. (c/ taxa): 163,59

COMP16LUMINÁRIA FLUORESCENTE COMPLETA PARAEMERGÊNCIA DE 15 W

UN

LUMINÁRIA FLUORESCENTE DE EMERGÊNCIA PARA 2 LAMPADAS (POTÊNCIA: 15,00 W / TENSÃO: 120/220 V)

UN 2,0000 142,575 285,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,3750 12,420 17,08

6113 AJUDANTE DE ELETRICISTA H 0,9990 6,620 6,61

285,15

23,69

308,84

24,96% 77,09

385,93

COMP17LUMINARIA PLAFON SOBREPOR P/LÂMP.COMPACTAELETRÔNICA 1 X 26W

UN

LUMINARIA PLAFON SOBREPOR P/LÂMP.COMPACTA ELETRÔNICA 1 X 26W

UN 1,0000 9,330 9,33

6113 AJUDANTE DE ELETRICISTA H 1,0222 6,620 6,77

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,6000 12,420 7,45

9,33

14,22

23,55

24,96% 5,88

29,43

COMP20DISJUNTOR TERMOMAGNETICO MONOPOLAR 10 AFORNECIMENTO E INSTALACAO

UND

2390 DISJUNTOR TERMOMAGNETICO MONOPOLAR 10A UN 1,0000 6,018 6,02

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1553 12,420 1,93

6,02

1,93

7,95

24,96% 1,98

9,93

COMP21DISJUNTOR TERMOMAGNETICO UNIPOLAR 20A 240V-FORN/COLOC

UN

2389 DISJUNTOR TERMOMAGNETICO MONOPOLAR 20A UN 1,0000 6,080 6,08

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1610 12,420 2,00

6,08

2,00

8,08

24,96% 2,02

10,10

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP22 DISJUNTOR TERMOMAGNETICO BIPOLAR 10 A,240VFORNECIMENTO E INSTALACAO

UN

DISJUNTOR TERMOMAGNETICO BIPOLAR 10A UN 1,0000 33,910 33,91

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1867 12,420 2,32

33,91

2,32

36,23

24,96% 9,04

45,27

COMP23DISJUNTOR TERMOMAGNETICO BIPOLAR 20 A,240VFORNECIMENTO E INSTALACAO

UN

2382 DISJUNTOR TERMOMAGNETICO BIPOLAR 20A UN 1,0000 40,630 40,63

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0300 12,420 0,37

40,63

0,37

41,00

24,96% 10,23

51,23

COMP24DISJUNTOR TERMOMAGNETICO BIPOLAR 32 A,240VFORNECIMENTO E INSTALACAO

UN

DISJUNTOR TERMOMAGNETICO BIPOLAR 32A UN 1,0000 34,366 34,37

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,2367 12,420 2,94

34,37

2,94

37,31

24,96% 9,31

46,62

COMP25DISJUNTOR TERMOMAGNETICO TRIPOLAR 25 A,240V, FORNECIMENTO E INSTALACAO

UN

DISJUNTOR TERMOMAGNETICO TRIPOLAR 20A UN 1,0000 42,145 42,15

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,4000 6,040 2,42

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,5450 12,420 6,77

42,15

9,19

51,34

24,96% 12,81

64,15

COMP26DISJUNTOR TERMOMAGNETICO TRIPOLAR 32 A,240V, FORNECIMENTO E INSTALACAO

UN

DISJUNTOR TERMOMAGNETICO TRIPOLAR 32A UN 1,0000 46,614 46,61

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,3989 6,040 2,41

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,5455 12,420 6,78

46,61

9,19

55,80

24,96% 13,93

69,73

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP27DISJUNTOR TERMOMAGNETICO TRIPOLAR 40 A,240V, FORNECIMENTO E INSTALACAO

UN

2380 DISJUNTOR TERMOMAGNETICO TRIPOLAR 40A UN 1,0000 42,310 42,31

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,4290 6,040 2,59

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,5869 12,420 7,29

42,31

9,88

52,19

24,96% 13,03

65,22

COMP28DISJUNTOR TERMOMAGNETICO TRIPOLAR 100 A,240V, FORNECIMENTO E INSTALACAO

UN

2373 DISJUNTOR TERMOMAGNETICO TRIPOLAR 100A UN 1,0000 62,845 62,85

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,4018 6,040 2,43

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,5446 12,420 6,76

62,85

9,19

72,04

24,96% 17,98

90,02

COMP29 DISJUNTOR TERMOMAGNETICO TRIPOLAR 225 A,240V, FORNECIMENTO E INSTALACAO

UN

2391 DISJUNTOR TERMOMAGNETICO TRIPOLAR 225A UN 1,0000 175,330 175,33

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,3009 6,040 1,82

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,4091 12,420 5,08

175,33

6,90

182,23

24,96% 45,48

227,71

COMP30 DISJUNTOR DR 32A 4 PÓLOS UND

DISJUNTOR DR 32A 4 PÓLOS UN 1,0000 124,641 124,64

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,6000 12,420 7,45

6113 AJUDANTE DE ELETRICISTA H 1,0231 6,620 6,77

124,64

14,22

138,86

24,96% 34,66

173,52

COMP31 DISJUNTOR DR 40A 4 PÓLOS UND

DISJUNTOR DR 40A 4 PÓLOS UN 1,0000 137,590 137,59

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,4120 12,420 5,12

6113 AJUDANTE DE ELETRICISTA H 0,3000 6,620 1,99

137,59

7,11

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

144,70

24,96% 36,12

180,82

COMP32 DISJUNTOR DR 100A 4 PÓLOS UND

DISJUNTOR DR 100A 4 PÓLOS UN 1,0000 166,292 166,29

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,4124 12,420 5,12

6113 AJUDANTE DE ELETRICISTA H 0,3000 6,620 1,99

166,29

7,11

173,40

24,96% 43,28

216,68

INSTALAÇÕES TELEFONICAS

COMP35CAIXA DE TELEFONE em chapa de aço padrão Telebrás , dimensões internas 1200 x 1200 x 150 mm

