7/29/2019 COC 133 45 Timeline
1/4
COC No. 45
Location: Bislig, Surigao del Sur
Total
J F M A
A. Regulatory/Administrative
Salaries
Consultancy fees & expenses
Travel expenses
Fuel
Cost Sub-total (Php) 14,241,507.23
B. Social/Community
Medical Mission/Outreach
Community Christmas Party
NCIP/FPIC consultations
MMT meetings
Peace & order consultation meetings
Community representation
Cost Sub-total (Php) 1,526,904.47
C. Technical
Geologic mappingDrilling Contract
Test pitting/ trenching
Topographic survey
Data encoding
Crop damages
Cost Sub-total (Php) 3,425,800.05
D. Infrastructure
Coal washing plant
Coal laboratoryBase Camp rehabilitation
Road rehabilitation/repair
Cost Sub-total (Php) 14,816,825.07
E. COC Acquisition Cost
Paid portion of liability to DOE on COC
Cost Sub-total (Php) 6,144,053.51
TOTAL
Note: MGMEC to continue paying balance of DMC-CERI liabilities (Php 4M) to DOE upon conversion of COC to DP.
40,155,090.33 GRAND TOTAL5,377,378.80 23,201,905.99 11,575,805.54
8,530,767.75 5,758,434.52
3,000,000.00 2,912,702.34 231,351.17
527,622.80
370,428.00
5,431,839.08
47,576.47
106,604.30
Q4 Q1 Q2
7,330,340.15
1,479,328.00
2,948,767.75
Q1 Q2 Q3 Q4
1,479,328.00
2005 2006 2007 2008
ACCOMPLISHMENTS Q1 Q2 Q3 Q3Q4
Continuation of exploration drillingprogram for Sicahoy-Bongkayao area.Cost: Php 3.4M
-
7/29/2019 COC 133 45 Timeline
2/4
COC 45 (Bislig, Surigao del Sur)
Timeline of Activities
Activity Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb
1. Deed of Assignment from DMC-CERI to MGMEC (June 6,
2005)
2. DOE approval of Deed of Assignment for COC 45 (July 7,
2005)
3. Turnover of geologic data from DMC-CERI
4. Commencement of confirmatory detailed surface geologic
mapping with test pitting & trenching in
Sicahoy_Bongkayao area (COC 45)
5. Detailed section and sampling of coal outcrops inclg.trenches & test pits
6. Topographic survey of Bongkayao area
7. Re-mapping and rehabilitation of old DMC-CERI test pits &
trenches for sampling
8. Relocation of DMC-CERI drillholes
9. Collation of DMC-CERI & MGMEC data for interpretation
and reserve evaluation
10. Report preparation
11. Submission of "Coal Reseve Evaluation Report" to DOE
12. Mobilization of drilling machines from CDSI for reserveverification and additional coal resource delineation.
13. Implementation of drilling program for Sicahoy-Bongkayao
area
Ex loration Ex enditures1. Deed of Assignment from DMC-CERI to MGMEC
2. Geologic mapping and trenching/test pitting
3. Topographic survey of Bongkayao area
4. Report preparation
5. Mobilization of drilling machines from CDSI for reserveverification and additional coal resource delineation.
6. Implementation of drilling program for Sicahoy-Bongkayao
area
2005 2006 2007 2008
-
7/29/2019 COC 133 45 Timeline
3/4
COC No. 133
Location: Argao, Cebu
TotalJ F M A
A. Regulatory/Administrative
Salaries
Consultancy fees & expenses
Travel expenses
Service vehicle rental
Lodging
Per diem allowances
Communication
Utility services
Fuel
Cost Sub-total (Php)
B. Social/Community
PAMB consultations
Permits (DENR/EMB, NCIP, LGU, etc.)
Consultation meetings with local politicians & community
Small-scale miners coordination meetings
Cost Sub-total (Php)
C. Technical
Geologic mapping (surface & underground)
Drilling Contract
Data encoding
Crop damages
Sample analysis
Small-scale monitoring
Report preparation
Cost Sub-total (Php)
TOTAL
Note: MGMEC pay LUVIMIN liabilities (Php 7M) to DOE upon conversion of COC to DP.
8,570,748.13 GRAND TOTAL
289,133.003,644,026.32
Q2
3,764,011.81 4,335,296.32 471,440.00
30,701.24
740,855.52
Q3 Q4
2,992,455.05 182,307.00
Q2 Q3 Q4 Q1
691,270.00
2008ACCOMPLISHMENTS
2005 2006 2007Q1 Q2 Q3 Q4 Q1
Implementation of exploration drillingand aditting program.
Cost:Drilling-Php 4.7MAditting-Php 18M.
COC expired due to evaluation ofMGMEC extension.
-
7/29/2019 COC 133 45 Timeline
4/4
COC 133 (Argao, Cebu)Timeline of Activities
Activity Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
1. Granting of COC to MGMEC
2. Mobilization of exploration personnel
3. Conduct of surface and underground geologic mapping
4. Mobilization of drilling equipment
5. Commencement of exploration drilling
6. Secure Certificate of Non-Coverage (EMB) - Nov. 30, 2005
7.Certification from NCIP
8. Issuance of manifesto to DOE by CBRMP on Argao watershed
(Aug. 8, 2006)
9. MGMEC received letter from DOE on CBRMP manifesto (Aug. 30,
2006)
10. Mobilization of consultant (S.F. Declaro)
11. PAMB Council meeting (Feb. 22, 2006)
12. First meeting with of FVL, RRL and RBB with Cong. S. Kintanar
and Mayor W. Caminero (Cebu)
13. Completion of surface geologic mapping and initial drilling
14. Preparation initial geologic assessment report
15. Mobilization of admininstrative personnel for inventory of mineworkings.
16. Meeting of RRL with Mayor Caminero on proposed joint venture
area (MG office)
17. Submission of Geologic Evaluation Report for COC 133 with
proposed supplemental exploration program
18. Evaluation by DOE of extension request for COC 133
19. Granting of extension for COC 133 (Feb, 22, 2007)
20. Transmittal by DOE and receipt of extension notice by MGMEC
(April 16)
21. Meeting with Cong. Kintanar and Mayor Caminero at Usec. Balce's
office (DOE)
22. Meeting of F. Lorilla with Mayor Caminero for marketing
agreement (Cebu)
23. Negotiation with Mayor Caminero & cong. Kintanar on coal
purchase terms & JV area agreement conditions
24. Implementation of supplemental geologic works by I.H. Francisco
(Consultant) - updating of underground mine data
25. Preparation of geologic report with reserve computation
26. Submission of Geologic Assessment Report to DOE for
conversion to D/P or extension exploration period
27. Preliminary talks with SINIAN International Inc. (SII) for explorationcontract
28. Solicitation of drilling proposals from contractors
29. Final negotiation with drilling contractor (MEGA Phils.)
Exploration ExpendituresPreliminary exploration
Initial drilling (CDSI)
Administrative expenses
Supplemental exploration mapping (I.H. Francisco)
2005 2006 2007