CÁLCULO DO TRAÇO DE CONCRETO P/ (1 m3)TRAÇO
CIMENTO AREIA BRITA ÁGUA
1 : 4 : 6 : 0.6MASSA UNITÁRIA (DEFINIDA) 1.42 1.50 1.40 1.00PESO ESPECÍFICO (DEFINIDA) 3.15 2.63 2.90 1.00
UMIDADE CRITICA DA AREIA KG/L 3 % L = LITROS Vs= VOLUME SECO
Kg = MASSA Vc= VOLUME ÚMIDO
COEF. DE INCHAMENTO DA AREIA 30 % RP= RESPOSTA PARCIAL Ms= MASSA SECARF= RESPOSTA FINAL Mu= MASSA ÚMIDA
1 SACO DE CIMENTO 50 Kg 1 LATA 18 LNÃO ALTERAR INSERIR DADOSRESULTADOS
1.1 CÁLCULO DOS VOLUMES DOS MATERIAS (SECO)
AREIA 4 RP= 2.67 L x 50 RF= 133.3 L1.50
BRITA 6 RP= 4.29 L x 50 RF= 214 L1.40
ÁGUA 0.6 RP= 0.60 L x 50 RF= 30 L1.00
1.2 CÁLCULO DA MASSSA DOS MATERIAS (SECO)
50 Kg
4 X 50 RF= 200.00 Kg
6 X 50 RF= 300.00 Kg
ÁGUA 30.00 L
1.3 CÁLCULO DO VOLUME DA AREIA (ÚMIDO)
133.33 L
133.33 + 133.33 x 30 %133.33 + 40.00
173.33 L
1.4 CÁLCULO DA MASSA DA AREIA (ÚMIDO)
200.00 L
200.00 + 200.00 x 3 %200.00 + 6.00
206.00 L
1.5 CÁLCULO DO EXCESSO DE ÁGUA NA AREIA (ÚMIDO)
206.00 - 200.00
VOLUME DE ÁGUA NA AREIA RF= 6.00 Kg ou L
1.5.1 RESUMOMASSA VOLUME LATAS POR LATAS POR
(Kg) (L) (Kg) (L)CIMENTO 50.00 - - -AREIA 206.00 173.33 11.4 9.6BRITA 300.00 214.29 16.7 11.9ÁGUA - 24.00 - 1.3
1.6 CÁLCULO DO TRAÇO EM MASSA C/ AREIA ÚMIDA (Kg)
50 206 300 24.0050 50 50 50
CIMENTO AREIA BRITA ÁGUATRAÇO C/ AREIA ÚMIDA (Kg) 1 : 4.12 : 6 : 0.48
1.7 CÁLCULO DO TRAÇO MISTO EM VOLUME C/ AREIA ÚMIDA (L)
50 173 214 24.0050 50 50 50
CIMENTO AREIA BRITA ÁGUATRAÇO MISTO C/ AREIA ÚMIDA (L) 1 : 3.47 : 4.29 : 0.48
1.8 CÁLCULO DO CONSUMO DE CIMENTO (m3)
C= 10001 + 4 + 6 + 0.60
PESO ESPECÍFICO 3.15 2.63 2.90 1.00CIMENTO AREIA BRITA ÁGUA
C= 10000.32 + 1.52 + 2.07 + 0.60
C= 10004.51
CIMENTO (Ms)
AREIA (Ms)
BRITA (Ms)
AREIA (Vs)
VOLUME ÚMIDO (VH)
VOLUME ÚMIDO (VH) RF=
AREIA (Ms)
VOLUME ÚMIDO (Mu)
VOLUME ÚMIDO (Mu) RF=
AREIA (Mu) - AREIA (Ms) = Ag
CIMENTO C= 222 Kg
CIMENTO POR SACOS 4 Und.
1.9 CÁLCULO DO CONSUMO DE MATERIAS EM (Kg )
AREIA 4.12 X 222 RF= 914 Kg
BRITA 6 X 222 RF= 1,331 Kg
1.10 CÁLCULO DO CONSUMO DE MATERIAS EM (L)
AREIA 3.47 X 222 RF= 769 L
BRITA 4.29 X 222 RF= 951 L
1.11 CÁLCULO DE ÁGUA EM (L)
ÁGUA 0.48 X 222 RF= 106 L
1.12 CÁLCULO DO MATERIAL PARA A OBRA
1 L 0.001 m3
QUANTITATIVO P/ 1.00 m3
AREIA 1m3 769.12 RP= 0.77 m3 RF= 0.77 m3
BRITA 1m3 950.83 RP= 0.95 m3 RF= 0.95 m3
CIMENTO (SACO 50Kg) 4 RP= 4 SACOS RF= 4 SACOS
1.13 CÁLCULO DO GASTO EM ($R)
VALORES DE 1m3 (PESQUISAR NO DISTRIBUIDOR)
AREIA 1m3 R$ 60.00 TOTAL DE GASTO R$ 265.79
BRITA 1m3 Nº1 R$ 105.00CIMENTO (SACO 50Kg) R$ 27.00
AREIA 0.77 m3 TOTAL AREIA R$ 46.15
BRITA 0.95 m3 TOTAL BRITA R$ 99.84
CIMENTO 4 SACOS TOTAL CIMENTO R$ 119.80
AUTOR : OBERTO ADAMASTOR DA SILVA NETO - TÉCNICO EM EDIFICAÇÕES - CEPEP-SALVADOR 05/02/2014 R-01