UN

14055CAIXA DE PASSAGEM N 6 PADRAO TELEBRAS DIM 120 X 120 X 12CM EM CHAPA DE

UN 1,0000 466,974 466,97

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 6,8720 12,420 85,35

6113 AJUDANTE DE ELETRICISTA H 5,0000 6,620 33,10

466,97

118,45

585,42

24,96% 146,12

731,54

COMP36 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 1" UN

1884 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 1" UN 1,0000 3,460 3,46

6113 AJUDANTE DE ELETRICISTA H 0,1287 6,620 0,85

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1221 12,420 1,52

3,46

2,37

5,83

24,96% 1,46

7,29

COMP37 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 1.1/2" UN

1870 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 1/2" UN 1,0000 1,280 1,28

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3991 12,420 4,96

6113 AJUDANTE DE ELETRICISTA H 0,3990 6,620 2,64

1,28

7,60

8,88

24,96% 2,22

11,10

COMP38 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 3" UN

1877 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 3" UN 1,0000 22,700 22,70

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,9714 12,420 12,07

6113 AJUDANTE DE ELETRICISTA H 0,9987 6,620 6,61

22,70

18,68

41,38

24,96% 10,33

51,71

COMP39 BUCHA E ARRUELA METALICA DIAM. 1" UN

855BUCHA E ARRUELA ALUMINIO FUNDIDO P/ ELETRODUTO 25MM (1'')

CJ 1,0000 1,030 1,03

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0100 12,420 0,12

6113 AJUDANTE DE ELETRICISTA H 0,0100 6,620 0,07

1,03

0,19

1,22

24,96% 0,30

1,52

COMP40 BUCHA/ARRUELA ALUMINIO 1 1/2" CJ

853BUCHA E ARRUELA ALUMINIO FUNDIDO P/ ELETRODUTO 40MM (1 1/2'')

CJ 1,0000 1,600 1,60

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0400 12,420 0,50

6113 AJUDANTE DE ELETRICISTA H 0,0400 6,620 0,26

1,60

0,76

2,36

24,96% 0,59

2,95

COMP41 BUCHA E ARRUELA METALICA DIAM. 3" UN

844BUCHA E ARRUELA ALUMINIO FUNDIDO P/ ELETRODUTO 75MM (3'')

UN 1,0000 4,750 4,75

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0100 12,420 0,12

6113 AJUDANTE DE ELETRICISTA H 0,0100 6,620 0,07

4,75

0,19

4,94

24,96% 1,23

6,17

COMP42 BLOCO TELEFONICO BLI-10 C/CANALETA UN

BLOCO TELEFONICO BLI-10 C/CANALETA UN 1,0000 3,800 3,80

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,5000 12,420 6,21

6113 AJUDANTE DE ELETRICISTA H 0,5000 6,620 3,31

3,80

9,52

13,32

24,96% 3,32

16,64 PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP43 ABRAÇADEIRO DE AÇO LAMINADO TIPO UNHA 6 UN

ABRAÇADEIRO DE AÇO LAMINADO TIPO UNHA 6 UN 1,0000 1,690 1,69

6113 AJUDANTE DE ELETRICISTA H 0,1000 6,620 0,66

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1000 12,420 1,24

1,69

1,90

3,59

24,96% 0,90

4,49

COMP44 ANEL GUIA PARA TELEFONIA UN

ANEL GUIA PARA TELEFONIA UN 1,0000 2,310 2,31

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1000 12,420 1,24

6113 AJUDANTE DE ELETRICISTA H 0,1000 6,620 0,66

2,31

1,90

4,21

24,96% 1,05

5,26

COMP45CANALETA PARA BLOCO TERMINAL DE TELEFONIAPARA CAIXA R1

UN

CANALETA PARA BLOCO TERMINAL DE TELEFONIA PARA CAIXA R1

UN 1,0000 1,530 1,53

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

1,53

19,04

20,57

24,96% 5,13

25,70

COMP46TAMPA FERRO FUNDIDO PADRAO TELEBRAS PARACAIXA R1

UN

6011 REGISTRO GAVETA 2.1/2" BRUTO LATAO REF 1502-B UN 0,0300 199,690 5,99

14112TAMPA FOFO TP R1 PADRAO TELEBRAS 385 X 630MM 25KG CARGA MAX 1500KG P/

UN 1,0000 110,810 110,81

4750 PEDREIRO H 2,0560 8,170 16,80

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 1,0000 6,040 6,04

116,80

22,84

139,64

24,96% 34,85

174,49

INSTALAÇÕES DE TV

COMP48 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 3/4" UND

1879 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 3/4" UN 1,0000 2,220 2,22

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0970 12,420 1,20

6113 AJUDANTE DE ELETRICISTA H 0,1000 6,620 0,66

PREÇO TOTAL + LS(SINAPI)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2,22

1,86

4,08

24,96% 1,02

5,10

COMP49 CURVA DE 135 GRAUS DE PVC RIGIDO DIAM. 3/4" UND

CURVA P/ ELETRODUTO PVC 3/4" UN 1,0000 1,560 1,56

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,1000 12,420 1,24

6113 AJUDANTE DE ELETRICISTA H 0,1000 6,620 0,66

1,56

1,90

3,46

24,96% 0,86

4,32

COMP50 ANTENA PARABOLICA UN

ANTENA PARABOLICA UN 1,0000 400,000 400,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 4,0000 12,420 49,68

6113 AJUDANTE DE ELETRICISTA H 4,0000 6,620 26,48

400,00

76,16

476,16

24,96% 118,85

595,01

PARA-RAIOS

COMP51 CABO DE AÇO 3/16 M

CABO DE AÇO 3/16 M 1,0500 2,050 2,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

2,15

19,04

21,19

24,96% 5,29

26,48

COMP54 SUPORTE TIPO SM 22 DIAM 2" UN

SUPORTE TIPO SM 22 DIAM 2" UN 1,0000 3,000 3,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

3,00

19,04

22,04

24,96% 5,50

27,54

COMP55SUPORTE REFORÇADO COM ROLDANA COM ROSCASOBERBA

UN

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MAO-DE-OBRA)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

7572SUPORTE ISOLADOR REFORCADO ROSCA SOBERBA EM FG C/ ISOLADOR

UN 1,0000 8,360 8,36

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0197 12,420 12,66

6113 AJUDANTE DE ELETRICISTA H 1,0013 6,620 6,63

8,36

19,29

27,65

24,96% 6,90

34,55

COMP56 SUPORTE SIMPLES COM ROLDANA UN

3396SUPORTE ISOLADOR SIMPLES ROSCA SOBERBA C/ ISOLADOR

UN 1,0000 3,530 3,53

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0091 12,420 12,53

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

3,53

19,15

22,68

24,96% 5,66

28,34

COMP57 SUPORTE DUPLO REFORÇADO COM ROLDANA UNSUPORTE ISOLADOR REFORCADO ROSCA SOBERBA EM FG C/ ISOLADOR

UN 2,0000 6,900 13,80

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

13,80

19,04

32,84

24,96% 8,20

41,04

COMP58 ESTICADOR DE CABO DE COBRE LATAO TIPO GT P23 UN

ESTICADOR DE CABO DE COBRE LATAO TIPO GT P23 UN 1,0000 2,99 2,99

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

2,99

19,04

22,03

24,96% 5,50

27,53

COMP59 ESTICADOR PARA CABO 1/4 UN

ESTICADOR PARA CABO 1/4 UN 1,0000 4,575 4,58

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

4,58

19,04

23,62

24,96% 5,90

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

29,52

COMP60 CANTONEIRA METALICA #4 100X050X50 UN

CANTONEIRA METALICA #4 100X050X50 UN 1,0000 25,630 25,63

6110 SERRALHEIRO H 1,6000 8,170 13,07

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,9000 6,040 5,44

25,63

18,51

44,14

24,96% 11,02

55,16

COMP61 CAPTOR DE LATAO CROMADO TIPO FRANKI UN

4274CAPTOR FRANKLIN 350MM, 1 DESCIDA DE CABO, LATAO NIQUELADO OU CROMADO

UN 1,0000 65,000 65,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,4610 12,420 5,73

6113 AJUDANTE DE ELETRICISTA H 0,3000 6,620 1,99

65,00

7,72

72,72

24,96% 18,15

90,87

COMP63 CONECTOR GAR BUMDY UN

1595CONECTOR DE ATERRAMENTO DE BRONZE P/ CABO 95MM2 A BARRA DE ATE 7MM2

UN 1,0000 10,680 10,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3000 12,420 3,73

6113 AJUDANTE DE ELETRICISTA H 0,3000 6,620 1,99

10,68

5,72

16,40

24,96% 4,09

20,49

COMP64 HASTE DE AÇO COBREADA 1/2" - 2450MM UN

3383 HASTE ANCORAMENTO 2400MM X 16MM (5/8") UN 1,0000 19,270 19,27

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3490 12,420 4,33

6113 AJUDANTE DE ELETRICISTA H 0,4013 6,620 2,66

19,27

6,99

26,26

24,96% 6,55

32,81

SOM

COMP65 CURVA DE 90 GRAUS DE PVC RIGIDO DIAM. 3/4" UND

1879 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 3/4" UN 1,0000 2,220 2,22

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0970 12,420 1,20

6113 AJUDANTE DE ELETRICISTA H 0,1000 6,620 0,66

PREÇO TOTAL + LS(SINAPI)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2,22

1,86

4,08

24,96% 1,02

5,10

COMP68 AUTO FALANTE TRIAXIAL 2,5RMS 8OHMS 6 UN

AUTO FALANTE TRIAXIAL UN 1,0000 212,5 212,5

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

212,50

19,04

231,54

24,96% 57,79

289,33

COMP69CAIXA DE SOM COM AMPLIFICADOR E COMPOTENCIOMETRO DE AJUSTE DE SOM

UN

CAIXA DE SOM UN 1,0000 608,000 608,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

608,00

19,04

627,04

24,96% 156,51

783,55

COMP70 MESA STANER 08 2S UN

MESA STANER UN 1,0000 690,000 690,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

690,00

19,04

709,04

24,96% 176,98

886,02

COMP71 AMPLIFICADOR STANER 200S UN

AMPLIFICADOR UN 1,0000 1.575,000 1.575,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,0000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,0000 6,620 6,62

1.575,00

19,04

1.594,04

24,96% 397,87

1.991,91

COMP74 TOMADA HEXAGONAL 2P + T - 20A - 250V UN

7531TOMADA EMBUTIR 3P 20A/250V C/PLACA, TIPO SILENTOQUE PIAL OU EQUIV

UN 1,0000 8,780 8,78

PREÇO (MAO-DE-OBRA)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

BDI (%)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3255 12,420 4,04

6113 AJUDANTE DE ELETRICISTA H 0,3214 6,620 2,13

8,78

6,17

14,95

24,96% 3,73

18,68

COMP75 TOMADA HEXAGONAL 2P + T - 20A - 250V NO PISO UNTOMADA EMBUTIR 3P 20A/250V C/PLACA, TIPO SILENTOQUE PIAL OU EQUIV

UN 1,0000 9,540 9,54

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3200 12,420 3,97

6113 AJUDANTE DE ELETRICISTA H 0,3200 6,620 2,12

9,54

6,09

15,63

24,96% 3,90

19,53

COMP76 PATCH PAINEL E HUB PARA 48 POSIÇOES UND

PATCH PANEL 48 PORTAS CAT.6 UND 1,0000 1.969,000 1.969,00

2439 ELETRICISTA INDUSTRIAL H 0,5000 24,900 12,45

242 AJUDANTE ESPECIALIZADO H 0,6378 10,330 6,59

1.969,00

19,04

1.988,04

24,96% 496,21

2.484,25

COMP77 CABO UTP-4P, CAT.5E, 24 AWG M

CABO UTP-4P, CAT.5E, 24 AWG M 1,0000 8,290 8,29

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,0650 6,040 0,39

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0650 12,420 0,81

8,29

1,20

9,49

24,96% 2,37

11,86

DADOS, VOZ E CFTV

COMP77 CABO UTP-4P, CAT.5E, 24 AWG M

CABO UTP-4P, CAT.5E, 24 AWG M 1,0000 8,290 8,29

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 0,0650 6,040 0,39

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,0650 12,420 0,81

8,29

1,20

9,49

24,96% 2,37

11,86

PREÇO TOTAL + LS(SINAPI)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP79 ELETROCALHA LEVE PERFURADA EM U 35X70X300 M

ELETROCALHA LEVE PERFURADA EM U 35X70X300 M 1,0000 30,670 30,67

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,6500 12,420 8,07

6113 AJUDANTE DE ELETRICISTA H 0,6500 6,620 4,30

30,67

12,37

43,04

24,96% 10,74

53,78

COMP82 TOMADA HEXAGONAL 2P + T - 20A - 250V UN

7531TOMADA EMBUTIR 3P 20A/250V C/PLACA, TIPO SILENTOQUE PIAL OU EQUIV

UN 1,0000 8,780 8,78

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,3265 12,420 4,06

6113 AJUDANTE DE ELETRICISTA H 0,3200 6,620 2,12

8,78

6,18

14,96

24,96% 3,73

18,69

COMPCM_121PARAFUSO, CABEÇA QUADRADA, AÇO ZINCADO,M16X250X170MM - FORN E INST

UN

432PARAFUSO M16 (ROSCA MAQUINA D=16MM) X 250MM CAB QUADRADA - ZINCAGEM A FOGO

UN 1,000 4,130 4,13

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 4,13

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 4,75

BDI (%) 24,96% 1,19

PREÇO TOTAL UNIT. (c/ taxa): 5,94

COMPCM_122PARAFUSO, CABEÇA QUADRADA, AÇO ZINCADO,M16X50X35MM - FORN E INST

UN

PARAFUSO, CABEÇA QUADRADA, AÇO ZINCADO, M16X50X35MM

UN 1,000 1,950 1,95

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 1,95

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 2,57

BDI (%) 24,96% 0,64

PREÇO TOTAL UNIT. (c/ taxa): 3,21

COMPCM_123PARAFUSO,CABEÇA ABAULADA,ACO ZINCADO,M16X150MMX 75MM - FORN E INST

UN

441PARAFUSO M16 (ROSCA MAQUINA D=16MM) X 150MM CAB QUADRADA - ZINCAGEM A FOGO

UN 1,000 2,680 2,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 2,68

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 3,30

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 0,82

PREÇO TOTAL UNIT. (c/ taxa): 4,12

COMPCM_124PARAFUSO,CABEÇA ABAULADA,ACOZINCADO,M16X70MMX 60MM - FORN E INST

UN

PARAFUSO,CABEÇA ABAULADA,ACO ZINCADO,M16X70MMX 60MM

UN 1,000 1,950 1,95

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 1,95

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 2,57

BDI (%) 24,96% 0,64

PREÇO TOTAL UNIT. (c/ taxa): 3,21

COMPCM_126PINO, ISOLADOR, PARA CRUZETA DE ACO, CLASSE15 KV, ROSCA 25 MM - FORN E INST

UN

PINO, ISOLADOR, PARA CRUZETA DE ACO, CLASSE 15 KV, ROSCA 25 MM

UN 1,000 6,600 6,60

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 6,60

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 7,22

BDI (%) 24,96% 1,80

PREÇO TOTAL UNIT. (c/ taxa): 9,02

COMPCM_127PORCA-OLHAL,ACO GALVANIZADO,ROSCA M16X2 -FORN E INST

UN

421PORCA OLHAL ACO P/ PARAFUSO C/ DIAM NOMINAL DE 16MM

UN 1,000 6,750 6,75

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 6,75

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 7,37

BDI (%) 24,96% 1,84

PREÇO TOTAL UNIT. (c/ taxa): 9,21

COMPCM_130PROTECOR PARA ESTRIBO E GRAMPO DE LINHAVIVA - FORN E INST

UN

PROTECOR PARA ESTRIBO E GRAMPO DE LINHA VIVA UN 1,000 0,850 0,85

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 0,85

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 1,47

BDI (%) 24,96% 0,37

PREÇO TOTAL UNIT. (c/ taxa): 1,84

COMPCM_131PROTETOR, EQUIPAMENTO, BUCHA, 15 KV - FORN EINST

UN

PROTETOR, EQUIPAMENTO, BUCHA, 15 KV UN 1,000 17,900 17,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 17,90

PREÇO (MAO-DE-OBRA) 0,62

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO TOTAL + LS(SINAPI) 18,52

BDI (%) 24,96% 4,62

PREÇO TOTAL UNIT. (c/ taxa): 23,14

COMPCM_132 PROTETOR, EQUIPAMENTO, PARA-RAIOS, 15 KV UN

PROTETOR, EQUIPAMENTO, PARA-RAIOS, 15 KV UN 1,000 17,900 17,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,420 1,24

PREÇO (MATERIAL) 17,90

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 19,14

BDI (%) 24,96% 4,78

PREÇO TOTAL UNIT. (c/ taxa): 23,92

COMPCM_134SAPATILHA,ACO GALVANIZADO, DIAMETRO, COLO,12MM - FORN E INST

UN

7581 SAPATILHA EM ACO GALV P/ CABOS DN ATE 5/8" UN 1,000 1,120 1,12

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 1,12

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 1,74

BDI (%) 24,96% 0,43

PREÇO TOTAL UNIT. (c/ taxa): 2,17

COMPCM_136SUPORTE "Z", CHAVE FUSÍVEL E PARA-RAIO, AÇOCARBONO, ZINCADO A QUENTE - FORN E INST

UN

SUPORTE "Z", CHAVE FUSÍVEL E PARA-RAIO, AÇO CARBONO, ZINCADO A QUENTE

UN 1,000 7,150 7,15

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 7,15

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 7,77

BDI (%) 24,96% 1,94

PREÇO TOTAL UNIT. (c/ taxa): 9,71

COMPCM_137TERMINAL COMPRESSAO CABO 50MM2 COBREESTANHADO - FORN E INST

UN

1578TERMINAL A COMPRESSAO EM COBRE ESTANHADO P/ CABO 50MM2

UN 1,000 1,570 1,57

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 1,57

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 2,19

BDI (%) 24,96% 0,55

PREÇO TOTAL UNIT. (c/ taxa): 2,74

COMPCM_138TERMINAL, COMPRESSAO, BRONZE, 50 MM2, 1 FURO,14 MM - FORN E INST

UN

1538TERMINAL A PRESSAO DE BRONZE P/ CABO A BARRA, CABO 50 A 70MM2, C/ 1 FURO DE FIXACAO

UN 1,000 3,770 3,77

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

PREÇO (MATERIAL) 3,77

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MAO-DE-OBRA) 0,62

PREÇO TOTAL + LS(SINAPI) 4,39

BDI (%) 24,96% 1,10

PREÇO TOTAL UNIT. (c/ taxa): 5,49

4.2 IMPLANTAÇÃO

COMPCM_141ABRAÇADEIRA PLÁSTICA TAMANHO GRANDE TIPOHELLMANN, PACOTE 10 UNIDADES - FORN E INST

UN

ABRAÇADEIRA PLÁSTICA TAMANHO GRANDE TIPO HELLMANN, PACOTE 10 UNIDADES

UN 1,000 120,000 120,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,420 1,24

PREÇO (MATERIAL) 120,00

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 121,24

BDI (%) 24,96% 30,26

PREÇO TOTAL UNIT. (c/ taxa): 151,50

COMPCM_142ARAME DE AÇO GALVANIZADO N.º12 BWG - FORN EINST

KG

MATCM_142 ARAME GALVANIZADO 12 BWG - 2,60MM - 48,00 G/M KG 1,000 8,670 8,67

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,420 1,24

PREÇO (MATERIAL) 8,67

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 9,91

BDI (%) 24,96% 2,47

PREÇO TOTAL UNIT. (c/ taxa): 12,38

COMPCM_076BASE PARA RELÉ FOTOELETRÔNICO 1800-1000-5A-220V - FOR E INST

UN

BASE PARA RELÉ FOTOELETRÔNICO 1800-1000-5A-220V

UN 1,000 7,500 7,50

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,040 12,420 0,50

6113 AJUDANTE DE ELETRICISTA H 0,040 6,620 0,26

PREÇO (MATERIAL) 7,50

PREÇO (MAO-DE-OBRA) 0,76

PREÇO TOTAL + LS(SINAPI) 8,26

BDI (%) 24,96% 2,06

PREÇO TOTAL UNIT. (c/ taxa): 10,32

COMPCM_053 BOX RETO ALUMINIO 4" (100MM) FORN. E INST. UN

BOX RETO ALUMINIO, 4" ( 100 MM) UN 1,000 49,240 49,24

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,060 12,420 0,75

6113 AJUDANTE DE ELETRICISTA H 0,060 6,620 0,40

PREÇO (MATERIAL) 49,24

PREÇO (MAO-DE-OBRA) 1,15

PREÇO TOTAL + LS(SINAPI) 50,39

BDI (%) 24,96% 12,58

PREÇO TOTAL UNIT. (c/ taxa): 62,97

COMP_BOX BOX RETO ALUMINIO FUNDIDO 25MM (3/4") UN

BOX RETO ALUMINIO FUNDIDO 25MM 3/4" UN 1,000 2,160 2,16

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

6115 AJUDANTE H 0,020 6,040 0,12

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,020 12,420 0,25

PREÇO (MATERIAL) 2,16

PREÇO (MAO-DE-OBRA) 0,37

PREÇO TOTAL + LS(SINAPI) 2,53

BDI (%) 24,96% 0,63

PREÇO TOTAL UNIT. (c/ taxa): 3,16

COMPCM_025 BOX RETO DE ALUMINIO 50MM UN

BOX RETO DE ALUMINIO 50MM UN 1,000 7,680 7,68

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,030 12,420 0,37

6113 AJUDANTE DE ELETRICISTA H 0,030 6,620 0,20

PREÇO (MATERIAL) 7,68

PREÇO (MAO-DE-OBRA) 0,57

PREÇO TOTAL + LS(SINAPI) 8,25

BDI (%) 24,96% 2,06

PREÇO TOTAL UNIT. (c/ taxa): 10,31

COMP_BAR4 BUCHA/ARRUELA ALUMINIO 4" CJ

845BUCHA E ARRUELA ALUMINIO FUNDIDO P/ ELETRODUTO 100MM (4'')

CJ 1,000 8,360 8,36

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,250 12,420 3,11

6113 AJUDANTE DE ELETRICISTA H 0,250 6,620 1,66

PREÇO (MATERIAL) 8,36

PREÇO (MAO-DE-OBRA) 4,77

PREÇO TOTAL + LS(SINAPI) 13,13

BDI (%) 24,96% 3,28

PREÇO TOTAL UNIT. (c/ taxa): 16,41

COMP_BAR2 BUCHA/ARRUELA ALUMINIO 2" UN

843BUCHA E ARRUELA ALUMINIO FUNDIDO P/ ELETRODUTO 50MM (2'')

CJ 1,000 2,290 2,29

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,067 12,420 0,83

6113 AJUDANTE DE ELETRICISTA H 0,060 6,620 0,40

PREÇO (MATERIAL) 2,29

PREÇO (MAO-DE-OBRA) 1,23

PREÇO TOTAL + LS(SINAPI) 3,52

BDI (%) 24,96% 0,88

PREÇO TOTAL UNIT. (c/ taxa): 4,40

COMPCM_155CABO DE COBRE ISOLACAO COMPOSTOTERMOPLASTICO 0,6/1KV, TIPO PP, 3x2,5MM2 - FORNE INST

M

CABO DE COBRE ISOLACAO COMPOSTO TERMOPLASTICO 0,6/1KV, TIPO PP, 3x2,5MM2

M 1,000 3,700 3,70

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

6113 AJUDANTE DE ELETRICISTA H 0,050 6,620 0,33

PREÇO (MATERIAL) 3,70

PREÇO (MAO-DE-OBRA) 0,95

PREÇO TOTAL + LS(SINAPI) 4,65

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 1,16

PREÇO TOTAL UNIT. (c/ taxa): 5,81

COMPCM_159CURVA 90º PVC RÍGIDO, 100MM, COM LUVAS, TIGREOU EQUIVALENTE - FORN E INST

UN

1878 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 4" UN 1,000 42,630 42,63

1895 LUVA PVC ROSCAVEL P/ ELETRODUTO 4'' UN 1,000 34,900 34,90

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,200 12,420 14,90

6113 AJUDANTE DE ELETRICISTA H 1,200 6,620 7,94

PREÇO (MATERIAL) 77,53

PREÇO (MAO-DE-OBRA) 22,84

PREÇO TOTAL + LS(SINAPI) 100,37

BDI (%) 24,96% 25,05

PREÇO TOTAL UNIT. (c/ taxa): 125,42

COMPCM_160CURVA 90º PVC RÍGIDO, 25MM, COM LUVAS, TIGREOU EQUIVALENTE - FORN E INST

UN

1884 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 1" UN 1,000 3,360 3,36

1892 LUVA PVC ROSCAVEL P/ ELETRODUTO 1" UN 1,000 1,600 1,60

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,210 12,420 2,61

6113 AJUDANTE DE ELETRICISTA H 0,210 6,620 1,39

PREÇO (MATERIAL) 4,96

PREÇO (MAO-DE-OBRA) 4,00

PREÇO TOTAL + LS(SINAPI) 8,96

BDI (%) 24,96% 2,24

PREÇO TOTAL UNIT. (c/ taxa): 11,20

COMPCM_161CURVA 90º PVC RÍGIDO, 50MM, COM LUVAS, TIGREOU EQUIVALENTE - FORN E INST

UN

1876 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 2" UN 1,000 7,810 7,81

1894 LUVA PVC ROSCAVEL P/ ELETRODUTO 2'' UN 1,000 5,420 5,42

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,118 12,420 1,47

6113 AJUDANTE DE ELETRICISTA H 0,200 6,620 1,32

PREÇO (MATERIAL) 13,23

PREÇO (MAO-DE-OBRA) 2,79

PREÇO TOTAL + LS(SINAPI) 16,02

BDI (%) 24,96% 4,00

PREÇO TOTAL UNIT. (c/ taxa): 20,02

COMPCM_162CURVA DE AÇO GALVANIZADO, PESADO, Ø100MM(Ø4") , 90°, RAIO LONGO, COM LUVAS - FORN E INST

UN

2621CURVA 90G FERRO GALV ELETROLITICO 4" P/ ELETRODUTO

UN 1,000 32,560 32,56

2641 LUVA FERRO GALV ELETROLITICO 4" P/ ELETRODUTO UN 1,000 8,750 8,75

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,200 12,420 14,90

6113 AJUDANTE DE ELETRICISTA H 1,200 6,620 7,94

PREÇO (MATERIAL) 41,31

PREÇO (MAO-DE-OBRA) 22,84

PREÇO TOTAL + LS(SINAPI) 64,15

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

BDI (%) 24,96% 16,01

PREÇO TOTAL UNIT. (c/ taxa): 80,16

COMPCM_184ELETRODUTO DE AÇO GALVANIZADO, PESADO,Ø50MM (Ø2") , 6M, COM LUVAS. - FORN E INST

UN

21134ELETRODUTO FERRO GALV OU ZINCADO ELETROLIT SEMI-PESADO 2" NBR 13057

UN 1,000 10,230 10,23

3912 LUVA FERRO GALV ROSCA 2" UN 1,000 17,530 17,53

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,000 12,420 12,42

6113 AJUDANTE DE ELETRICISTA H 1,000 6,620 6,62

PREÇO (MATERIAL) 27,76

PREÇO (MAO-DE-OBRA) 19,04

PREÇO TOTAL + LS(SINAPI) 46,80

BDI (%) 24,96% 11,68

PREÇO TOTAL UNIT. (c/ taxa): 58,48

COMPCM_185ELETRODUTO PEAD, 32MM COM LUVAS, KANAFLEXOU EQUIVALENTE - FORN E INST

M

2690 ELETRODUTO PVC FLEXIVEL CORRUGADO 32MM TIPO TIGREFLEX OU EQUIVM 1,000 2,500 2,50

1900 LUVA PVC DE PRESSAO P/ ELETRODUTO TIGREFLEX 32 UN 1,000 1,260 1,26

2436 PAREDE, P/LIGAÇÃO PREDIAL DE AGUA H 0,150 12,420 1,86

6113 AJUDANTE DE ELETRICISTA H 0,150 6,620 0,99

PREÇO (MATERIAL) 2,50

PREÇO (MAO-DE-OBRA) 2,85

PREÇO TOTAL + LS(SINAPI) 5,35

BDI (%) 24,96% 1,34

PREÇO TOTAL UNIT. (c/ taxa): 6,69

COMPCM_027ELETRODUTO PEAD, 50MM, COM LUVAS, KANAFLEXOU EQUIVALENTE

M

2446 ELETRODUTO 2" TIPO KANALEX OU EQUIV M 1,050 7,660 8,04

1900LUVA PVC DE PRESSAO P/ ELETRODUTO TIGREFLEX 32

UN 1,000 1,260 1,26

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,150 12,420 1,86

6113 AJUDANTE DE ELETRICISTA H 0,150 6,620 0,99

PREÇO (MATERIAL) 8,04

PREÇO (MAO-DE-OBRA) 2,85

PREÇO TOTAL + LS(SINAPI) 10,89

BDI (%) 24,96% 2,72

PREÇO TOTAL UNIT. (c/ taxa): 13,61

COMP_TAMPTAMPAO FF P/CX R1 PADRAO TELEBRAS ASSENTC/ARG CIM/AREIA 1:4.

UN

14112TAMPA FOFO TP R1 PADRAO TELEBRAS 385 X 630MM 25KG CARGA MAX 1500KG P/ CAIXA TELEFONE

UN 1,000 110,810 110,81

13891BETONEIRA 320 LITROS, SEM CARREGADOR, MOTOR A GASOLINA

UN 0,012 5.199,340 62,39

4229 GRAXA KG 0,003 11,200 0,03

4227ÓLEO LUBRIFICANTE PARA MOTORES DE EQUIPAMENTOS PESADOS (CAMINHÕES, TRATORES, RETROS E ETC...)

L 0,001 9,350 0,01

4222 GASOLINA COMUM L 0,044 3,900 0,17

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

1379 CIMENTO PORTLAND COMUM CP I- 32 KG 16,965 0,730 12,38

367 AREIA GROSSA M3 0,057 47,120 2,69

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 1,625 6,040 9,82

4750 PEDREIRO H 1,500 8,170 12,26

4230 OPERADOR DE MAQUINAS E EQUIPAMENTOS H 0,029 13,290 0,39

PREÇO (MATERIAL) 188,48

PREÇO (MAO-DE-OBRA) 22,47

PREÇO TOTAL + LS(SINAPI) 210,95

BDI (%) 24,96% 52,65

PREÇO TOTAL UNIT. (c/ taxa): 263,60

4.4SISTEMA DE PROTEÇÃO CONTRA DESCARGAS ATMOSFÉRICAS-SPDA

COMPCM_034 CADINHO CABO HASTE 50MM X 5/8" UN

CADINHO CABO HASTE 50MM X 5/8" UN 1,000 149,000 149,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,050 12,420 0,62

6113 AJUDANTE DE ELETRICISTA H 0,050 6,620 0,33

PREÇO (MATERIAL) 149,00

PREÇO (MAO-DE-OBRA) 0,95

PREÇO TOTAL + LS(SINAPI) 149,95

BDI (%) 24,96% 37,43

PREÇO TOTAL UNIT. (c/ taxa): 187,38

COMPCM_035CADINHO PARA SOLDA EXOTÉRMICA TIPOCABO/CABO 35MM² , TIPO "X"

UN

CADINHO PARA SOLDA EXOTÉRMICA TIPO CABO/CABO 35MM² , TIPO "X"

UN 1,000 178,000 178,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,420 1,24

PREÇO (MATERIAL) 178,00

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 179,24

BDI (%) 24,96% 44,74

PREÇO TOTAL UNIT. (c/ taxa): 223,98

COMPCM_036CADINHO PARA SOLDA EXOTÉRMICA TIPOCABO/CABO 35MM², TIPO "T"

UN

CADINHO PARA SOLDA EXOTÉRMICA TIPO CABO/CABO 35MM², TIPO "T"

UN 1,000 198,000 198,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,100 12,420 1,24

PREÇO (MATERIAL) 198,00

PREÇO (MAO-DE-OBRA) 1,24

PREÇO TOTAL + LS(SINAPI) 199,24

BDI (%) 24,96% 49,73

PREÇO TOTAL UNIT. (c/ taxa): 248,97

COMPCM_037CAIXA DE INSPEÇÃO DE ATERRAMENTO TIPO SOLOEM PVC Ø40X50CM C/ TAMPA DE FERRO FUNDIDO

UN

CAIXA DE INSPEÇÃO DE ATERRAMENTO TIPO SOLO EM PVC Ø40X50CM C/ TAMPA DE FERRO FUNDIDO

UN 1,000 260,000 260,00

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,010 12,420 0,12

6113 AJUDANTE DE ELETRICISTA H 0,100 6,620 0,66

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

PREÇO (MATERIAL) 260,00

PREÇO (MAO-DE-OBRA) 0,78

PREÇO TOTAL + LS(SINAPI) 260,78

BDI (%) 24,96% 65,09

PREÇO TOTAL UNIT. (c/ taxa): 325,87

COMPCM_160CURVA 90º PVC RÍGIDO, 25MM, COM LUVAS, TIGREOU EQUIVALENTE - FORN E INST

UN

1884 CURVA PVC 90G P/ ELETRODUTO ROSCAVEL 1" UN 1,000 3,360 3,36

1892 LUVA PVC ROSCAVEL P/ ELETRODUTO 1" UN 1,000 1,600 1,60

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 0,260 12,420 3,23

6113 AJUDANTE DE ELETRICISTA H 0,275 6,620 1,82

PREÇO (MATERIAL) 4,96

PREÇO (MAO-DE-OBRA) 5,05

PREÇO TOTAL + LS(SINAPI) 10,01

BDI (%) 24,96% 2,50

PREÇO TOTAL UNIT. (c/ taxa): 12,51

COMPCM_169ELETRODUTO PEAD, ARAME GUIA, 25MM COMLUVAS, KANAFLEX OU EQUIVALENTE

M

2688ELETRODUTO PVC FLEXIVEL CORRUGADO 25MM TIPO TIGREFLEX OU EQUIV

M 1,000 46,164 46,16

1899LUVA PVC DE PRESSAO P/ ELETRODUTO TIGREFLEX 25

UN 1,000 0,800 0,80

342 ARAME GALVANIZADO 12 BWG - 2,60MM - 48,00 G/M KG 8,670 0,200 1,73

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 2,000 12,420 24,84

6113 AJUDANTE DE ELETRICISTA H 2,000 6,620 13,24

PREÇO (MATERIAL) 48,69

PREÇO (MAO-DE-OBRA) 38,08

PREÇO TOTAL + LS(SINAPI) 86,77

BDI (%) 24,96% 21,66

PREÇO TOTAL UNIT. (c/ taxa): 108,43

COMPCM_171ESCAVAÇÃO MANUAL DE VALAS CAIXAS EREATERRO

M3

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 6,250 6,040 37,75

PREÇO (MATERIAL) -

PREÇO (MAO-DE-OBRA) 37,75

PREÇO TOTAL + LS(SINAPI) 37,75

BDI (%) 24,96% 9,42

PREÇO TOTAL UNIT. (c/ taxa): 47,17

COMPCM_043 PÓ DE SOLDA EXOTÉRMICO Nº90 UN

PÓ DE SOLDA EXOTÉRMICO Nº90 UN 1,000 8,550 8,55

2436 ELETRICISTA OU OFICIAL ELETRICISTA H 1,000 12,420 12,42

PREÇO (MATERIAL) 8,55

PREÇO (MAO-DE-OBRA) 12,42

PREÇO TOTAL + LS(SINAPI) 20,97

BDI (%) 24,96% 5,23

PREÇO TOTAL UNIT. (c/ taxa): 26,20

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

INSTALAÇÕES HIDRAULICAS/SANITARIAS/ PLUVIAIS

COMP116TAMPA QUADRADA FOFO C/ BASE 600 X 600MMCARGA MAX 2000KG P/ CAIXA INSPECAO, ESGOTO,AGUA,ELETRICA ETC

UN

1379 CIMENTO PORTLAND COMUM CP I- 32 KG 1,1310 0,700 0,79

367 AREIA GROSSA M3 0,0008 48,120 0,04

21072TAMPA QUADRADA FOFO C/ BASE 600 X 600MM CARGA MAX 2000KG P/ CAIXA INSPECAO, ESGOTO, AGUA,ELETRICA ETC

UN 1,0000 172,520 172,52

6111 SERVENTE OU OPERARIO NAO QUALIFICADO H 1,0000 6,040 6,04

4750 PEDREIRO H 1,0000 8,170 8,17

4230 OPERADOR DE MAQUINAS E EQUIPAMENTOS H 0,0087 13,290 0,12

173,35

14,33

187,68

24,96% 46,84

234,52

COMP117 CAIXA D'AUGA TUBULAR METALICA 60.000M3 M

CAIXA D'AUGA TUBULAR METALICA 60.000M3 UN 1,0000 121.814,000 121.814,00

121.814,00

-

121.814,00

24,96% 30.404,77

152.218,77

COMP_TB6 TUBO CONCRETO ARMADO CA-1 DN-600MM M3

7762TUBO CONCRETO ARMADO CLASSE PA-2 PB NBR-8890/2007 DN 600 MM PARA ÁGUAS PLUVIAIS

M 1,0000 154,830 154,83

73879/004ASSENTAMENTO DE TUBO DE CONCRETO DIAMETRO 600 MM, JUNTAS COM ANEL DE BORRACHA, MONTAGEM COM AUXÍLIO DE EQUIPAMENTOS

M 1,0000 37,860 37,86

154,83

37,86

192,69

24,96% 48,10

240,79

COMP_TB8 TUBO CONCRETO ARMADO CA-1 DN-800MM M3

7763TUBO CONCRETO ARMADO CLASSE PA-2 PB NBR-8890/2007 DN 800 MM PARA ÁGUAS PLUVIAIS

M 1,0000 235,660 235,66

73879/006ASSENTAMENTO DE TUBO DE CONCRETO DIAMETRO 800 MM, JUNTAS COM ANEL DE BORRACHA, MONTAGEM COM AUXÍLIO DE EQUIPAMENTOS

M 1,0000 61,260 61,26

235,66

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

61,26

296,92

24,96% 74,11

371,03

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP_TE TAXAS E EMOLUMENTOS UN

001 ART DE EXECUÇÃO TX 1,000 158,08 158,08

002 ART DO POÇO TX 1,000 158,08 158,08

003 ART ETE TX 1,000 158,08 158,08

004 ART CONSULTORIA TX 1,000 60,00 60,00

005 ART'S (FONTE: CREA-AM) TX 1,000 158,08 158,08

006 ALVARÁ DE CONSTRUÇÃO (3.240,70 m2) TX 1,000 6.319,37 3.954,75

007 HABITE-SE TX 1,000 6.319,37 3.954,75

008 ELETROBRÁS - AMAZONAS ENERGIA TX 1,000 158,08 158,08

PREÇO (MATERIAL) 8.759,90

PREÇO TOTAL + LS(SINAPI) 8.759,90

BDI (%) 24,96% 2.186,47

PREÇO TOTAL UNIT. (c/ taxa): 10.946,37

COMP_LP LIMPEZA PERMANENTE DA OBRA MÊS

6111 SERVENTE H 192,0008 6,040 1.159,68

1.159,68

-

1.159,68

24,96% 289,46

1.449,14

COMP_TRAFOINSTALAÇÃO DE TRANSFORMADOR DE 500 KVA ASECO

CJ

MERCADOTRANSFORMADOR DE DISTRIBUIÇÃO DE 500 KVA A SECO, 13,8 KV/220/127 V, REGULAÇÃO DE 600 EM 600 V

UND 1,0000 29.488,000 29.488,00

00002436 ELETRICISTA OU OFICIAL ELETRICISTA H 16,0000 12,420 198,72

00006113 AJUDANTE DE ELETRICISTA H 32,0000 6,620 211,84

29.488,00

410,56

29.898,56

24,96% 7.462,68

37.361,24

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

OBRA: Construção do Campus Itacoatiara

Endereço: Rod. AM-010, km 08, s/n - Itacoatiara/AM.

COMPOSIÇÕES UNITÁRIAS

LEIS SOCIAIS0:85,34%

DATA BASE: ABRIL/2013

CODIGO DESCRIÇÃO UN COEF. P. UNIT. P. TOTAL

COMP_MD MOBILIZAÇÃO/DESMOBILIZAÇÃO DA OBRA CJ

73875/001TRANSPORTE, MOBILIZAÇÃO E DESMOBILIZAÇÃO DE MATERIAIS E EQUIPAMENTOS

TON 1,0000 50,000 50,00

73875/001LOCACAO DE ANDAIME METALICO TUBULAR TIPO TORRE

M/MES 50,0000 12,760 638,00

00020193ANDAIME METALICO TIPO FACHADEIRO LARG=1,20M ALTURA = 2,0M

M2/MES 49,0000 2,570 125,93

00006111 SERVENTE H 0,6770 6,040 4,09

813,93

4,09

818,02

24,96% 204,18

1.022,20

PREÇO (MATERIAL)

PREÇO (MAO-DE-OBRA)

PREÇO TOTAL + LS(SINAPI)

BDI (%)

PREÇO TOTAL UNIT. (c/ taxa):